Title Page

  • Document No.

  • Node ID (eg 5CPK-05-07)

  • Conducted on

  • Prepared by

  • Node Location

Connection outcomes

  • Verify if connection is correct as per spreadsheet

  • Add further detail (confirm connection location):

  • Is there an alternative/closer/easier location to connect to?

  • What / where is the alternative?

Connection point scoping details

  • Mains side?

  • Service side?

  • Pole?

  • Pole top arrangements:

  • LV conductor type:

  • LV conductor size:

  • Unfused service pit

  • Fused service pillar?

  • Vacant service fuse base available?

  • Was pillar/pit installed as part of a URD?

Other Information:

  • Earthing arrangements:

  • Other SAPN services in the area (eg: existing HV / LV Cables in the vicinity of NBN works):

  • Take photos of point of connection

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.