Title Page
-
Site conducted
-
CONDUCTED ON
-
ELECTRICAL WORKER NAME
- ANTHONY HOPKINS
- DAN HUTTON
- HARRY PYMONT
- BEAU HARRIS
- ALEC DANELUTTI
- CALLUM COLLINS
-
SAFETY OBSERVER NAME
- ANTHONY HOPKINS
- DAN HUTTON
- HARRY PYMONT
- BEAU HARRIS
- ALEC DANELUTTI
- CALLUM COLLINS
-
TRAFFIC CONTROLLERS NAMES
-
SITE CONDITIONS
-
HAVE ALL MEMBERS OF THE WORK GROUP SIGNED ONTO THE RISK ASSESSMENT AND APPLICABLE SWMS FOR THE WORK
POLE INSPECTION
- POLE INSPECTION
-
STREET ADDRESS
-
CONDUCTED ON
-
IS THE RATE 3 LABEL AND POLE ID LABEL VISIBLE?
-
WHICH LABEL NEES TO BE REPLACED?
- GREEN 3
- POLE ID
- BOTH
-
POLE NUMBER
-
Pole Height
-
Confirm pole type
- BPM
- SBM
- Hinged
-
Out Reach Size
-
Out Reach Type
-
Out Reach Type
-
Out Reach Type
-
Out Reach Type
-
Out Reach Size
-
Out Reach Type
-
Out Reach Type
-
Out Reach Type
-
Out Reach Type
-
Out Reach Size
-
Out Reach Type
-
Out Reach Type
-
Out Reach Type
-
Out Reach Type
-
CAN POLE BE SAFELY ACCESSED?
-
WHY CAN THE POLE NOT BE ACCESSED?
- CAR/ VEHICLE PARKED IN WAY
- LOCATED IN PARK
- CONSTRUCTION SITE
- POLE MISSING
- OTHER - PLEASE SPECIFY
-
PHOTO OF ENTIRE POLE
-
PHOTO OF POLE NUMBER
-
RECORD LUMINAIRE TYPE/SIZE
- L80-25-L3 :Cree STR-LWY-2S-__-08-E-UL-525-40K-CONFIGURED – 133W
- L40-3M-L3 :Cree STR-LWY-3M-__-04-E-UL-350-40K-CONFIGURED – 44W
- L20-3M-L3 :Cree STR-LWY-3M-__-02-E-UL-350-40K-CONFIGURED – 24W
- SYLVANIA- RoadLED Midi 100W 4K Aeroscreen
- SYLVANIA- StreetLED3 24W Aeroscreen
- SYLVANIA- StreetLED3 17W 4K Aeroscreen
- Other
-
What Type ?
-
CHECK LUMINAIRE TIGHT/LEVEL CONNECTION TO OUTREACH
-
HAS THE ISSUE BEEN RECTIFIED
-
WHAT IS THE ISSUE
-
CLEAN/WIPE DOWN LUMINARE FITTING
-
REPLACE PE CELL
-
IS THE GASKET FITTING CORRCTLY
-
CAN IT BE FIXED ONSITE
-
IS THE FITTING OPERATIONAL?
-
CAN THE FAULT BE EASILY DETERMINED?
-
WHAT IS THE CAUSE OF THE FAULT?
- NO POWER TO GEAR TRAY
- POLE CIRCUIT BREAKER FAILED/ FAULTY
- POLE ISOLATOR FAILED/FAULTY
- OTHER- PLEASE SPECIFY
- Faulty Light Fitting
-
CONFIRM ALL LED MODULES WORKING
-
HOW MANY LED'S ARE NOT WORKING?
-
PHOTO OF COMPLETED WORKS
-
HAVE YOU COMPLETED A TOP DOWN INSPECTION OF THE POLE?
-
WHY NOT?
-
WERE ANY OF THE FOLLOWING ISSUES IDENTIFIED?
- DAMAGED HATCH SCREW
- ANT OF BUG INFESTATION
- INCORRECTLY WIRED
- NO ISOLATOR IN POLE
- NO ISOLATION POINT
- NO FUSED CABLE JOINT AT PIT ( JU POLES)
- FAULTY CIRCUIT BREAKER
- FITTING FULL OF WATER
- DAMAGE TO POLE
- DAMAGE TO GROUT
- POLE BASE BELOW FINISHED SURFACE
- OTHER -PLEASE SPECIFY
- Faulty Light Fitting
-
HAS THE SITE BEEN LEFT NEAT AND TIDY, HAS THE POLE HATCH BEEN SECURED, HAVE SWITCHBOARDS BEEN CLOSED?
-
ANY OTHER THINGS TO REPORT?
-
PLEASE PROVIDE DETAILS
COMPLETION
-
HAVE ALL POLES BEEN CLOSED UP, HATCH SCREWS SECURED AND SWITCHBOARDS BEEN CLOSED AND LOCKED?
-
ARE ALL LIGHTS /CIRCUITS BACK ON?
-
HAS ANYTHING BEEN TAGGED OUT / MADE SAFE THAT REQUIRES FURTHER ATTENTION?
-
PLEASE PROVIDE DETAILS
-
HAVE ALL TRAFFIC CONTROL DEVICES BEEN REMOVED FROM SITE?
-
HAS ALL WASTSE BEEN REMOVED FROM SITE?
-
HAVE ANY INCIDENTS OR NEAR MISSES OCCURED?
-
Add signature