  • Read Preamble/Audit Methodolgy
    http://goo.gl/0memcJ

  • Step 1 - On Site Inspections
    Fill out for randomly selected worksite

    Step 2 - Contractors Records
    Select last 2 compiled documents given by contractor and complete audit

    Step 3 - Electric Line Clearance Audit
    Randomly select 6 roads and complete audit

    Audits need to be completed 3 times a year

  • Document No.

  • Prepared by

Step 1

Audit Information

  • Location
  • Date of Audit

  • Auditor

  • Name of Contractor

Audit

  • All staff hold appropriate tickets to undertake works

  • EPV has current weight test certificates

  • EPV has current electrical testing certificate

  • All necessary signage is in place

  • Restricted entry into worksite

  • Traffic Management Plan on site if necessary

  • All workers with necessary PPE

  • Correct use of safety harness

  • JSA available on site

  • Debris cleaned everyday

  • Pruning to Australian Standards standard

  • Tree stump removed by stump grinding machine if applicable

  • Risk Assessment on site and all works undertaken according to that

Completed

  • Comments

  • Signature

Audit 2

Audit Information

  • Location
  • Date of Audit

  • Auditor

  • Name of Contractor

Audit

  • Road Name

  • Date of actual work done

  • Records checked by

  • Number of trees pruned was recorded

  • Evidence of pre-work inspection by Parks & Gardens supervisor

  • Record of all staff on site each day

  • Recorded details of plants pruned every day (tree genus)

  • Inspection of record by Parks & Gardens Team Leader

  • Record of equipment on site for each day

  • Inspection (pruning) lists on site and filled in accurately

  • Are there any environmental/culturally significant trees on the pruning list?

  • Are there any habitat (breeding) trees on the pruning list?

  • Does any fauna need to be relocated?

  • Is there any cutting/removals deemed urgent on the pruning list?

  • Have all affected persons been notified of urgent works (if any)?

  • Are any trees on the pruning list deemed hazardous?

  • Is an Arborist required to audit any hazardous trees on the pruning list?

Completed

  • Comments

  • Signature

Explaination

  • The next sections will be the 6 individually audited locations. Pay attention to the heading at the top of the section to check the location is correct (eg, Stawell 1 should be in Stawell). The arrows in the blue bar at the top of the page (< >) will allow you to move between the sections.

Stawell 1

Stawell 1

Audit Information

  • Road Name

  • Date of Audit

  • Auditor

  • Name of Contractor

Audit

  • Bushfire Risk

  • Are lines transmitting less than 22KV present?

Up to 22KV

  • Minimum clearance space at section of spans near the pole > 1000mm

  • Minimum clearance space at span up to and including 45m > 1000mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting between 22-66KV present?

Between 22KV - 66KV

  • Minimum clearance space at section of spans near the pole > 1500mm

  • Minimum clearance space at span up to and including 45m > 1500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting more than 66KV present?

Over 66KV

  • Minimum clearance space at section of spans near the pole > 2250mm

  • Minimum clearance space at span up to and including 45m > 2500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 3000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 3500mm

  • Minimum clearance space at span exceeding 100m > 3500mm

Stawell 2

Stawell 2

Audit Information

  • Road Name

  • Auditor

  • Date of Audit

  • Name of Contractor

Audit

  • Bushfire Risk

  • Are lines transmitting less than 22KV present?

Up to 22KV

  • Minimum clearance space at section of spans near the pole > 1000mm

  • Minimum clearance space at span up to and including 45m > 1000mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting between 22-66KV present?

Between 22KV - 66KV

  • Minimum clearance space at section of spans near the pole > 1500mm

  • Minimum clearance space at span up to and including 45m > 1500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting more than 66KV present?

Over 66KV

  • Minimum clearance space at section of spans near the pole > 2250mm

  • Minimum clearance space at span up to and including 45m > 2500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 3000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 3500mm

  • Minimum clearance space at span exceeding 100m > 3500mm

Stawell 3

Stawell 3

Audit Information

  • Road Name

  • Auditor

  • Date of Audit

  • Name of Contractor

Audit

  • Bushfire Risk

  • Are lines transmitting less than 22KV present?

Up to 22KV

  • Minimum clearance space at section of spans near the pole > 1000mm

  • Minimum clearance space at span up to and including 45m > 1000mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting between 22-66KV present?

Between 22KV - 66KV

  • Minimum clearance space at section of spans near the pole > 1500mm

  • Minimum clearance space at span up to and including 45m > 1500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting more than 66KV present?

Over 66KV

  • Minimum clearance space at section of spans near the pole > 2250mm

  • Minimum clearance space at span up to and including 45m > 2500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 3000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 3500mm

  • Minimum clearance space at span exceeding 100m > 3500mm

St Arnaud 1

St Arnaud 1

Audit Information

  • Road Name

  • Date of Audit

  • Auditor

  • Name of Contractor

Audit

  • Bushfire Risk

  • Are lines transmitting less than 22KV present?

Up to 22KV

  • Minimum clearance space at section of spans near the pole > 1000mm

  • Minimum clearance space at span up to and including 45m > 1000mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting between 22-66KV present?

Between 22KV - 66KV

  • Minimum clearance space at section of spans near the pole > 1500mm

  • Minimum clearance space at span up to and including 45m > 1500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting more than 66KV present?

Over 66KV

  • Minimum clearance space at section of spans near the pole > 2250mm

  • Minimum clearance space at span up to and including 45m > 2500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 3000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 3500mm

  • Minimum clearance space at span exceeding 100m > 3500mm

St Arnaud 2

St Arnaud 2

Audit Information

  • Road Name

  • Date of Audit

  • Auditor

  • Name of Contractor

Audit

  • Bushfire Risk

  • Are lines transmitting less than 22KV present?

Up to 22KV

  • Minimum clearance space at section of spans near the pole > 1000mm

  • Minimum clearance space at span up to and including 45m > 1000mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting between 22-66KV present?

Between 22KV - 66KV

  • Minimum clearance space at section of spans near the pole > 1500mm

  • Minimum clearance space at span up to and including 45m > 1500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting more than 66KV present?

Over 66KV

  • Minimum clearance space at section of spans near the pole > 2250mm

  • Minimum clearance space at span up to and including 45m > 2500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 3000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 3500mm

  • Minimum clearance space at span exceeding 100m > 3500mm

St Arnaud 3

St Arnaud 3

Audit Information

  • Road Name

  • Date of Audit

  • Auditor

  • Name of Contractor

Audit

  • Bushfire Risk

  • Are lines transmitting less than 22KV present?

Up to 22KV

  • Minimum clearance space at section of spans near the pole > 1000mm

  • Minimum clearance space at span up to and including 45m > 1000mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting between 22-66KV present?

Between 22KV - 66KV

  • Minimum clearance space at section of spans near the pole > 1500mm

  • Minimum clearance space at span up to and including 45m > 1500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 2000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 2500mm

  • Minimum clearance space at span exceeding 100m > 2500mm

  • Are lines transmitting more than 66KV present?

Over 66KV

  • Minimum clearance space at section of spans near the pole > 2250mm

  • Minimum clearance space at span up to and including 45m > 2500mm

  • Minimum clearance space at span exceeding 45m, up to and including 70m > 3000mm

  • Minimum clearance space at span exceeding 70m, up to and including 100m > 3500mm

  • Minimum clearance space at span exceeding 100m > 3500mm

Completed Individual Audits

  • Once all 6 locations have been audited, complete this section

Completed

  • Comments

  • Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.