POS Manager Name:
-
Client:
-
Location
-
MAP & PICTURES (of Site Visit/Client)
-
Job Details:
General
-
Are all permits present e.g. ALO permit to work. permit to dig/isolations and cover the work location?
-
Comment / Action Taken:
-
If ALO works, is there an ALO Planner/ALO Responsible Manager on call identified?
-
Comment / Action Taken:
-
Is there a Lift/Plant Planner on site or on-call identified?
-
Comment / Action Taken:
-
Have all personnel been briefed on following:
-
Comment / Action Taken:
-
Induction
-
Work Package Pack (WPP)
-
Task Brief
-
SCAN/picture (date&signatures)
-
Have you briefed all MOs, MC/CCs and slingers on the content of the OTP and Lift Plan[s]?
-
Comment / Action Taken:
-
Is enough DECT Duplex communications available and working correctly? (Radio or hand-signal alternatives can only be used post start of work) and/or contingencies documented?)
-
Permanent, Semi-permanent or Temporary RRAP(s) in a good condition, secured and of an approved type?
RRV #1
-
RRV (number)
-
Are all OTP documents in place i.e. Plant pack with OTP Plan, Lift plan[s], MC/CC Checklist (F015)?
-
MC/CC Checklist (F015):
-
F015 must be completed by MC/CC and SCANNED(pictured) by POSM before starting any operation:
-
Plant pack with OTP Plan
-
TXM Plant WEBLINK:
-
Lift plan[s]
-
SCANNED/pictured if not TXM Plant produced
-
TXM Plant WEBLINK:
-
ISO permit
-
Relevant permit must be SCANNED/pictured if applicable
-
Are this RRV OTP MC/CCs and MOs Competence requirements checked and correct as planned?
-
MC/CC Phone number
-
MC/CC sign:
-
MC/CC NCCA (Sentinel2) card picture
-
OP Phone number:
-
OP sign:
-
Operator's NCCA (Sentinel2) card picture:
-
Slingers/Others involved names if applicable
-
Slingers/Others involved NCCA (Sentinel2) card picture if applicable
-
POSM sign if applicable:
-
Have personnel for this RRV been briefed on following:
-
SSoW pack
-
SCAN/picture (date&signatures)
-
Task Brief
-
SCAN/picture (date&signatures)
-
Have this RRV Movement Limiting Devices been checked and operate as expected? Are keys available to lock once set?
-
Has a functionality test been completed and if any defects, the engineer or on call engineer contacted to repair?
OTP & Attachments
-
Are all OTP, attachments, trailers and any other Plant as identified in the plan? Are all Plant, attachments or lifting accessories fit-for-purpose and all documents such as EACs present? Do the log-books indicate all are free from safety critical defects?
-
If lifting accessories are being used, do they have a unique number, tare weight and WLL/SWL displayed, and is the Thorough Examination Cert in date and where required, safety catches fitted (FIBC)?
-
OTP
-
RRV (number) delivere/parked on site
-
EAC link
-
RRV (number) delivere/parked on site
-
EAC link
-
RRV (number) delivere/parked on site
-
EAC link
-
RRV (number) delivere/parked on site
-
EAC link
-
RRV (number) delivere/parked on site
-
EAC link
-
RRV (number) delivere/parked on site
-
EAC link
-
Attachments
-
Attachment
-
Attachment
-
Attachment
-
Attachment
-
Attachment
-
Attachment
Core Activity Timings
-
Off track work/preparation started
-
Took Possession
-
Work Site granted to ES
-
First ISO permit issued (if applicable)
-
OTP on-tracked & brake tested
-
First (only) RRV started activity
-
All work complete
-
Last (only) RRV off tracked
-
All on-track and Construction Plant secured and protected from vandals?