Title Page
-
Prepared by
-
Serial Number
-
Date
MWD Disassembly
-
Place DHP into torque machine.
-
Break all torqued connections, UPU to Collar, MVS to UPU, and any others if applicable.
-
Remove tool from Torque Machine and place on proper disassembly stands.
-
Secure UPA and Unthread from Monel.
-
Pull UPA with attached string from Monel until first probe string connection with UPA is visable.
-
Break connection between SNT and UPA by placing parmalee on SNT sleeve, use backup parmalee on SNT housing if needed.
-
-
Move UPA to designated disassembly area.
-
Pull probe string from collar.
-
Move Collar to appropriate area for maintenance.
-
Move Collar to appropriate area for maintenance.
-
Verify caps are covering exposed lemo connections.
-
Using pressure washer, spray all invert and debris from probe string.
Probe String Maintenace.
-
Connect the tool to the test equipment. Power tool up through the lower module.
-
Start ToolManager.
-
Select Navi probes shop in the FILENAME drop down menu.
-
Click on LOAD and then CONNECT
-
Check if all nodes are green.
-
Select MEM tab.
-
Click on the Synchronize Time button. Then click the Yes
-
select the directory within in which the memorey files will be stored.
-
click on the Dump Memory button.