Information
-
Job Site/Job Number
-
Location
-
Conducted on
-
Prepared by
-
Inspection Type?
- Post Award
- Pre Mob Pile Installation
- Pre Mob Pile Chipping
-
Were both inside and outside perimeter of job site inspected for utilities?
-
Utilities?
-
Location
- Inside perimeter
- Outside perimeter
-
Source
- Overhead
- Underground
-
Type
- Cable
- Electrical
- Fiber
- Gas
- Phone
- Sewer/Storm Drain
- Water
- Other
-
Photo(s)
-
Job site fenced?
-
Photo(s)
-
Photo(s)
-
Installation Conflicts?
-
Type
- Batter piles
- Existing buildings
- Existing footers
- Fences
- Overhangs
- Trees
-
Photo(s)
-
Access restrictions?
-
Type
- Limited space for steel
- MOT (parked cars)
- Poor access/egress
- Utilities
- Other
-
Sketch
-
Photo(s)
-
Special trucking needs?
-
Issue?
- Gate size
- Lot size
- Metered parking
- Permits
- Ramps
- Other
-
Photo(s)
-
Were soil borings reviewed?
-
Contact PM for copy of report.
-
Level working grade?
-
Improvements recommended...
- Compact
- Grade
- Roll
-
Photo(s)
-
Stable working grade?
-
Improvements recommended?
- Crane mats
- Road plates
- Rock
- Other
-
Working grade elevation?
-
2" water connection on site?
-
Photo(s)
-
Solutions recommended?
- 3/4" to 2" adapter
- Off site hydrant
- Water truck
- Other
-
Add signature
-
Were both inside and outside perimeter of job site inspected for utilities?
-
Utilities?
-
Location
- Inside perimeter
- Outside perimeter
-
Source
- Overhead
- Underground
-
Type
- Cable
- Electrical
- Fiber
- Gas
- Phone
- Sewer/Storm Drain
- Water
- Other
-
Photo(s)
-
Toilet(s) on site?
-
Add media
-
Job site fenced?
-
Photo(s)
-
Installation Conflicts?
-
Type
- Batter piles
- Existing buildings
- Existing footers
- Fences
- Overhangs
- Trees
-
Photo(s)
-
Access restrictions?
-
Type
- Limited space for steel
- MOT (parked cars)
- Poor access/egress
- Utilities
- Other
-
Sketch
-
Photo(s)
-
Special trucking needs?
-
Issue?
- Gate size
- Lot size
- Metered parking
- Permits
- Ramps
- Other
-
Photo(s)
-
Were soil borings reviewed?
-
Contact PM for copy of report.
-
Level working grade?
-
Improvements recommended...
- Compact
- Grade
- Roll
-
Photo(s)
-
Stable working grade?
-
Improvements recommended?
- Crane mats
- Road plates
- Rock
- Other
-
Working grade elevation?
-
Benchmarks?
-
Sketch
-
Photo(s)
-
2" water connection on site?
-
Photo(s)
-
Solutions recommended?
- 3/4" to 2" adapter
- Off site hydrant
- Water truck
- Other
-
Layout?
-
Is there enough to begin production?
-
Type of marker...
- Flags only
- Nails
- Rebar
-
Photo(s)
-
Cages?
-
Are there enough to begin production?
-
How many?
-
Photo(s)
-
Contact Malta and/or iron-work foreman.
-
Test pile locations?
-
Sketch
-
Photo(s)
-
Add signature
-
Are there enough exposed piles to be productive?
-
How many?
-
Photo(s)
-
Are the pile caps formed?
-
Photo(s)
-
Is a tower crane being erected?
-
Can work be completed simultaneously with crane erection?
-
Photo(s)
-
Photo(s)
-
Is the excavation over 4'?
-
Is there access to a 4 gas meter for atmosphere testing?
-
Proper access/egress?
-
- Ladders
- Ramps
- Other
-
Photo(s)
-
Photo(s)
-
Is there accumulated water in the excavations?
-
How deep?
- 0" - 3"
- 3" - 6"
- Above 6"
-
Photo(s)
-
Is a water pump on site?
-
Are there any utilities in the excavation(s)?
-
Type
- Cable
- Electrical
- Fiber
- Gas
- Phone
- Sewer/Storm Drain
- Water
- Other
-
Photo(s)
-
Is there enough room for equipment?
-
Photo(s)
-
Is there any material and/or equipment within 2' of excavation?
-
Photo(s)
-
Are pile butts being removed?
-
Are there known weights for the pile butts?
-
Weight?
-
Contact your Superintendent.
-
Contact your Superintendent.
-
Is the proper rigging available?
-
Contact your Superintendent.
-
Contact your Superintendent.
-
Add signature