Title Page

  • Site conducted

  • Conducted on

  • Location
  • Project Manager

  • Inspection Number

  • Inspector

  • Installer

  • Is this a remedial action inspection

  • Give previous project inspection number

Project Information

EQUIPMENT DETAILS

  • Inverter Brand

  • System kWp

  • Modules Size

  • Number of inverters

  • Inverter size

  • Type

  • Monitoring Equipment ( OOB, Janitza, MeteoControl, Weather station)

Module Area

Module mounting

  • Is clamps in clamp zone?

  • Any Broken modules?

  • Is there clamps close to the edge of the shortrails?

Labels

  • String labels on roof are present

  • String labels at DC junction box and/or Inverters are present

  • String labels for DC High voltage present on cable trays

Layouts

  • Has modules installation been finished?

  • String layout is confirmed to match final design Commissioning Form should confirm this

  • If there have been changes, these have been communicated to the EE design team for update

  • String layout from Project Description is being followed

  • Is the Layout from PVSol followed?

  • Number of Modules per String match PVSol Design and SLD

  • List anomalies

  • Number of Strings match PVSol Design and SLD

  • String Input to Inverters matches PVSol Design and SLD

Earthing

  • An earthing and bonding arrangement has been established inter Array

  • Method of interconnecting earthing between sub arrays

  • Is there an Earth busbar or connection point on cable tray?

  • The earth conductor size from sub arrays to earth connection point on roof

  • The earth conductor size from earth connection point on roof to Main earth bar in PV Sub DB

  • Is the Earth wire terminated with a lug and serrated washer to roof clamp/rail?

  • Is a rayvolt clip used?

  • Any loose earthing/bonding connection?

  • Spot checks for loose bonding lugs has been done on the outside modules and no loose lugs found

  • Latest design has been confirmed and approved by EE Design team Natheera and Dayne

  • Earthing layout follows design

MC4's

  • All MC4 connectors have been crimped with correct tool and tightened to the correct torque

  • Exposed MC4s are sealed and not exposed to the weather while not connected

  • No MC4 connectors are touching the roof sheeting

  • Only original MC4s are being used on site Especially SolarEdge sites

  • Is this a SolarEdge system

  • SolarEdge optimiser layout is being followed

  • Optimiser sticker layout is complete and clear

  • No mistakes are found in optimiser spot checks (Check at least 5)

Cable Trays

  • Has the position of cable trays, bends, entry points been identified

  • Cable entries into trays are mechanically protected and not exposed to sunlight or sharp edges

  • Any joins or connection in the DC cable are identified and recorded for asbuilt

  • DC cable is protected from sharp edges in trunking

  • Has the joins and cuts been cold galvanised or protected from environment in some manner?

  • Cables are managed neatly in the cable trays and will not pinch in the lid and no sharp edges at cable tray joints

  • Is sprague used between modules, module arrays and leading to cable trays or junction boxes?

  • Is the sprague fixed properly at all places?

  • Is the same sprague used thoughout the project? Multiple sizes allowed but only one manufacturer and type

  • Cable trays are properly fixed and does not show excessive deflection

  • Walkways are properly fixed and does not show excessive deflection

  • Is the cable tray lids properly fixed?

  • Sharp bends or turns on the DC cable

Inverter / LV Area

  • Has the PV Sub DB been installed?

  • Take photo of PV DB location and surrounding area

  • Brief description of PV DB location

  • The SLD lines up with the physical site inspection

  • NRS 097 Warning Labels have been procured and the position is determined

  • Labelling is complete and permanent All devices are clearly labelled including Inverters, Circuit Breakers, Isolators and DB boards

  • Is the Installation finished

  • The EE Commissioning Forms have been filled in and returned by the installer

  • All the CoC tests have been performed and results recorded by someone on site Record the name of the person who performed the testing

  • The CoC has been issued

  • Inverter casings and all metal cableways are bonded less than 0.2Ω

  • All serial sumbers have been recorded in the commissioning forms

  • Main DB?

Main DB

  • The Tie-In point to client DB has been identified

  • Take photo of Busbars/connection point (AC and Earth)

  • Take photo of Motorised breaker (connections/ trip settings/Serial Number/motorising unit)

  • Is the connections torqued and have they been marked?

  • Current rating and setting applied

  • Is the breaker 3 or 4 Pole

  • Breaker Fault level in kA

  • Is there terminal blocks for control wiring from PV DB to main motorised breakers in Main DB

  • Is the control cable directly wired?

  • AC Cables size/ busbar size from Main busbar/connection point to Main DB motorized breaker

  • Evidence required

  • Type of cables

  • AC Cables size from Main DB motorized breaker to PV DB motorized breaker

  • Type of cables

  • Earth Cables size from Main DB to PV DB

  • Type of cables

  • Cable sizes are sufficient to carry the current from the inverters/system. Refer to SANS 101421, Table 6.4(a) for SWA Armoured Cable

  • Cables.PNG
  • Cables.PNG
  • Does the Breaker and setting of breaker match SLD ( current and Fault rating)

  • Have the cables heatshrink been properly done?

  • Have the Breaker been labelled correctly?

  • Is there generator integration?

  • Take photo of generator tie in ( circuit breakers and wiring)

  • Is the Generator correct tie in correct?

  • Take photos of Generator integration conroller

  • Are the CT's in the correct location?

  • Where is the CTs located (Mains input/ generator input/ Automatic transfer switch output)

  • The grid consumption CTs are installed in the correct direction, ie. K or P1 towards the Grid For Solar Edge, Arrow points towards the grid

  • Take pictures of CT location, wiring and Serial Number/nameplate

  • Details of the CT's (Class/A rating/ VA rating/ 333mV or 5A output)

  • Main breaker in PV sub DB?

