1. Safety Policy

  • 1:1 Is the mine's Safety Policy displayed publicly for all to see.

  • 1:2 Does the mine have a Safety Policy

  • 1:3 Is the Policy communicated at induction

2. Work Safety Management Plan.

  • 2:1 Is a Documented Safety Management Plan in place

  • 2:2 Is the plan approved by the Functional Manager

  • 2:3 Is the Safety Management Plan issued as a controlled document to supervisory staff and discussed accordingly with them.

3. Safe Work Instructions

  • 3:1 Have high/moderate risk activities been identified.

  • 3:2 Have JobSafety Analyses been carried out.

  • 3:3 Have Safe Work Instructions (SWIs) been developed

  • 3:4 Have SWIs & procedures been communicated to the workforce.

4. Subcontractors Safety Management.

  • 4:1 Has a Safety Management Plan been obtained from all contractors on site.

  • 4:2 Have the Plans been approve by the responsible Manager

  • 4:3 Have the Plans been implemented throughout the subcontractors team

  • 4:4 Are the subcontractors systems regularly audited

5. Investigations

  • 5:1 Is a system in place for reporting and investigating all accidents, incidents and non-conforances.

  • 5:2 Are all the relevant supervisors included in the reporting and investigation of the above

  • 5:3 Does the incident investigation system require checks in such laces as maintenance records, personal records, training records and production results to compare the number of repeat occurrences.

  • 5:4 Have the personnel who are required to conduct investigations been provided with formal training.

  • 5:5 Is corrective action carried out, within the allocated time, as recommended in the report

6. Safety Management System Review.

  • 6:1 is there a system in place for conducting comprehensive audits to check compliance with the safety management system

  • 6:2 Are audits conducted in accordance with the system.

  • 6:3 Are the findings of the review documented and actions formulated to address any identified deficiencies

  • 6:4 Are the actions corrected and approved by the agreed upon time frame

  • 6:5 Do senior management review the reports.

7. Training Systems -General (operational)

  • 7:1 Is a training system in place to develop and administer all training requirements.

  • 7:2 Has a clear career path been mapped out for operational personnel

  • 7:3 Is training aligned to the above career path (operations).

  • 7:4 Is the training aligned to the above career path.

  • 7:5 Has a systematic approach been used used to identify all employees training needs (training matrix) (operational)

  • 7:6 Do the instructors have the necessary competences for the specific topics in which they assess.

  • 7:7 Are the trainers given the necessary training to maintain their qualifications.

  • 7:8 Are lesson plans and effective training aids available and used for all the training programs.

  • 7:9 GOLD Are all aspects of training integrated into a singalong training management system to prevent duplication and manual manipulation of work.

  • 7:10 GOLD Does on-on-the job coaching form a part of the operator training programme.

  • 7:11 GOLD Are the defined career paths applied with operations personnel.

  • 7:12 GOLD Are the training requirements inter-linked with planned task observations and personnel assessments.

8. Site Inductiom

  • 8:1 Is an induction programme in place for new employees.

  • 8:2 Is the presenter, carrying out the training course, qualified to do so.

  • 8:3 Are all relevant and required topics covered in the induction.

  • 8:4 Are questionnaires completed by the learners.

  • 8:5 Is the induction well streamlined with minimal disruptions.

  • 8:6 Are records of induction completed and updated.

  • 8:7 Are all personnel on site inducted prior to commencing their duties.

  • 8:8 Is a specific induction program in place for supervisors.

  • 8:9 Is the content of the induction program adequate for the supervisory function.

  • 8:10 Have the supervisors completed induction questionnaires.

9. Supervisor Training.

  • 9:1 Is a specific training program in place for supervisors

  • 9:2 Does the program cover the basic requirements associated with the equipment and the mining process used throughout the mine

  • 9:3 Does the program cover fundamental elements of mechanised mining and supervision

  • 9:4 Does the program cover the basic soft skills associated with supervising the workforce (plan-do-check-act, leadership, delegation, mentoring etc)

  • 9:5 Do supervisors have a clearly defined career path available to follow.

