Title Page
-
Conducted on
-
Prepared by
-
Site / Job number
-
Plot / Unit Numbers
System Information
System Information
-
Boiler Make
-
Boiler Model
-
Boiler Serial number
-
Boiler Installed by
-
Boiler Commissioned by
-
Cylinder Make
-
Cylinder Model
-
Cylinder Serial Number
-
Cylinder Installed by
-
Cylinder commissioned by
Commissioning Documents Completed
-
Boiler
-
Cylinder
-
CP12
-
MVHR
Controls
-
Room Stat Fitted
-
Make
-
Model
-
Location fitted
-
Central Heating Programmer Fitted
-
Make
-
Model
-
Location Fitted
-
Hot Water Programmer
-
Make
-
Model
-
Location fitted
System Checks
-
System Cleansed / Flushed By
-
Amount of cleanser used (litres)
-
Inhibited by
-
Amount of inhibitor used (Litres)
-
undefined
-
Flow restrictors fitted (if applicable)
-
Locations
-
Bath Tap Set to 48 Degrees
-
TRV’s & Lockshields fitted and left in OPEN position
-
Room Stats and programmer fitted
-
ALL radiators up to temperature (set to 700c on boiler)
-
Hot water temp – Set unvented cylinder stat to 4 (four = 600c) located within electrical box – front panel
-
Hot water temp – Combi boiler – Set to 600c
-
Stop cock labelled
-
Primary circuit from boiler to cylinder insulated, including all visible pipework
-
Hot & cold water pipe from cylinder insulated a minimum of 1m-If hot return applicable – All pipework insulated and to be cable tied - NO Ducktape
-
Gas pipe sleeved
-
Mains cold water feed to cylinder – lever valve labelled
-
All cold water mains insulated (within floor / ceiling voids) – ie adjacent to HW pipe
-
Outside tap insulated and service valve to tap labelled
-
Washing machine valves correctly indexed (hot & cold) - capped if applicable
-
Inline scale reducer fitted to boiler / cylinder
-
External cage fitted to PRV & TPRV from cylinder (above gully or trap if possible)
-
Flow rates & temperature set @ 480c – Bath taps NOT to exceed this temp
-
Condense to boiler fitted correctly
-
Two (2) drain offs fitted to flow & return under boiler
-
PRV & TPRV – Tundish visible min 300mm from bottom of TD to 1st bend (G3 regs). PRV fitted at 1500mm above FFL(ext) & turned back to wall (block of flats)
-
If high temp pipework fitted between soil stack & tundish – is a HEP V O trap fitted
-
Gas cooker isolation labelled
-
Water Butts Installed & level
-
Filling loop - capped & secured to boiler
-
Gas meter labelled with correct house / flat number
-
If 2nd AECV - is it labelled, acessible, test gas point visible & directional tape fitted
-
If gas run is vertical (floor 2 ceiling & boxed in) is there sufficient ventilation
-
Gas pipework sleeved must be sealed at one end
-
Correct working pressure at meter (CP12)
-
Tracpipe ® fittings must have silicone tape on pipe & joint
-
Visual Inspection of Flue & Gasket / Seal
-
All compression fittings accessible