Main breaker in PV Sub DB

  • The Tie-In point to client Main DB has been identified

  • Take photo of Busbars/connection point (AC and Earth)

  • Take photo of Motorised breaker (connections/ trip settings/Serial Number/motorising unit)

  • Is there terminal blocks for control wiring from PV DB to main motorised breakers in Main DB

  • Is the control cable directly wired?

  • Is the connections torqued and have they been marked?

  • Current rating and setting applied

  • Is the breaker 3 or 4 Pole

  • Breaker Fault level in kA

  • AC Cables size from Main DB to PV DB motorised breaker

  • Cable sizes are sufficient to carry the current from the inverters/system. Refer to SANS 101421, Table 6.4(a) for SWA Armoured Cable

  • Cables.PNG
  • Cables.PNG
  • Does the Breaker and setting of breaker match SLD ( current and Fault rating)

  • Have the cables heatshrink been properly done?

  • Have the Breaker been labelled correctly?

  • PV DB?

PV DB

  • Any loose connections found in PV DB?

  • Is the modules connected directly to earth busbar?

  • Earth cable size

  • Evidence required

  • Earth cable type

  • Evidence required

  • Type of termination on CB's and Terminals in PV DB

  • Take photo of all terminations on CB's, Terminal block, fuses and other equipment in DB

  • Is there a OOB Relay?

  • Type of Relay

  • Location of Voltage reference

  • Is there Relay voltage reference protection (type and size)

  • Are bootlace ferrules used on all connection on relay?

  • Is there terminal blocks for control wiring from OOB relay to motorised breakers

  • Are there bootlace ferrules used on the connections of the terminal blocks?

  • Is the control cable directly wired?

  • Take photo of serial numbers

  • Out of Bounds relay connection is correct and operates the MCCBs or contactors 2 in series. The OOB relay must be able to open and close the solar connection

  • Is the system smaller than 30kVA?

  • Solar DB design has been reviewed and is sized correctly for cooling etc

  • Is cooling equipment required?

  • Take photo of cooling equipment in DB

  • Is there AC SPD?

  • Type of SPD

  • Does the SPD have Fuse protection?

  • Fuze size

  • Cable size to fuse from Busbar

  • Cable size to fuse from SPD

  • Inverter Breakers

Inverter Breakers

  • Take photo of Busbars/connection point where inverter breakers are tied in to

  • Is the connections torqued and have they been marked?

  • Current rating and setting applied

  • Is the breakers 3 or 4 Pole

  • Breaker Fault level in kA

  • AC Cables size from Inverters to PV DB inverter breakers

  • Cable sizes are sufficient to carry the current from the inverters/system. Refer to SANS 101421, Table 6.4(a) for SWA Armoured Cable

  • Cables.PNG
  • Cables.PNG
  • Does the Breaker and setting of breaker match SLD ( current and Fault rating)

  • Have the cables heatshrink been properly done?

  • Have the Breakers been labelled correctly?

  • Earth cable size from earth busbar to inverters

  • Earth cable type from earth busbar to inverters

  • Inverters

Inverters

  • Take pictures of inverter Serial Numbers

  • Take Pictures of String Inputs to inverters

  • All strings are labelled on the roof and at inverter

  • Inverter mounting and spacing is as per the installation manual

  • Inverter installation manual is on site with the installation team

  • All inverters are producing energy and are communicating with the monitoring platform

  • Unused glands and holes are to be sealed with the blanks supplied in the inverter box

  • Is the inverters located outside

  • Does it require a cage and roof?

  • The inverter room has sufficient airflow and cooling

  • Inverter covers are mounted securely and all screws and glands are tightened correctly

  • Bonding, Earthing and insulation resistance test has been done and has passed before turning the power on

  • Production reading lines up with a manual measurement

  • Cable Trays

Cable trays

  • AC and DC cable trays separate?

  • Is the AC and DC cable trays mounted securely?

  • Is the AC and DC Cable tray lids mounted securely?

  • Is the AC and DC Cable trays bonded?

  • Comms Cable running separately from AC and DC conductors?

  • Cable bends are not too small in radius and are mechanically protected

  • Cable tray edges are deburred and or mechanically protected

  • Is the cuts cold galvanised?

  • Is the cuts cold galvanised?

  • Comms

Comms

  • Has the communication and metering equipment location been finalised

  • Take photo of Comms box inside and location

  • Datalogger type

  • Does the system require SCADA(>100kVA) (cape town)

  • For plants greater than 100kVA The Scada Device has been procured and the installation location is established

  • The connection between the inverters and the Scada device has been wired

  • Wiring method (RS485 or Modbus TCP)

  • Rs485 Cables used for Smartlogger/janitza/power meters/solaredge inverters ?

  • Does devices at start and end of chain have terminating resistor or switch?

  • Is the metal shielding connnected to ground on one side and disconnected on the other end?

  • Is there an Ethernet Switch?

  • Is there a power point in/nearby comms DB or in PV DB?

  • Is the installer aware that there is a need to install the techsitter meter

  • Is this a roof rental or PPA Has the Techsitter meter been ordered with the correct CTs

  • Does the monitoring system have its own router?

  • Is the router easily accessible for O&M?

  • Is the router set up and internet connectivity good?

  • Is the inverters running?

  • Inverter brand

  • IP Address of Smartlogger/Datalogger

  • IP Address of Inverters

  • IP Address of Datamanager/Datalogger

  • IP Address of Inverters

  • Is all the inverters set to static IP?

  • IP Address of Datamanager/Datalogger

  • IP Address of Inverters

  • Is all the inverters set to static IP?

  • Modbus ID's of inverters

General

  • Any additional remarks?

  • Is there boot marks on the modules

  • Is the site in neat condition and housekeeping done?

  • Is this site BUILT TO LAST

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.