  • 9:6 Is supervisor task training/assessments undertaken with supervisors.

  • 9:7 Are appropriate records pertaining to the above available.

  • 9:8 GOLD Are the supervisors evaluated using assessments on a regular basis (6 months)

  • 9:9 GOLD Have the majority of the supervisors attended the supervisory training courses

  • 9:10 GOLD Are defined career paths applied with the maintenance personnel.

  • 9:11 GOLD Are supervisors evaluated using Planned Task Observations.

10. External Certificates

  • 10:1 Do personnel in restricted occupations posses the required certificates of competency necessary to perform their tasks (winder certificate, electrical etc)

  • 10:2 Are copies of certificates available.

11. Competency Assessments.

  • 11:1 Are competency assessments performed across the required functions

  • 11:2 Are competency assessments performed on a regular, pre-defined basis

  • 11:3 Is the assessor performing the assessments qualified to do so.

  • 11:4 Are assessment records available.

  • 11:5 PLATINUM. Are competency assessments used to review individuals performance and define training needs.

12. Specific Skills.

  • 12:1 Is there a training program in place for maintenance personnel

  • 12:2 Has a clear career path been mapped out for the maintenance personnel.

  • 12:3 Is training aligned to the above career path (maintenance)

  • 12:4 Are programs updated whenever there are changes to systems of work or equipment.

  • 12:5 Are assessments regularly performed on the maintenance personnel.

  • 12:6 Are the above assessments records available

  • 12:7 GOLD Are all aspects of training integrated into a single training management system to prevent duplication and manual manipulation of work.

  • 12:8 GOLD Does on-the-job coaching form part of the maintenance training program.

  • 12:9 GOLD Are training requirements inter-linked with PJO and personnel assessments

13. Task Observations.

  • 13:1 Is a system in place which requires supervisors to conduct observations of tasks being performed

  • 13:2 Does the system ensure that all employees will be periodically observed whilst performing their required function

  • 13:3 Are the results of the observations clearly documented

  • 13:4 Are inspections in line with procedural compliance expectations

  • 13:5 GOLD. Is there a system to a sure that identified non-compliances are corrected

  • 13:6 GOLD. Are task observations linked to training/coaching needs and requirements

14. Group Communcation

  • 14:1 Is a group Communication system in place

  • 14:2 has responsibility been assigned to appropriate individuals for conducting these communication meetings

  • 14:3 Do all relevant personnel attend these communication meeting.

  • 14:4 Are minutes of these meetings taken and formally recorded on file

  • 14:5 Is a centralised control in place

  • 14:6 Is an effective communication system available throughout all working sections of the mine (with radios on all primary equipment)

  • 14:7 GOLD. Is there evidence of these meetings being used to review work practices and procedures.

  • 14:8 GOLD. Is a formalised communication system in place to discuss previous "planned v achieved" shift performance.

  • 14:9 GOLD. Is the control room used to effectively monitor and control the operation.

15. Pre-start Checks

  • 15:1 Are pre-start check lists developed and in place for all equipment.

  • 15:2 Are operators trained in the correct completion of these pre- start checks

  • 15:3 Are the pre-start checklist completed correctly each shift

  • 15:4 Are the completed pre-start check lists handed over to the maintenance department

  • 15:5 GOLD. Is the information from the pre-start check lists scheduled and the schedule communicated to the workforce on a daily basis

16. Emergency Preparedness

  • 16:1 Have the relevant types of emergencies bee identified

  • 16:2 Have emergency action plans been established

  • 16:3 Have the mine Coordinator and wardens been identified

  • 16:4 Has the evacuation plan/routes been displayed at all waiting places

  • 16:5 Is emergency awareness training conducted.

