Information

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

HIRAC (Hazard Identification Risk Assessment and Control)

  • Has a project specific Risk Register or similar document been prepared?

  • Is the Risk Register current and reviewed?

  • SWMS or similar are suitably documented are- compliant, reviewed and Communicated to all relevant workers, and demonstrate evidence of worker participation/consultative process in their development

  • Do SMWS identify plant management requirements, including tag test, maintenance and fualty equipment requirements

  • Are permits included for activities such as excavations, hot works, confined space entry, heights/harnesses, isolation and energisation of electricity etc.

  • Are safety-related records suitably managed on site (e.g.; risk assessments, maintenance and inspection records, testing, SDS, permits, and traffic management plans)?

  • Has a design risk assessment been developed and included in the documented project risk assessment process (within safety plan or risk register, SMWS etc)?

  • Are there adequate arrangements to coordinate subcontractor activities?

  • Principal Contractor and trade works are being carried out in accordance with the relevant legislation, regulations, codes of practice and, as applicable, Australian & National Standards?

  • Mobile plant, other plant & equipment is fit for purpose and maintained as per manufacturer's requirements?

Consultation, Induction, Training and Competency

  • Have all workers completed a site induction

  • Have white cards been provided by all workers

  • Have all visitors been inducted to site and signed off as competent

  • Have Site safety rules been communicated at site induction and recorded

  • Are neighbouring properties notified of works that will impact them , noise, vibration, road closures etc

  • Have all workers received WHS training such as chemical management, hazard management, reporting requirements, manual handling etc

Emergency Planning and Response

  • Are contact details for key people available to all workers

  • Is required PPE available

  • Do workers understand what is required for a notifiable incident and reporting requirements

  • Do induction records specifically identify that the worker received the appropriate information

  • Emergency response plan displayed & understood by all employees

  • Evacuation procedures practised regularly?

Chemical Management

  • Does the site have a hazardous substance register and SDS for all chemicals on site

  • Do subcontractors that handle hazardous chemicals have a hazardous substance register and SDS for all chemicals- on site

  • Hazardous substance register complete and available

  • Are eye wash stations/showers easily accessed

Fire Management

  • Extinguishers recently serviced? (Check 6 monthly punch mark on tabs.)

  • Are fire extinguishers compliant for area and suit possible combustibles

  • Extinguishers in place, clearly marked for type of fire?

  • Extinguishers clear of obstructions?

First Aid

  • Has First Aid facilities and planning been based on a First Aid risk assessment (WHS CoP First Aid)?

  • Are suitable First Aid facilities established in accordance with risk assessment and/or regulatory requirements?

  • Is First Aid signage in place including names of First Aiders suitably displayed/ communicated?

  • Is the First Aid training current for nominated First Aiders?

  • Are First Aid facilities suitably stocked and in clean condition?

Facilities

  • Is there fresh drinking water, amenities and lunch rooms provided for workers (WHS CoP Managing Work Environment & Facilities)?

  • Are toilets provided if so are they clean, have hand washing facilities and are stocked with soap and tiolet paper

Electrical Management

  • RCD and earth leakage protection is afforded to all electrical boards, portable generators (and earthing is as necessary)?

  • Is testing and tagging in accordance with AS3760 requirements for all 240 volt electrical items (plant, equipment, leads, etc)?

  • Are flexible electrical leads and construction wiring properly protected, elevated and less than 30 metres in length?

  • Are temporary DB's correctly marked (origin/electrical warning signage), secured, RCD protected and tested and tagged?

  • Is there a suitable documented LOTO (lockout and Tag out)process? If so, has it been suitably implemented?

  • Have overhead and underground power services been suitably identified and controlled (consideration for floating of mobile plant to and from site, mobile plant movement on site, excavations, permits etc)? Dial Before you Dig contacted etc

Manual Handling

  • Manual Handling risks have been identified and suitably controlled, including the use of mechanical devices, team lifting, safe unloading of vehicles etc?

  • There are documented processes for Manual Handling communicated to workers? (Induction, Training, SWMS etc

Mobile Plant and Traffic management

  • Traffic movement has been assessed and Traffic Management Plans and controls established and implemented?

  • Persons implementing and inspecting Traffic Management Plans and signage are suitably trained?

  • Traffic Management Plans for external use have been approved by the relevant authority?

  • Movement of traffic is in accordance with the approved TMP?

  • Are spotters being used for internal traffic movement as necessary?

