Information

  • Audit Title

  • Conducted on

  • Prepared by

  • Location
  • Personnel

General

  • Posted OSHA & other Jobsite posters

  • Safety program & substance abuse manual

  • HazCom & MSDS sheets - including subcontractors

  • Emergency numbers/procedures available

  • Rebar capped as necessary

  • Jobsite warning signs posted as necessary

Housekeeping & Sanitation

  • General neatness of working areas & walkways

  • Sanitary,adequate,clean facilities

  • Materials properly stored or stacked

  • Passageway cleared

  • Adequate supply of drinking water & cups

  • Adequate lighting

Fire Prevention

  • Required fire extinguishers in equip properly charged and inspected

  • Fire watch/fire tarps used while doing hot work

Electrical Safety

  • GFCI's used where required

  • Proper guards on temporary lights

  • Lockout/tagout procedures in place- To include Electric panels guarded with proper labels

  • Cords routed to prevent safety dangers & damages

Hand Tools & power tools

  • Proper tools and operator for the job task

  • Damaged tools repaired or replaced

  • Properly guarded

  • PPE used

Hoist, Cranes, & Derricks

  • Crane inspections properly completed by operator

  • Qualified operator

  • Lift areas barricaded & secured

  • Qualified signal person demonstrating proper signaling practice

  • Overhead power lines deactivated or marked

  • Rigging in proper working condition

Heavy Equipment

  • Regular inspection & maintenance

  • Lights, brakes, & warning signals operative

  • Seat belts in good condition and used

  • Operator trained

Excavation

  • Barricading in place during & after work hours

  • Proper egress provided within 25 ft

  • Utility lines located: soil type identified

  • Proper shoring, benching, sloping as required

  • Materials stored at least 2 feet from edge

Flammable Gasses & Liquid

  • Approved containers used & clearly identified

  • Proper storage / Oxy & acetylene tanks separated

  • Fire extinguisher available and properly charged

Welding & Cutting

  • Fire extinguisher within 25 ft

  • Proper PPE being utilized

  • Gas cylinders properly stored, in or out of use

  • Oxy acetylene torch sets, regulator, hoses & attachments inspected

  • Welding cables: leads, connectors, & cable condition

Personal Protective Equipment (PPE)

  • Safety glasses/face shields/goggles

  • Hearing protection

  • Gloves (if needed)

  • Safety harnesses & lanyards (if needed)

Fall Protection

  • 100% tie off above 6 ft & retrieval plan created

  • Proper anchorage points

  • Floor/wall openings covered or guarded

  • Guardrail systems in place & properly installed

  • Roof edge protected

Confined Space

  • Atmospheric testing completed

  • Permit completed & posted

  • On-site rescue provided (if needed)

  • Competent person on-site (if needed)

  • Entering employees properly trained

Stairways & Ladders

  • Stairs with 4 or more steps protected by rail

  • Stairways blocked if unusable

  • Extension ladders secured 1/4 slope, 3" above landing

  • Proper use of ladders

Scaffolds

  • All components properly used / free of defects

  • Mobile scaffolding used as required

  • Scaffolding at or above 20' guyed tied off to structure

  • Planks properly installed

  • Scaffold inspections completed

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.