  • 16:6 Are all refuge chambers and emergency routes sufficiently visible throughout the mine

  • 16:7 Is the emergency procedure regularly rehearsed

17. Equipment Selection

  • 17:1 Has a review been conducted to determine the equipment specifications required to ensure production targets are met within the given mining environment

  • 17.2.Does the review take into account availability of spare parts and consumables?

  • 17.3.Has equipment been purchased in accordance with the review?

  • 17.4. Are frontline personnel involved in the equipment selection process

  • 17.5. GOLD Are follow-up reviews conducted to evaluate previous decisions and future requirements based on planned vs. actual.

18. CONSUMABLES (Rock Tools)

  • 18.1.Has a list of critical consumables been for each machine type?

  • 18.2.Have minimum stock levels been determined?

  • 18.3.Has responsibilities been assigned to correctly manage stock levels?

  • 18.5.Is consumable usage formally reported on a monthly basis?

  • 18.4. GOLD Is usage monitored taking into account performance achieved and expenditure vs. budget?

  • 18.5. GOLD Are stock-outs measured and used to update minimum stock levels.

  • 18.6. GOLD Is consumables consumption used to evaluate individuals performance and integrated into a performance appraisal system.

19. PLANNING - LONG TERM

  • 19.1.Does the organisation have a long-term production plan in place?

  • 19.2.Does the long-term plan reflect the original business plan that was compiled to allow funding for the operation to proceed?

  • 19.3.Is the long term production plan updated at least monthly to show actual meters excavated?

  • 19.4.Where an obvious production shortfall occurs has the organisation developed an action plan to remedy the situation?

  • 19.5.Does the long term plan take into account tipping points and tramming distances?

20. PLANNING - MONTHLY

  • 20.1.Is there a system in place to ensure formal planning is conducted monthly?

  • 20.2.Are all appropriate positions/people involved in the determination of the monthly plan?

  • 20.3.Are clear production targets established within the monthly plan?

  • 20.5.Does the short-term plan reflect the requirements of the long-term plan?

  • 20.6.Are all relevant mine measurements incorporated into the monthly plan?

  • 20.4. GOLD Are production shortfalls from previous months taken into account?

  • 20.5. GOLD Is a Lost Blast Analysis conducted to determine shortfalls in production and reasons for not achieving the plan.

  • 20.6. OLD Is a "planned vs. achieved" analysis carried out to determine compliance with the monthly plan.

21. PLANNING - DAILY

  • 21.1.Is there a system in place to ensure daily production expectations are planned with the supervisors?

  • 21.2.Is the daily plan directly aligned with the monthly plan?

  • 21.3.Do all supervisors and leading hands receive a copy of the daily plan?

  • 21.4.Are planned versus actual activities recorded at the end of each shift?

  • 21.5.Is the monthly production plan updated daily?

  • 21.6.Is the actual production information used to identify trends and assist in problem solving?

  • 21.7 GOLD Is a "planned vs. achieved" analysis carried out to determine compliance with the daily plan.

  • 21.8. GOLD Is the achieved production and development within 80% compliance of the plan.

  • 21.9. GOLD Is a Lost Blast Analysis conducted per day to determine production and development deficiencies.

22. PLANNING - SHIFT

  • 22.1.Is there an appropriate pre-shift meeting with all the necessary members of the team?

  • 22.2.Is the pre-shift meeting conducted in a quiet area, record kept, with appropriate visual aids for the capturing and communication of critical information?

  • 22.3.Is the information updated (and accurate) at the end of each shift by the off going supervisor?

  • 22.4.Does the communicated information reflect the requirements of the 24 hour cycle plan?

  • 22.5. GOLD Is a Lost Blast Analysis conducted per shift to determine production and development deficiencies.

23. SHIFT PERFORMANCE MEASUREMENT

  • 23.1.Have shift performance measurement parameter requirements been determined for each piece of equipment?

  • 23.2.Have these expectations been communicated to the team?

  • 23.3.Is the equipment capable of achieving the required performance measures/parameters?

