  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

General Requirements:

  • Site specific safety plan located on site?

  • Safety manual located on site?

  • SDS book located on site?

  • Weekly tool box meetings complete?

  • Jobsite required posters?

  • At least two employees trained in first-aid/CPR on site?

  • First-aid kit is stocked?

  • Nearest health clinic/hospital identified?

  • Emergency action plan shared with all employees?

  • Fire extinguishers on site and up to date?

  • Drinking water available?

  • Does all hand tools have the original guards in place?

  • Secondary containers have GHS labels?

Personal Protective Equipment (PPE):

  • Hard hats, safety glasses and gloves being worn?

  • Hi-visibility safety vests or shirts with reflective stripes being worn?

  • Dust masks or respirators being worn when required?

  • Face shields being used when cutting?

  • Hearing protection being worn when needed?

Housekeeping:

  • Conex clean and material neatly stored?

  • Laydown area organized?

  • Fuel storage bermed/protected; 20 lb fire extinguisher located between 25 feet and 75 feet?

  • Flammable materials stored in fire box outside of conex?

  • Damaged tools or cords disposed of or tagged "Do Not Use"?

Trenching & Excavations:

  • Written daily inspections done by Competent Person?

  • Shored, Sloped, or benched 1.5:1 unless can prove better soil type?

  • Tabulated for trench box date on site?

  • Slope toe is 18" below trench box?

  • Trench box max 2 feet above bottom of trench?

  • Trench box not damaged or missing parts?

  • Excavation is barricaded?

  • Spoil pile is 2 feet away from edge?

  • Exit for employees - ramp of ladder within 25 feet?

  • Ladders extended 36" above excavation or trench box?

  • Ladder rails and rungs in good repair?

  • Warning labels/stickers in place and legible on ladders?

  • Underground locate performed prior to digging?

  • Existing utilities potholed prior to digging?

  • Equipment parked minimum of 20 feet from excavation?

  • Is blasting required?

  • Is a blasting safety plan in place and being followed?

Equipment Safety:

  • Lights, brakes, horn and back-up alarm functioning?

  • Windshields are in good repair?

  • Inspection and maintenance logs current?

  • Fire extinguisher installed?

  • Seat belts being worn?

  • Safe speeds, controlled motion?

  • Rigging inspected, safely configured, tagged?

Confined Space:

  • Is the area a permitted confined space? If so, is the entry permit filled out?

  • Manhole air quality tested before entry?

  • Manholes are ventilated? Blowers used before and during work, especially in shot rock areas?

  • Purge with air at least 5 minutes before entry?

  • Tripod and safety harness in place?

  • No employees in manhole during stack out?

Roadways

  • Roads, sidewalks, public access areas safe to public?

  • Traffic control plan complete?

  • Traffic control per MUTCD, local, county or state standards?

  • Correct warning signs installed per plan?

  • Flaggers are trained?

  • Flaggers wearing proper PPE?

  • Flaggers using proper signage or flags?

  • PM Signature

  • Superintendent Signature

  • Foreman Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.