Title Page
-
Site conducted
-
Penthouse
-
Conducted on
-
Prepared by
-
Drawings Used
Room included
-
Secondary Master
-
Secondary master bathroom
-
Guest 1
-
Guest 1 Bathroom
-
Guest 2
-
Guest 2 Bathroom
-
Cinema room
-
Guest 3
-
Guest 3 Bathroom
-
FCUs
-
FCU Filter can be removed and taken through access panel
-
Return Air Path Builders work hole correct size
-
FCU Labelled Correctly and visible from access panel
-
Control Panel cover installed
-
Frese Valves left in bypass
-
Secondary ductwork Supported correctly
-
Secondary ductwork lagged with correct IDs and no damage
-
Flexible Connection, sound & free from damage.
-
Plenums set to finished ceiling height.
-
Plenums lagged & free from damage
-
Open end filter protection removed
-
Condense correctly lagged and labelled (1m)
-
Condense hose connected with hose clips & free from kinks
-
FCU Drip Tray clean & Free from damage
NOX Filer
-
Filters can be removed through access panel
MVHR Ductwork
-
Ductwork supported correctly
-
Joints secure & tapped
-
Flexible Connections, sound & free from damage.
-
Extract grilles installed to RCP
-
Supply Air Plenums set to finished ceiling height
-
Ducting connected to MVHR correct handing, (extract & supply checked)
-
VCDs Installed correctly & supported with Chocs
-
VCDs are accessible and left in open position
-
Attenuators supported correctly
-
Ductwork sealed to attenuators
-
Ductwork insulation free from rips & tears
-
IDs installed correctly
-
Fire sleeves have been installed correctly
-
MVHR duct wrapped to the first attenuator
Kitchen Extract & Supply air
-
Extract flex installed to kitchen layout drawing
-
Supply air grille installed to RCP
-
Supply air Filter within access panel.
-
Supply air VCD accessible
-
Extract & supply air supported correctly
-
Insulation free from rips & tears
PIB
-
Return Air paths back to FCUs correct sized
-
Pattress installed for Extract Grilles
-
Patresses have been installed for return air grilles
-
No air leakage between rooms
-
Extract grilles cut out
Pipework
-
Shower head Backplate elbow installed to SOP & RCP
-
Backplate elbow installed square (pattress checked)
-
Pipework clipped parallel & Level
-
Pipework spacing so no lagging is touching other services
-
Pipework heights clear of lighting coffers
-
Clips screwed & secured correctly
-
Condense pipe clipped at correct distances
-
Condense pipe has correct gradient to SVP.
-
Flood Test complete
-
Frese Valve Actuators correct orientation.
Lagging
-
Damaged lagging, rips & tears repaired
-
Correct labels installed to each service
-
Labels installed in correct direction
-
Labels installed visually from access hatches
Sprinkler
-
Sprinkller installed to drawing
-
All joints have been glued to manufacturs instructions
-
Pipework is clear and not touching any rejected materials / other services
-
All heads are set the correct height and allined to the RCP
-
All installed brackets are signed off and correct
-
All pipework through BWH has been correctly fire stopped and acoustic batted
Signatures of Inspection & Review
ESG
-
Print Name and Signature:
-
Position
-
Date:
Ellmers
-
Print Name and Signature:
-
Position
-
Date: