Information
-
Job # / Job Name
-
Conducted on
-
Prepared by
-
Location
-
Document No.
Quality Control Item
Heads and bed joints inspection
-
Head joint size within tolerance? (+- 1/8”)
-
Bed joints size within tolerance? (+- 1/8”)
-
All head joints full?
-
All bed joints full?
-
Less than full joints pointed in?
-
Wire fully in bed joint?
-
Sled runners are being used?
Plumpness of walls inspection
-
Walls within tolerance?
Customer Contact
-
My signature acknowledges that I have walked this job and have found all workmanship to be of professional quality
-
Foreman's Signature & Date
-
Rebar & grout inspection
-
Dowels in correct spacing within cell?
-
Dowels match reinforcing schedule? Ie., every 4th cell for 32” OC?
-
Rebar positioners are being used?
-
Rebar placed correctly prior to grout?
-
Grout is consolidated?