Documentation
-
-
Is the Construction phase H&S Plan up to date?
-
Are all RAMS up to date?
-
Site induction & signing in book up to date?
-
Is D&A Testing being carried out at Induction?
-
Why not?
-
Permits to work and safety procedures in place for hot works, confined spaces, and live electrical works?
-
Any specific certificates ie plant operators, on file?
-
Is an F10 required and displayed?
-
Is all information on the F10 correct?
General
-
-
General site tidyness, trailing leads, materials?
-
Waste Management?
-
Appropriate safety signs in place?
-
Site security, gates, hoarding, protection of the public?
-
Flammable liquids/gasses locked away, materials stored correctly?
-
Sufficient light for tasks?
-
Access to work areas?
Scaffolding
-
-
Scaffold inspections up to date/scafftag, incomplete scaffolds blocked off & signed?
-
Scaffold boards; condition?
-
Guards/netting etc in place?
-
Clips or fixings - potential for injury?
-
Tubes a trip hazard?
-
Ladder, condition, ladders secured?
- Good
- Fair
- Poor
- N/A
-
Mobile towers, correctly assembled, used in safe locations?
-
Exposed edges?
-
Steps/hop-ups being used correctly?
-
Other hop-ups being used safely?
Welfare
-
-
Toilet facilities kept clean, sufficient toilet paper, soap, paper towels?
-
Hot and cold running water, drinking water?
-
Rest facilities clean?
-
Facilities to boil water, prepare/eat meals?
-
Facilities for drying clothes in wet weather, facilities for storing/changing clothes?
Personal protective equipment
-
-
Standard PPE being worn? Boots, hard hats, hi viz, gloves, glasses?
-
Extras - goggles, ear defenders etc?
-
Mandatory PPE zones?
Electricity
-
-
Battery operated or 110V?
-
PAT testing records, date marked or tagged on equipment?
-
Trailing leads?
-
Cable damage?
Plant / Equipment
-
-
Lifting equipment, including MEWPs and Cherry Pickers, cranes, hoists, marked with SWL, competent person available for lifting operations, test certificates available?
-
Compressors, generators, mixers, saws, drills, guards, used in safe location, suitable PPE worn?
-
Are Lasers being used on site?
-
Are they Class 1 or Class 2?
-
Are extra safety precautions in place for this class of Laser?
-
Work must be stopped immediately until the correct safety precautions are in place.
Fire Precautions
-
Is there a fire detection system in place?
-
Emergency exits suitably signed, kept clear of obstructions, assembly point signed?
-
Fire extinguishers available, inspected?
-
Emergency plans, sufficient detail, location marked on plan?
-
Are Hotworks being carried out on site?
-
Is there a Hotworks Permit System in place? (If no, work must stop immediately)
-
Are the works being carried out in accordance with the permit?
-
Is the correct fire extinguisher being used?
First Aid
-
-
First Aider or Appointed persons on site, deputies in case of absence?
-
First Aid box stocked?
-
Firat Aid point easily seen?
-
Location of nearest A&E hospital known?
-
Is there a Defibrilator on site?
Traffic Management
-
-
Is the works area seperated from plant/vehicles?
-
Are there padestrian routes?
Sundry
-
Are all other QMUL site rules being followed?
-
Is the QMUL issue reporting QR Code posted and visible?
-
Any other information