Scope: Utilize this procedure for any maintenance or servicing of aforementioned equipment:
Purpose: To protect authorized employees against unexpected activation of equipment or energy while servicing equipment.
Authorization: The plan administrator (as defined in Patterson written lockout program) is responsible for all procedural steps.
Enforcement: Failure to properly follow lockout/tagout procedures may result in disciplinary action.
Notify affected personnel that Lockout/Tagout is Being Performed
Isolation Devices & Details
Step 1 / Appendix 1
-
Type of Energy
- Electrical
- Pneumatic (Air)
- Hydraulic
- Chemical (gas/liquid)
- Potential/Kinetic
- Thermal
-
Describe where the energy isolation point is located
-
Describe how to disconnect (de-energize) this energy source
-
Identify the device required for lockout/tagout
- Lock & Tag
- Plug Lock Device
- 1/4 Turn Valve Cover
- Circuit Breaker Device
- Cable Device
Step 2 / Appendix 2
-
Type of Energy
- Electrical
- Pneumatic (Air)
- Hydraulic
- Chemical (gas/liquid)
- Potential/Kinetic
- Thermal
-
Describe where the energy isolation point is located
-
Describe how to disconnect (de-energize) this energy source
-
Identify the device required for lockout/tagout
- Lock & Tag
- Plug Lock Device
- 1/4 Turn Valve Cover
- Circuit Breaker Device
- Cable Device
Step 3 / Appendix 3
-
Type of Energy
- Electrical
- Pneumatic (Air)
- Hydraulic
- Chemical (gas/liquid)
- Potential/Kinetic
- Thermal
-
Describe where the energy isolation point is located
-
Describe how to disconnect (de-energize) this energy source
-
Identify the device required for lockout/tagout
- Lock & Tag
- Plug Lock Device
- 1/4 Turn Valve Cover
- Circuit Breaker Device
- Cable Device
-
Photos of the Steps / Appendix above in order
Verify the De-energization of all energy sources
-
Lockout Removal Process:
1 - Inspect the work area to verify all tools, equipment, and materials have been removed 2 - Verify that controls are neutral 3 - Remove devices in reverse order 4 - Notify employees that work is complete -
Periodic Inspection Date (Date of the Annual Review):
-
Date of Lockout Creation / Update: