Information
-
Engineer Name
-
Customer
-
Store Name
-
Store Number
-
Conducted on
-
Proceed to next section >
Prerequisite Tasks
SCO Check
-
Is there damage to any of the power cables
-
State which SCO number(s)
-
Take clear pictures of damaged cable(s)
-
If there is damage to the power cable, inform Mission Control and wait for further instructions on how to proceed.
-
Proceed to next section >
New Parts Installed - Normal SCO
-
Click "ADD Normal SCO" to record details and tests carried out:
-
The very first SCO in the coral will only need 1 x photo
-
You will record the details of the belted SCO on the next page
Normal SCO
-
Lane number of SCO - (For example, 116, 201)
Before Photographs
-
Take a clear picture of the wiring and earth bonding ( 2 x photos all together. Both sides of the machine)
Completed Work Photographs
-
Take a clear picture of the newly installed conduit ( 2 x photos all together. Both sides of the machine)
-
Take a clear picture of each new installed L brackets installed (2 x photos all together. Both sides of the machine)
-
Take a picture of the SCO welcome screen (Should say lane closed)
New Parts Installed - Belted SCO
-
Click "ADD Belted SCO" to record details and tests carried out:
Belted SCO
-
Lane number of Belted SCO - (For example, 135, 136)
Completed Work Photographs
-
Take a clear picture of each new installed L brackets installed
-
Take a picture of the SCO welcome screen (Should say lane closed)
Site Sign Off
Engineer Sign Off
-
By ticking the box, the Engineer is confirming that all work and tests were completed as per NCR and Customer Requirements
-
Please enter any additional comments or notes here
-
Have you brushed and mopped the area to look good?
Customer Sign Off
-
By ticking the box, you are confirming that all work has been completed successfully and too satisfaction per individual SCO
-
Store Representative Position
-
Store Representative Name & Signature