Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Job Number Miles College
-
Weather<br>Low: 67<br>High: 84
-
Site Hours 6:30-4
-
Number of employees on-site Joey and 13 men
-
Overall days production
-
Description of work Framed student center lobby entrance wall 1st floor and multi purpose east wall. Started setting trusses over south end of student housing and bolting 2x8 ledger for corridor joists. Joey started laying out 4th floor.
Media
-
Site pictures
-
We're there any delaying factors if so explain
-
We're there any injuries
-
We're all tools locked up and stored properly
-
Change orders
-
We're there any safety violations
Equipment on site
-
Man Lift
-
Skytrac
-
Crane<br>
-
Are there any pieces of equipment down
-
Paul Cox