Title Page
NICEIC QS Inspection
-
Project Name:
-
Project Number:
-
inspection Date:
-
Inspected by:
-
Stage of install audit is carried out:
Safe Systems of Work
-
RAMS Covering all electrical works
-
Safe Isolation procedure documented
-
Appointed Person in place
-
Lock Off Kits available if required
-
Calibration Certificates for any test equipment
Source of supply
-
DNO Service Head & Meter Install
-
Correct cable size from DNO to Consumer side.
-
Separate Main Isolator installed (if required)
-
Generator installed correctly (if required)
-
Generator cable sized correctly?
Earthing
-
Main Earth Bar Installed
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Main Earth Connected
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Main Earth sized correctly?
-
Main Protective Bonds Connected
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Main Protective Bonds sized correctly?
-
Earth Mat installed (if required)
-
Has a copy of the Earth Mat Certificate been issued?
-
Who has cert been issued to?
-
Lightning Protection Tapes and rods installed
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Has a copy of the Lightning Protection Certificate been issued?
-
Who has Cert been issued to?
-
Bonding Clamps tight
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Safety Electrical Connection labels fitted
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Earth Tags fitted to metal back boxes
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Cross bonding of containment
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
First Fix Containment
-
All cut metal Galvanised Sprayed
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All unistruts have end caps
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All bracketry fixed with a fire rated fixing
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Brackets either side of a Fire Wall must be 150mm away maximum
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Appropriate distance between brackets for all containment, maximum as per table D1, D3 & D4 of BS7671
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All containment to have a minimum 20% spare capacity
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Secure fixing of all containment
-
All bracketry square with containment & level
-
Trunking to have no open holes
-
All external metal containment & strut Hot Dipped Galvanised
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Conduits have no more than 180deg total bends between inspection boxes or accessories
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Trunking lids are complete
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Trunking lids have sufficient number of camlocks
-
All back boxes installed at correct heights
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All back boxes within fire walls to have Putty Pad installed and signed off on register
First Fix Wiring
-
Cables run within correct zones in walls
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Cables sized correctly for use
-
Cable ties used throughout on ladder, basket and tray
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Metal cable ties used every 1m on ladder, basket and tray on vertical drops and escape routes. (Cat6 to be around the external side of containment, not directly on cables)
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Cables are not burned or snaged/cut insulation
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
LV & ELV circuits segregated
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Cables are not under strain round bends
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Cables are supported sufficiently in their entirety
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Cat6 Data cable Velcro tie wrapped only
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
Second Fix Accessories
-
All terminations tight and correct
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All accessories free from damage
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Correct IP ratings used for outdoors & special locations
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Correct identification of cables used, including sleeving
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Mechanical isolators can be locked in the OFF position
-
All accessories installed level and tight
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
Distribution Boards/Panels
-
All freestanding LV panels to have a built in plinth
-
All SWA's to have Critchley marker with circuit details on them both ends
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All wall mounted DB's mounted at a suitable height & uniform throughout if more than 1
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All DB's metal, & correct IP rating for outdoor use
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All DB's wrapped in suitable sized Trunking with a minimum 20% spare capacity
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All DB cable entries slotted not bushed
-
All DB's have Paxolin between trunking and DB
-
Only circuits fed from DB are in the DB, no other circuits passing through
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Correct ACB, MCCB, MCB & RCBO ratings used
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All cables leaving terminations within DB to have circuit reference
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All barriers present
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
No cable ties holding cables in place within DB
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
All shrouds within DB fitted
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
DB lids have no screws missing
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
DB lids lockable
-
DB/Panel blanks fitted
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Voltage Warning stickers fitted to DB's and JB's
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
SPD Installed sticker fitted
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Date of Next Inspection' sticker fitted
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
RCD 6 monthly test noticed fitted
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Electric Shock notice fitted next to DB/Panel
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
DB schedule fixed next to or on the lid of DB/Panel
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
-
Rubber floor matting fitted by all LV Panles and DB's (where required)
- Yes
- Ongoing Works
- Works not yet started
- No - Major
- No - Minor
- N/A
Testing & Inspection
-
Ze is within Maximum for Earthing Type
-
PFC is within Main Breaker breaking capacity
-
Zs of final circuits are within their maximum allowed
-
RCD times are less than 40ms @ 5x
Declaration
-
Have all Major issues been rectified from previous audit?
-
Have all Minor issues been rectified from previous audit?
-
Does site team have any queries with issues raised?
-
Site team comments (if required):
NOTE: Any defects marked MAJOR must be rectified within 24hrs and evidence given. Any defects marked MINOR must be rectified before next inspection
Position
-
NICEIC QS Sign
-
Supervisor Sign
-
Date