Information

  • Viscore ID:

  • Address

  • Fibre Access Type

  • Site Survey Conducted by:

Fibre Access for UFB Connect Criteria

  • Is heavy duty build equipment required?

  • Provide a description of the work for referral to BAU build

  • Can ROW crews complete this fibre access build?

  • Provide a description of the work for referral to BAU build

  • Is there more than 5m OSB hard surface reinstatement is required?

  • How much?

  • Is there more than 10m OSB soft surface reinstatement required?

  • How much?

Scoping Details

  • Describe the fibre access connection from network to customer.

  • Add photos for design. Network connection - OSB; access for customer - ISB

  • Will the connection be serviced via ABF, fixed fibre or aerially?

  • Other requirements? I.e TMP, Arborist

  • Additional Notes

Health, Safety and Environmental Issues

  • Have existing utility corridors been considered using on site observations & plans as part of the scope?

  • Build work in close proximity to HV Electricity or HP gas equipment?

  • Working at heights?

  • Dogs on site?

  • Unprotected edge? e.g. Trench, depression or waterway

  • Enter further notes for HS&E risk elimination or mitigation, e.g chemicals or asbestos, confined spaces, gas detection requirements etc.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.