Audit

1. PREPARATION OF GROUT

All tendons checked for passage of air

Any tendons need drilling

Mixture

Cement type GP to AS3972 to be used

Any additives used (Viscocrete 10 or approved other)
If 'other', please provide detail

Water to cement ratio up to 0.45

(Maximum 9 litres of water per 20Kg of cement)

Water was measured

2. GROUTING PROCEDURE

Type of ducting used:

Check for looped tendons

Check intermediate points

Bucket operator confirms grout quality expelled

Check ducts are clear and have free passage of air

3. GROUTING RESULTS

Operators have checked perimeter for any leaks of grout

All tendons grouted and complete

Cable numbers not yet grouted

4. IF INCOMPLETE, WHY WAS DECK NOT FULLY GROUTED (Ignore if grouting complete)

4a. Follow up required before signing off?

Send form to Construction Manager for review

COMMENTS / NOTES

Pump Operator (Print Name and Sign)
Bucket Operator (Print Name and Sign)
Nozzle Operator (Print Name and Sign)
CONFORMANCE

It is hereby confirmed that all post-tensioning tendons to the above noted slab / deck have been fully grouted

Main Contractor (Print Name and Sign)
Fortec Leading Hand (Print Name and Sign
Please note that this checklist is a hypothetical example and provides basic information only. It is not intended to take the place of, among other things, workplace, health and safety advice; medical advice, diagnosis, or treatment; or other applicable laws. You should also seek your own professional advice to determine if the use of such checklist is permissible in your workplace or jurisdiction.