Job number
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Type of works
-
Type of traffic control being used
- 2 way Lights (40mph and below)
- 2 way Lights (50mph and above)
- Multiphase Lights (40mph and below)
- Multiphase Lights (50mph and above)
- Static Stop/go (40mph and below)
- Static Stop/go (50mph and above)
- Mobile Stop/go (40mph and below)
- Lane Clousure (30 mph)
- Lane Clousure (40 mph and above)
- Road Closure and Diversion
- Road Clousure, No Diverion
- Pedestrian management
- Convoy Works
- Signs, Lighting & Guarding
-
What where the site staff doing when you arrived?
-
Are operatives carrying their lantra cards/certification/slg card?
-
Have the vehicle checks been completed? Are there any issues? Is the vehicle in a good and presentable condition?
-
Operative briefed on latest Safety Alert/Toolbox talk?
-
Do all members have the correct PPE for this site, and is it in good condition and presentable?
-
What was the general state of the traffic management equipment/system being used?
-
Does the site comply with the relevant drawing, RA/MS, ACOP, and chapter 8?
-
Are all signs secured, footways clear and drives and junctions clear of obstructions?
-
Where there any site specific instructions issued and are they being carried out
-
Where the operatives briefed correctly by the operations team, is the information suitable for the site and is there anything that can be improved upon?
-
Ask the operative for feedback regarding health and safety, safety and quality of site and equipment
-
Has an environmental assessment been carried out for this site, and was one required?
-
Additional notes regarding site and site staff
-
Add media
-
Auditor Signature
-
Foreman/Operative signature
-
Is the customer happy with the service supplied so far? (Please provide customer feedback)
-
Customer signature