Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Project and Quality Management

  • Is the consultant management team engaged with the quality program? <br>Principal? <br>Project Manager? <br>Quality Manager?

  • Where is the production work being completed? <br> How is quality oversight taking place in:<br> Remote offices? <br> Subconsultant offices?

  • Was the Itemized Submittal List provide to the OCTA QAM in advance of the audit/surveillance?<br>

  • Was the QC Activity schedule completed and provided? Does the actual schedule closely match the planned schedule?

  • Is a Risk Identification Log maintained? <br> Was an Assessment of the Risks conducted?<br> Was the Risk Register distributed to the Project Team who need to know this information?

  • What method is being used to track action items?

  • Is the Design Control Log apply to this milestone? <br> If yes, is it completed and distributed to the Project Team?

Roadway Drawings

  • Are the documents that are noted on the Itemized Submittal List available?

  • is the Discipline Review quality records available for review?<br> Are they satisfactory?<br> Are some disciplines of work missing? which ones?<br> Overall, is the Discipline Review meet the requirements of the quality program?

  • Are any obvious drawing missing for this submittal?

Structures Drawings

  • Are structures included with this submittal?<br> Bridges?<br> Retaining Walls?<br> Sound Walls?<br> Special Structures?

  • Are the calculations prepared in accordance with the Checking Calculations Procedure?

  • Has the Independent Check of Structures been completed?<br> What is the status?

Reports

  • List Reports that are included with this submittal.

  • Are calculations checked?

  • Are drawings and exhibits checked?

  • Are the reports presented neat, orderly and in accordance with the style guide?

  • Has the report been checked by a minimum or two people?

  • Has the body of the report checked and confirmed against the appendices, exhibits, tables, etc?

Cost & Quantity Estimate

  • Was a cost estimate completed for this milestone?

  • Is there evidence that the accuracy check of the quantities was completed? <br> Are the calculation presented neatly and orderly?<br> If a spreadsheet was used, were the cell calculations checked?

  • Is there sufficient evidence that a "Reasonableness Check" conducted?

  • Explain how the unit costs were determined?

  • Has the engineer's construction cost substantially changed since the prior submittal?

Quality Control Processes

  • Is there sufficient evidence that Inter-Discipline coordination has taken place? <br> What methods were used?<br> Are meeting notes available?<br> Was an action item log used to track issues and coordinate resolution?

  • Was accuracy checks conducted prior to the discipline review?

  • Was a Discipline Review conducted after the accuracy check and before the Inter-Discipline Review?

  • Was the Inter-Discipline completed? <br> Did all applicable discipline participate?

  • Has the Management Review and QA Certification been completed?

Quality Control Procedures

  • Are the quality program mechanics being properly followed?<br> Use of a color code system?<br> Use of the Check Print stamps?<br> Use of the Review Print stamp?<br> Use of Checklists?

  • Software selection and validation?

  • Checking Calculations?

  • Checking Drawings?

  • Checking Reports?

  • Checking Specifications?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.