Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

NYX Tool Build Report

  • Mold Number

  • Program Designation

  • Part Name

  • Mold Source

  • Planned Press Size

  • Material Code

  • Tooling Engineer

Mold Base

  • Mold Labeled in Accordance with NYX Mold Build Standards?

  • Quick Mold Change Slots are Present on the Cavity Half Clamp Plate?

  • Oversized Guard Plates for Water and Hydraulic Fittings are Adequate?

  • Is the Swivel Type Single Point Lift Ring Present on the Mold?

  • Are Eyebolt Holes present at the four corners of the back of the Cavity and Core Clamp Plates?

  • Is there clearance holes for the Valve Gate Pins?

  • Is the Clamp Slot Thickness correct for the mold size?

  • Are the clamp slots on the Operator and Non-Operator side of the mold?

  • Are all mold corners broken including the parting line?

  • Are all thread sizes in inch standard?

  • Are all features flush to the mold base?

  • Is the shot counter installed on the Operator Side parting line?

  • Are the Safety Straps on both the Operator and Non-Operator side of the mold?

  • Does the mold fit in the planned Machine Size as Designed?

  • Has a quote been provided for Long Lead / Special Order Components?

  • If over 250 tons, is there 2 Eyebolt holes on each rail?

  • Is there Wear Plates on the Parting Line Locks?

  • Is there verification that the mold does not overhang the platen or has clearance been verified?

Mold Actions

  • Are the lifter rods 1" diameter and locked in place?

  • Can the lifters be disassembled from the parting line?

  • Do the hydraulic connections conform to the NYX Mold Build Standard?

  • Are the horn pins removable from the parting line?

  • Are the slides retained in the open position by springs?

  • Do the threads for ejection comply with the NYX Mold build Standard?

  • Is the ejector box covered on the top of the mold?

  • Does mechanical ejection have return springs or gas struts?

Water

  • If over 350 tons, is there a water manifold on core half and cavity half?

  • Are the water channels labeled? (IN 1, OUT 1, etc.)

  • Are all circuits independently attached to the mold or manifold?

  • Are there red hoses on the outlet lines and blue hoses on the inlet lines?

  • Is the manifold color matched to the lines ( Red & Blue )

  • Are the water fittings labeled?

  • Are the water lines recessed and flush?

  • Does the cooling hookup comply with the NYX Mold Build Standard?

Hot Runner Manifolds

  • Is there a plaque for the Hot Runner Schematic and required information?

  • Does the cavity half clamp plate have an insulator plate?

  • Do the Valve Gate Hydraulics and Cooling meet the Supplier Specification?

  • Are the electrical hook ups flush to the mold base?

  • Are the Power and TC Plugs correct to the NYX Mold Build Standard?

  • Is the manifold functioning correctly?

  • Are the Valve Gates functioning correctly?

Gating, Runners and Sprues

  • Is the sprue bushing, DME or equivalent for taper and Finish?

  • Is the sprue bushing recess less than 3.0" in depth?

  • Is the Sprue Bushing Nozzle Seat 3/4" radius?

  • Is the locating ring 4" diameter?

  • If Family Mold, are there runner shutoff's and are they DME or Equivalent?

  • Is the runner identified with material code and cavity ID?

  • Are there cold slug wells on the runner?

  • Does the runner system and gating comply with the NYX Mold Build Standard?

  • Are the gate blocks removable from the front of the mold?

Venting and Mold Surfaces

  • Are Parting Line Vents cut in every 1.50" on center around the periphery of the cavity(s)?

  • Is there a clearance hole where required?

  • Is there provisions to remove Pocerax Inserts for ease of cleaning?

  • Are features deeper than 0.25" inserted and vented?

  • Do A Surface ribs have vents?

  • Is the parting line relieved 0.030" - 0.050"?

Visual Part Surface Inspection

  • Is the Parting Line free of Flash?

  • Are the runners and gate inserts free of flash?

  • Are the slide seal off areas free of flash?

  • Are the Lifters free of flash?

  • Is the Parting Line Match on Class 'A' Surface acceptable?

  • Is the Class 'A' Surface free of Sink Marks?

  • Is the Class 'A' Surface free of high gloss areas or gloss variation?

  • Is the Class 'A' Surface free of Read through of B Side Features?

  • Is the Class 'A' Surface free of Stress Marks?

  • Is the Class 'A' Surface free of Splay?

  • Has the wall thickness been verified to data?

  • Have Knitline locations been approved by Engineering an Manufacturing?

  • Is the 'A' Surface acceptable? ( No Hard Lines, Blended Radii, etc. )

  • Is the Core Surface acceptable?

  • Are all second surface features polished?

  • Is Cavity Number, Mold Number, Part Number Engraved correctly in Mold Cavities?

  • Are all second surface features free of distortion?

  • Are all second surface features less than 60% of the nominal wall thickness?

  • Are all second surface features filled?

  • Are the ejector pins free of plastic? ( flash )

  • Are the ejector pins flush with the core surface?

  • Are the slides and lifters flush to the core surface?

  • Are the vents open?

  • Does the gloss level reading meet the specification? ( Post Grain )

  • Is the grain area free from surface imperfections? ( drag, non-uniform gloss, etc )

Mold Perfromance

  • Does the ejector system move freely? ( no binding, galling, etc. )

  • Is there sufficient ejector stroke for the part to clear the core side?

  • Are there a sufficient number of ejector pins to demoed the part?

  • Can the part be removed by the EOAT and Robot?

  • Do the slides move freely? ( no binding, galling, etc. )

  • Is the slide travel sufficient to clear the part?

  • Do the lifters move freely? ( no binding, galling, etc. )

  • Is the lifter travel sufficient to clear the part?

  • Do the gates trim cleanly without vestige?

  • Does the mold cycle at or below the quoted rate?

  • Is the cavity fill balanced and acceptable?

  • Is the part/shot weight at or below the quoted estimate?

  • Is the part dimensionally correct?

  • Does the part(s) fit the gage and is the gage approved?

  • Is the mold free of any hydraulic or water leaks?

Mold Profile Information

  • Mold Length

  • Mold Width

  • Mold Shut Height

  • Mold Weight

  • Number of Hydraulic Cores / Slides

  • Core Sequence

  • Number of Slides

  • Number of Lifters

  • Ejection Type (Machine or Hydraulic)

  • Ejection Stroke

  • Ejector Plate Thread Size

  • Shrink Value (inches)

  • Orifice Diameter

  • Number of Cavities

  • Sprue Bushing Depth (recessed)

  • Gate Type and Number

  • Hot Runner Type

  • Number of Zones

  • Valve Gates and Number of

  • Water System ( Manifold or Multiple )

  • Water Fitting Size

  • Number of Water Hook-Ups

  • Mode of Operation (Robot, Auto, Semi)

Injection Molding Process Data

  • Injection Fill Time, Fill Pressure, Fill Weight

  • Pack Time, Pack Pressure

  • Hold Time, Hold Pressure

  • Cure Time, Recovery Time, Back Pressure

  • Full Part Weight, Shot Weight

  • Barrel Temperatures (Nozzle - Rear)

  • Hot Runner Temperatures

  • Mold Temperatures (Cavity and Core)

  • Cycle Time

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.