Title Page
-
Project Title (Job type - Name - Address)
-
Conducted on
-
Prepared by
-
Location
External Work
-
Is the heat pump level
-
Is the base suitable, Solid level base to take weight, or on gravel soak away
-
Are the external pipe extrusions sealed
-
Have clearances been met as per manufactures instructions
-
Are pipes correctly insulated bonded and sealed with 19mm wall suitable for external conditions, i.e primary pro, HT or external trunking
-
Anti-vibration feet or wall brackets with Anti-vibration mounts installed
-
Isolation valves on Flow and return for ASHP including strainer valve
-
Does the condensate terminate correctly/soak away to prevent future hazards
Internal Checks
-
Are internal pipe intrusions sealed
-
Is the pipe work insulated and sleeved the entire depth of the wall
Removal of old sytem
-
Evidence of boiler removal and previous flue hole brick up
-
Confirm that the gas pipe has been capped correctly to GSE regs
-
Has the previous heating electrical supply been isolated and made safe?
-
Confirm removal of existing HW cylinder and cold water poly tanks
-
Let by and tightness test recorded on TPI and sent to manometerresults@lowribeckfield.co.uk
-
Record Gas safety report of gas installation remaining (certificate on TPI)
Cylinder installation
-
Isolation valve installed above control group
-
Confirm Discharge D1 is max 600mm to tundish
-
Confirm Discharge D2 is min 300mm before first bend
-
Picture of termination of D2 pipework inc required cage
-
Picture of Cylinder and surrounding pipework, Lagging and insulation done correctly to a high standard
Commissioning
-
System parameters set up, Flow temperatures set up with weather curve
-
System flushed
-
System balanced, vented and ensured system gets to temperature
-
Cylinder hot water temperature set to min 50℃ (legionnaires cycle set up if below 55℃)
-
System controls, thermostats, programmers and safety controls all explained to the client/homeowner/tenant/landlord (picture taken of programmer set up)
-
Benchmark filled out for heatpump & recorded
-
Benchmark filled out for cylinder and recorded
-
ASHP data badge
-
Cylinder data badge filled out