Information
-
Project Name
-
Powercor CitiPower References
-
Plan Number
-
Client Contact and Phone Number
-
Location
-
Prepared by
-
Personnel
-
Date Installed
-
If installation date is after target date please provide reason:
Inspection Item Guidelines
INSTALLATION
-
Coverguards installed ≥ 2.4m above ground
-
Comments
-
Cover slab overlapping bottom of coverguard
-
Comments
-
U/G cable warning sign attached
-
Comments
-
Marker tape installed 300mm below ground for all open trenching
-
Comments
-
Pit level and presents no tripping hazard
-
Comments
-
Pit installed in concrete footpath with 150mm concrete encasement.
-
Comments
-
Lead-in conduit(s) installed in pit
-
Comments
REINSTATEMENT
-
Trench back filled and compacted with topsoil and grass seed where required
-
Comments
-
Site clean and level with rubbish and spoil removed
-
Comments
AS-BUILT DETAILS
-
Depths recorded
-
Comments
-
Route deviations > 200mm recorded
-
Comments
-
Offsets and cable running measurements accurate to 100mm
-
Comments
-
Distance to a permanent reference point recorded (e.g. Title boundary or crossing intersecting road)
-
Comments
-
As built plan returned to Powercor within 2 days of installation
-
Comments
-
The above project complies with all relevant Powercor Technical Standards at the time of installation (audit)
-
Job Title
Powercor Use Only
-
Received By
-
As-built plan to Powercor/Citipower Standard ( Y / N )