Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Level
- Ground Level
- Level 1
- Level 2
- Level 3
- Level 4
- Level 5
- Level 6
- Level 7
- Level 8
- Level 9
- Level 10
- Level 11
- Level 12
- Level 13
-
Elevation
-
Section
-
Gridlines
-
Core / Apartment (Apt)
Setting out - Gridline/Datum
-
Drawing ref number:
-
Has all SFS been installed at this location?
-
Is SFS set out correctly to gridline and/or datum?
Deflection
-
Has 25 mm minimum been allowed for deflection?
-
Has the correct deflection brackets been installed?
Head Track
-
Have the correct heavy duty tek fixings 2No 6.5x45 TAPCON ANCHORS been used to fix to the concrete?
-
Are head tracks fixed to the substructure as per detail?
Studs
-
Have the studs been installed to the correct centres, maximum 600 mm?
-
Have the correct fixings 2No 5.5dia TEK SCREWS been used?
Base Track
-
Have the correct heavy duty tek fixings 2No 6.5x45 TAPCON ANCHORS been used to fix to the concrete?
-
Fixings to the substructure as per detail?
Sheathing Board
-
Typical board fixing to SFS
-
Is the sheathing board installed a Siniat Weather Defence?
-
Have fixings self drilling screws been used to fix the board onto SFS?
-
Are the self drilling screws at maximum 600 mm centres?
-
Are the self drilling screws at a minimum of 13 mm and maximum 20 mm from joints?
-
Are all the joints sealed with Fire Rated Silicone Sealant or Weather Defence Joint Tape?
Sign Off
-
On behalf of Jessella
-
On behalf of the Client