  • 23.4. GOLD Are the performance parameters correctly monitored and communicated to all parties concerned?

  • 23.5. GOLD Is action taken when KPIs not to expectation?

  • 23.6. GOLD Is shift performance collated into monthly and annual performance information (per person).

  • 23.7 GOLD Do individuals receive feedback regarding their daily and monthly performance and any related deficiencies.

24. MAINTENANCE - GENERAL

  • 24.1.Is a maintenance strategy defined.

  • 24.2.Is a maintenance philosophy defined.

  • 24.3.Do maintenance staff know what the meaning and purpose of the above are?

  • 24.4.Is information from the Pre-start checks captured and scheduled? (Backlogs created)

  • 24.7.Are sufficient maintenance personnel available for breakdown requirements?

  • 24.8.Are sufficient means of communication available for the breakdown crews to operate effectively?

  • 24.9.Are breakdown personnel able to respond in a timely fashion?

  • 24.5. GOLD Has a review been conducted to determine the personnel skills and compliments required?

  • 24.6. GOLD Have the review findings been complied with?

  • 24.7. GOLD Have the maintenance strategy and philosophy been applied (as defined)

25. MAINTENANCE - WORKSHOP

  • 25.1.Is the structure of the workshop adequate for the maintenance requirements?

  • 25.2.Are appropriate ablutions available for workshop personnel?

  • 25.3.Is adequate tooling available with reference to the machinery on site?

  • 25.4.Is an in-line Oils and lubricants delivery system in place (borehole)?

  • 25.5. Are oils and lubes transported using drums (underground to surface)

  • 25.6.Is Oil and Diesel consumption measured?

  • 25.7.Can ‘used’ lubricates be disposed of correctly?

  • 25.8.Is Electrical power available for specific equipment?

  • 25.9. GOLD Has a workshop review conducted annually to determine workshop requirements given changes in production demands and machine fleet sizes.

  • 25.10. GOLD Has the above assessment been complied with

  • 25.11. GOLD Has an assessment been conducted to determine optimum location of the main workshop and main workshop requirements

26. MAINTENANCE - SPARES ON SITE

  • 26.1.Is a critical spares list in place for every machine on site?

  • 26.2.Is the critical spares list reviewed and updated?

  • 26.3.Is a person responsible for spares issuing and monitoring of spares?

  • 26.4.Is a person responsible for spares ordering?

  • 26.5.Are stores facilities adequate for the required spares (sufficient stores with security, ventilation, shelving etc)

  • 26.6.Are all stores and spares personnel adequately trained to manage, issue and monitor spares

  • 26.7.Are minimum stock levels determined?

  • 26.8.Are stock levels maintained according to the spares requirements?

  • 26.9.Are parts costs reconciled and reported?

  • 26.10.Are planned materials (parts) ordered and linked to a Work Order prior to the work being scheduled?

  • 26.11.Is there a stock procurement procedure in place?

  • 26.12. Is there an emergency parts ordering procedure in place?

  • 26.13. Are lead times recorded and considered in the procurement process?

  • 26.14 Are the contractors parts ordering procedure known by the mine?

  • 26.15. GOLD Are stock outs measured?

  • 26.16. GOLD Are late deliveries measured?

  • 26.17. GOLD Is a computerised stores management system in place for all stores?

  • 26.18. GOLD Is the stock procurement procedure adhered to?

  • 26.19. GOLD Are stock levels evaluated on a 6 monthly basis to ensure current consumption is aligned with spares requirements.

26. MAINTENANCE - SPARES SHARED SERVICES

  • 26.1.Is a critical spares list in place for every machine on site?

  • 26.2.Is the critical spares list reviewed and updated?

  • 26.3.Is a person responsible for spares issuing and monitoring of spares?

  • 26.4.Is a person responsible for spares ordering?

  • 26.5.Are stores facilities adequate for the required spares (sufficient stores with security, ventilation, shelving etc)

  • 26.6.Are all stores and spares personnel adequately trained to manage, issue and monitor spares

  • 26.7.Are minimum stock levels determined?

