A weekly plant inspection of the refrigeration system is to be carried out by the site supervisor/ Manager (Yes = Checked OK, No = Fault) All critical/ Urgent issues must be reported immediately to the project manager. Add notes and photos to each section where there are issues found
Refrigeration Systems
-
Anchor/fixing size(s) correct<br><br>
-
-
-
Support type and size correct –saddles, brackets or straps (rubber or plastic)<br>
-
-
-
Support spacing correct <br><br>Frequency of supports as recommended by BS4434 is as follows:<br><br> up to 22mm 1m spacing<br><br> 28mm to 54mm 2m spacing<br>
-
-
-
Pipework routing as per drawing and installed so as not to sustain damage<br>
-
-
-
Pipework size correct <br><br>
-
-
-
Pipework materials correct – Only copper tubing used (BS2872 Part 2, Table 2)<br><br>
-
-
-
Pipe bends are circular in section and smooth in bore, pulled bends are preferred<br>
-
-
-
All pipelines installed with minimum number of joints<br><br>
-
-
-
Brazing or silver solder used for jointing pipelines <br>Brazing for copper to copper, silver solder for copper to brass or steel<br><br>
-
-
-
Insulation if provided on suction pipelines to minimise condensation – insulation to comply with BS476 Part 7 Class O
-
-
-
The identification of pipework is in accordance with BS1710<br><br>
-
-
-
Any condensate drains to cooling coils are correctly fitted and laid to falls<br><br>
-
-
-
Leakage pressure test satisfactorily carried out (Specialist Sub Contractor)<br><br>
-
-
-
Evacuation pressure test satisfactorily carried out (Specialist Sub Contractor)<br><br>
-
-
-
System satisfactorily charged with refrigerant (Specialist Sub Contractor)<br>
-
-
-
All bracketry suitably treated with anti corrosion paint on cut ends<br>
-
-
-
Any further comments
-
Site Managers Signature