Site Safety Audit
Pre-Construction Steps
-
Site Plan/Field Sketch showing excavation limits or bore path.
-
Excavation OR Horizontal Directional Drilling "PERMIT" APPROVED?
-
Pre-Excavation/Boring meeting with Locator Service, High Priority Utility Owners (Fiber, High Pressure Gas, Water Sewer)?
-
Area White Lined per drawings or plan.
-
Utility Locate Request (CALL Before You Dig 811) sent 3 business days prior.
-
Utility Locate Request Ticket Current Within 10 Days?
-
Private Utilities Located?
-
ALL Utilities Marked Clearly (Not Faded) per Uniform Color Code & Marking Guidelines?
-
Utility Markings Photographed?
-
Site Checked for visible signs of utilities that may have been missed (Pedestals, Risers, Meters, Trench Lines)?
-
Verify service feeds from buildings have been located?
-
Markings added to drawings?
-
Toolbox Talk and/or AHA with all personnel on site?
-
Emergency Action Plan communicated to all personnel?<br>Gas Line Hit = CALL 911-EVACUATE AREA IMMEDIATELY! Then from safe distance call Supervisor AND Gas Company!<br>Electrical Line Hit = Stay in Cab - Ground Workers use shuffle or bunny hop methods to safe area!<br>Phone, Water, Cable, Water, Sewer, etc. = Call Supervisor Immediately!
Pre Work Photographic or Video Documentation:
-
Utility Markings?
-
Pedestals, Risers, Meters, etc?
-
Sidewalks, Driveways, Streets, Curbs for cracks, condition and pre-existing damage?
-
Trees, Shrubs, Flower Beds?
-
Mail boxes, Street Signs, Monuments?
Traffic Control:
-
Traffic Control Plan Developed per industry standard (MUTCD)?
-
Traffic Control Plan Approved by City?
-
Traffic Control Devices installed per plan?
-
Traffic Control Devices adequate?
-
Traffic Control Plan requires Field Modification to accommodate site hazards?
-
Traffic Control DevIces maintained (Clean, Faded, Blown/Drove Over, etc.)?
-
Traffic Control Devices taken down when not needed or project completion (Extended breaks, Done for the Evening)?
Personal Protective Equipment:
-
ANSI Approved High Visibility Outer Clothing Worn and in good condition?
-
ANSI Approved Hardhat Worn Properly (No Ball Caps, Brim Forward) and in Good Condition?
-
ANSI Approved Safety Glasses by ALL Personnel?
-
Minimum Short Sleeved Shirt and Long Trousers Worn?
-
Heavy Duty Work Boots WORN Properly (Laced up) and in GOOD Condition?
-
Appropriate Work Gloves Worn?
-
Proper Lifting procedures followed for manual material handling?
Equipment Safety:
-
ALL equipment and tools inspected prior to use?
-
Owner's Manual for all equipment readily available?
-
Operators have been trained in Safety Features and Procedures?
-
Have the areas around site excavations been cordoned off?
-
Has a height permit issued as well as a excavation permit?
-
Are the operatives working in pairs around or inside the excavation?
-
Were the utility drawings checked prior to excavations being started? Ask to be shown drawings and comment
-
Does the excavation permit show instructions for scanning the area prior to excavating?
Section 7.0 Mewps and Plant
Section 8.0 Skips & Waste
Section 9.0 - Fire Prevention & Hazardous Materials
Section 10.0 PPE & Noise
Section 11.0 Electricity
Section 12.0 General
-
Any general comments, observations, or concerns about this site?
-
Add signature
Site Administration
Section 1.0 Management Poster
-
Has the management poster been kept up to date?
-
Section 2.0 Permits
-
Have all permits been completed correctly with correct controls?
-
Have all hot works permits been closed off correctly?
Section 3.0 Inductions
-
Check Stats Inspection Folder. Have all the inductions been filled in correctly?
-
And uploaded? (large sites only)
-
All the companies mentioned in inductions have been mentioned in the Rams Log?
Section 4.0 Rams Check
-
Pick a random contractor. Can they be seen to be working within their rams?
-
Has a rams review form been done?
-
If there were any discrepancies were they sent back to the contractor to re-submit?
Section 5.0 Site Tasks
-
Are there any outstanding tasks?
Section 6.0 MEWP/Plant Inspections
-
Are the mewp inspection forms being completed correctly by all operatives using them?
-
Are all the LOLER certificates displayed on the Management Poster incl forklift
Section 7.0 Weekly Site Audits by Site Manager
-
Have the weekly self site audits been done?
-
Have all the remedials been actioned?