Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Inspection check list

  • Drawing attached and mark up of area

  • Brickwork is to the standard and quality set out in the approved sample panel.

  • Blockwork is to the standard and quality set out in the approved sample panel.

  • Wall ties, l-shaped ties, head restraints and other steel sundries are installed correctly .

  • All horizontal and vertical DPCs are installed correctly and to specification.

  • Membranes, weep vents and/or air bricks are installed correctly.

  • Brickwork and blockwork is set out correctly to position, line and gauge.

  • All openings are correct to current drawings and have been set to the height and position required

  • Have all cavities been cleaned and are free from debris.

  • Are all concrete or steel lintels installed correctly to position and height.

  • Are all heads, columns and other abutments of walls closed and sealed as per architects requirements.

  • DPCs are installed in the correct heights and positions.

  • Acceptance of trial panel

  • Air temp check +3C and rising

  • Visual inspection and picking of reclaimed bricks

  • Type of bond

  • Installation of reinforcing expanded metal meshwork

  • Position and installation of movement joints

  • Wall Thickness

  • Ground level change in brick

  • Type of pointing

  • Head restraint ties are installed correctly

  • Curing / Protection Method

  • Cleanliness of facing brick

  • Photos are available for this inspection or handover.

This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining the sub-contractors responsibility until practical completion has been achieved.

  • Signed on behalf of Sub Contractor

  • Signed on behalf of Main Contractor

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.