  • 26.8.Are stock levels maintained according to the spares requirements?

  • 26.9.Are parts costs reconciled and reported?

  • 26.10.Are planned materials (parts) ordered and linked to a Work Order prior to the work being scheduled?

  • 26.11.Is there a stock procurement procedure in place?

  • 26.12. Is there an emergency parts ordering procedure in place?

  • 26.13. Are lead times recorded and considered in the procurement process?

  • 26.14 Are the contractors parts ordering procedure known by the mine?

  • 26.15. GOLD Are stock outs measured?

  • 26.16. GOLD Are late deliveries measured?

  • 26.17. GOLD Is a computerised stores management system in place for all stores?

  • 26.18. GOLD Is the stock procurement procedure adhered to?

  • 26.19. GOLD Are stock levels evaluated on a 6 monthly basis to ensure current consumption is aligned with spares requirements.

27. MAINTENANCE - PERFORMANCE MEASUREMENT

  • 27.1.Has a review been conducted to determine performance measurement KPIs?

  • 27.2.Are the approved KPIs documented and distributed to all involved?

  • 27.3.Are the KPIs formally reported on?

  • 27.4.Is there a formal Root Cause Failure analysis process in place?

  • 27.5.Are chronic failures identified and addressed, i.e. is there a continuous improvement action plan in place?

  • 27.6.Is the equipment Availability measured and analysed (trended)?

  • 27.7. Is the Planned Vs Unplanned Work Ratio documened and reported?

  • 27.8. Is there a Backlog board in place?

  • 27.9.  Is the backlog board updated daily?

  • 27.10.  Is a weekly maintenance plan issued to the maintenance staff (supervisors & artisans) prior to the week commencing?

  • 27.11. GOLD Is the equipment MTTR measured and analysed (trended)?

  • 27.12. GOLD Is the equipment MTBF measured and analysed (trended)?

  • 27.13. GOLD Is the equipment Labour utilisation measured and analysed (trended)?

  • 27.14. GOLD Are top ten cost items identified and reported per machine type per month

  • 27.15. GOLD Is the root cause failure programme resulting in improved reliability and/or reduced costs.

  • 27.16. GOLD Are Planned versus Unplanned works ratios understood and proactively managed.

  • 27.17. GOLD Are top ten downtime items identified and reported per machine type per month

28. OPERATIONS - STANDARDS

  • 28.1.Have work place standards been documented?

  • 28.2.Have they been approved by the responsible manager?

  • 28.3.Have the standards been communicated to all applicable personnel?

  • 28.4.Are formal inspections conducted to measure compliance with the standards?

29. OPERATIONS - SURVEY

  • 29.1.Are survey plans available for all areas of development?

  • 29.2.Are special instructions noted on plans where applicable?

  • 29.3.Do all relevant departments approve plans prior to their final release?

  • 29.4.Are the survey plans issued to all necessary personnel?

30. OPERATIONS - KPIs

  • 30.1.Have Key performance indicators been determined and documented?

  • 30.2.Do all pieces of equipment been assigned KPIs?

  • 30.3.Have the KPIs been communicated to all personnel involved?

  • 30.4.Are KPIs measured and formally reported on?

  • 30.5. GOLD Is action taken when KPIs not to expectation?

  • 30.6. GOLD Do individuals receive feedback regarding their daily and monthly performance and any related deficiencies.

31. OPERATIONS - SYSTEM OVERVIEW

  • 31.1.Is there a system in place for conducting unbiased audits?

  • 31.2.Are previous Audit reports available?

  • 31.3.Have Action Plans been established, based on the findings of these Audits?

  • 31.4.Have the above action plans been approved and implemented?

  • 31.5. GOLD Is system performance tracked and trended on a monthly basis

  • 31.6. GOLD Is the system used as a tool for continuous improvement

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.