Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Project name
-
Location
-
EED Inspector name
Work area set up
-
Silica signs posted
-
Silica red work area tape at entrance to the area
-
Silica HEPA vacuums being used
-
Power tools with factory attached HEPA vacuums being used
-
Sewer and track drains have been sealed
-
What environmental dust controls are being used: water spraying with additives
-
OSS approval letter for the product on site
-
List how the contractor workers are using adequate water supply to keep dust down. List all that apply
-
How’s the contractor collection spent water
-
Has the contractor tested the water prior to disposal
Observation Log
-
Work area:
-
Contract number
-
General Contractor
-
Contractor schedule sent to EED
-
Environmental Consultant
-
NYCT Contractors approved work plan is on site
-
Has baseline sampling been performed as per work plan
-
Explain why not
-
Has the contractor conducted personal air monitoring on the first day of each job activity on the site
-
Were the sample results forwarded to EED
-
Safety engineer on site (Name)
-
Has the safety engineer conducted a daily Safety meeting for all workers on site
-
Contractor defiency
-
Explain why and when
-
Corrective action taken
-
Corrective action closed
-
Contractor PPE on site
-
Contractor equipment on site