Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Property / Flat Number (Photograph of Front Door)
Details of the Property
-
What is the Status of the Property?
Inspection
-
Is this a technical Inspection for Meter Work
-
Is this a Post Meter Audit
-
Meter Fitter's Name
General
-
Does the Operative have access to the appropriate work procedures/ codes of practise?
-
Is the Atmospheric Monitoring Equipment tested in date and used when required?
-
Are G/17 or G/19 in place for meter installations >bar and for all electrical and instrumentation work?
-
Are faults on meter installations reported as per fault finding procedure PM/FAULT/1?
Method of Working
-
Does the Meter Fitter have Two Volt Sticks? (Photographic Evidence)
-
Are they clean and serviceable?
-
Was the Volt Stick used as Appropriate?
-
Has the Volt Stick been "Proved" against a known Electrical Source? (Photographic Evidence)
-
Was the Temporary Continuity Bond used as appropriate? (Photographic Evidence)
-
Was / Is the Meter Location Acceptable? (Photographic Evidence)
-
For external installations; Is the Meter Box fit for purpose and has it been correctly installed? (Photographic Evidence)
-
Has the rear pipe exit of inset meter box been sealed ? (Photographic Evidence)
-
Has the Pipework been installed correctly ?
-
Has the meter bracket been fitted correctly? (Photographic Evidence)
-
Are Cork Washers Fitted?
-
Is the correct meter and materials used for MAM?
-
Has the Meter been installed, exchanged or been removed as per procedure?
-
Are Shear Bolts fitted correctly?
-
Is the ETM securely fixed to the floor / wall ? State Which
-
Are the ETM Battery Compartment Seals Fitted ?
-
Has Flux Spillage and Debris been removed from Stainless Steel Meter Connections ?
-
Has the Testing and Purging Procedure been followed ?
-
Is the Emergency Control Accessible, Operable and falls into the "Off Position"
-
Has the ETM Fault / Maintenance Procedure been followed ?
-
Has a replacement meter regulator been identified and exchanged as per PM/TMP/14 ?
-
Is the Working Pressure at the Meter Outlet Correct and Regulator Sealed ? Detail Pressure (Photographic Evidence)
-
Has the Meter Control Valve been exchanged as per procedure ?
-
Has the earth strap been fitted if meter is being removed longer term ? (Photographic Evidence)
-
Is the "On / Off" Tape attached ? Is it in good condition ? (Photographic Evidence)
-
Is the "Gas Tape" attached ? Is it in good condition ? (Photographic Evidence)
-
Is the Equipotential Bonding correct ?
-
If Equipotential Bonding is incorrect or can't be connected has safety warning card been left ?
-
Was the correct procedure followed if MEB was altered when meter was relocated ?
-
Have MPRN labels been attached and completed where applicable.
-
Visual inspection of Meter Installation / appliances (Photographic Evidence)
-
If Meter / Appliances are deemed as unsafe has an appropriate "Warning / Concern Label been fitted / left with occupier ?
Documentation
-
Is the "Job Reporting Documentation" and Data Capture Correct
-
If there are faults on the meter installation, have these been reported as per the "Fault Finding Procedure" ?
-
Is the Meter Fitter fully aware of the company's accident / incident reporting procedure and the RIDDOR reporting procedure when required ?
Customer Service and Perception
-
Was the appearance of the Meter Fitter appropriate ? (Photographic Evidence)
-
Did the Meter Fitter introduce themselves and show their ID Badge / ID Card ?
-
Did the Meter Fitter explain the nature of their visit, description of the works to be conducted and any necessary safety warnings whilst they were carrying out the works ?
-
Was the Customer's property adequately protected during the works ? (Photographic Evidence for a live audit)
-
Did the Meter Fitter position their tools and equipment safely ?
-
Was there any waste generated ? Was this disposed of correctly and the property left clean and tidy?
-
Were the Correct Customer Care Leaflets / Information Packs Left with the Customer ?
Performance Score
-
Risk Rating of Performance and Installation - 1-4 (High Risk) 5-7 (Medium Risk) 8-10 (Low Risk)
-
Comments / Recommendations
Sign Off
-
Auditors Name