Mobile Plant

  • Is mobile plant entering and working on site subject to a risk assessment process? If so, explain process.<br>Is there evidence that plant maintenance and repair is current in accordance with manufacturer's requirements?<br>

  • Is mobile plant being operated by suitably competent (trained, skilled &/or experienced) persons, including any need for formal licensing such as forklift?

  • Is mobile plant entering and working on site subject to a risk assessment process? If so, explain process.

  • Is plant being operated safety and properly (warning devices working, flashing rotating light, operators wearing seat belts)?

  • Is plant movement on site suitably controlled (plant, vehicles and pedestrians isolated)? Include reference to internal traffic management planning and speeds.

  • Is the item of plant suitable for the tasks being performed (for example, excavators being used as cranes are suitably fitted with charts in cabins, burst valves, manufacturer fitted lifting points etc)

  • Are there appropriate records of daily mobile plant checklist or pre starts being conducted?

  • Do High-Risk plant have a compliant SWMS

Excavation

  • Are excavation risks suitably identified, rated and controlled within the documented risk register and risk assessments (SWMS/JSA/SWP/SOP etc)?

  • Are excavations suitably benched, battered or shored? (mandatory for excavations over 1500mm)

  • Have geotech's reports been provided for excavations, as required?

  • Suitable barriers, signage and/or fencing has been established in and around the excavations in accordance with statutory requirements?

  • Are trenches regularly inspected by competent persons to ensure controls remain adequate? (this includes after inclement weather)

  • The excavations have a safe means of access and egress and any confined space aspects suitably identified and controlled?

  • Risks of movement of mobile plant in and around trenches and other excavations have been suitably identified and controlled?

  • Possible water sources have been identified and control measures implemented to remove the risk of flooding and/or engulfment due to water infused soil instability?

PPE

  • PPE has been supplied and is suitable for the task?

  • PPE is being suitably maintained and used correctly (include workers awareness of these requirements)?

  • Are workers observed wearing correct PPE for the tasks being completed?

Falls

  • Are all areas where there is a risk of a person falling more than 2 metres identified and controlled in accordance with hierarchy of controls (refer CoP Falls in Workplaces)

  • Are all areas where there is a risk of injury to a person falling identified and suitably controlled?

  • Are risks of falling objects identified, assessed and suitably controlled? (Includes protective structures such as roof guarding, scaffold decks, crash decks etc).

  • Are reinforcement bars capped or other protrusions/impalement hazards suitably controlled?

  • Is there a documented work at heights process which is to be controlled through formal training for workers, correct testing of height access equipment (harness/shackles/clips etc)?

  • Is there evidence of compliant practices when working at heights (includes registers, training, evidence of inspection, permits etc)?

Environment

  • Are Stockpiled materials protected? Are dust suppression measures in place?

  • Are adequate erosion control measures in place? Are silt controls in place (fencing, hay bales, drains etc)

  • Are there suitable noise and vibration controls in place? (EPA Guidelines for noise in the workplace)

  • Are sediment control basins in place and if so, are they being correctly monitored?

  • Storm water inlet protection provided and maintained?

  • Are water bodies suitably protected?

  • Are heritage, cultural and flora/fauna considerations applicable to the project, and if so, are they being correctly

Site Security and Protection of the Public

  • Is the site suitable protected by barriers and/or fencing?

  • Are access and egress risks suitably controlled, including warning signs/speed signs at each entry/exit (as applicable)?

  • Is there sufficient effort to discourage/stop unauthorised entry to the site commensurate with the level of public risk?

  • Are construction materials, waste, plant and equipment suitably stored within the site boundary (no public risk)?

  • Are surrounding roadways and footpaths clear (of mud/site materials)?

  • Are the public adequately protected from project risks such as open excavations, falling objects, traffic etc?

Scaffold

  • Are all the toe boards in place

  • Is the scaffold tag in date

  • Are the deck planks in there specified location

  • Is all excess scaffold material stored away from the construction site or in need of removal

  • Are the any gaps greater than 250 mm if so are they protected to prevent workers falling through

Housekeeping

  • Access and egress to and around site is clear and unhindered?

  • Walkways are clear, including scaffold decks? (site is tidy, no slip and trip hazards)

  • Waste is sufficiently managed and segregated where possible? Are bins provided, if so are they managed so that rubbish cannot be blown out

  • Task lighting and access lighting is suitable?

Sign Off

  • On site representative

  • Auditor's signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.