Information

  • Document No.

  • Audit Title

  • Client / Site

  • Add media

  • Conducted on

  • Prepared by

  • Foreman On Site

  • Project Manager

  • Location
  • System Size

  • Job Number

Central Inverter

    Inverter
  • Name Plate, Make and Model

  • Add media

  • Mounted Square On Pad<br>

  • Add media

  • Lamacoids Installed As Per SLD

  • Add media

AC Side of Inverter

  • AC Conductors Installed As Per SLD

  • Wire Size As Per SLD

  • Include picture of wire size

  • Wire Phased Correctly

  • Add media

  • Conduits Sealed

  • Add media

  • Lugs Rubber Taped

  • Add media

  • Torqued and Marked

  • Add media

  • Grounds Torqued and Marked<br>

  • Add media

  • Are Cavities Clean and Free of Debris

  • Add media

  • Safety Guards Installed ,Gland Plates In

  • Add media

DC Side of Inverter

  • DC Conductors Installed As Per SLD<br>

  • Wire Size As Per SLD

  • Include picture of wire size

  • Wire Phased Correctly

  • Add media

  • Conduits Sealed

  • Add media

  • Lugs Rubber Taped

  • Add media

  • Torqued and Marked

  • Add media

  • Grounds Torqued and Marked <br>

  • Add media

  • Are Cavities Clean and Free of Debris<br>

  • Add media

  • Safety Guards Installed, Gland Plates In

  • Add media

Monitoring

  • Are Conduits Run to Cavities On Inverter

  • Add media

  • Are Wires Pulled To Cavity in Inverter

  • Add media

  • Are Communication Wires Terminated

  • Add media

Page Complete

  • Add signature

Inverter pad

  • Cement Work Done to RESCo Standards

  • Add media

  • Picture of Ground Plate With Ground Wire Attached

  • Add media

  • Fence Installed to RESCo Standards

  • Add media

  • Fence Welded

  • Add media

  • Fence Bonded

  • Add media

  • Locks and U Bolt Installed

  • Add media

  • Signage Installed

  • Add media

  • Lock Box On Fence

  • Add media

  • All Strut Galv Sprayed and Secure

  • Add media

Cable Tray

  • Installed Securely

  • Add media

  • Bonded every 50 Feet, Back to Recombiner

  • Add media

  • Cable Space Maintained <br>

  • Add media

  • Cables Secured

  • Add media

  • Cover Installed Correctly

  • Add media

Pipe Work

  • Pipe Supported Properly to Code

  • Add media

  • All Connectors Installed Tightly With Sealing Rings

  • Add media

  • LB'S Drilled / Drain Hole

  • Add media

  • Pipe or Uni Strut Galv Sprayed

  • Add media

Page Complete

  • Add signature

String Inverters

    String Inverter
  • Ground Bushing Present for Metalic Conduit

  • Add media

  • Clean and Free of Debris

  • Add media

DC Side of Inverters

  • DC Conductors Installed As Per SLD

  • Add media

  • Wire Size As Per SLD

  • Add media

  • Correct Polarity and Phase

  • Add media

  • Conduits Sealed

  • Add media

  • Ground Bushings Present On Metallic Conduit <br>

  • Add media

  • Terminations Torqued and Marked

  • Add media

  • Grounds Torqued and Marked

  • Add media

  • Cavities Clean and Free of Debris

  • Add media

  • Safety Guards Installed

  • Add media

  • Name Plate ,Make and Model

  • Add media

  • Mounted Secure and Square

  • Add media

  • Lamacoids As Per SLD

  • Add media

AC Side of Inverter

  • All Conductors Installed As Per SLD

  • Add media

  • Wire Size As Per SLD

  • Add media

  • Wire Phased Correctly

  • Add media

  • Conduits Sealed

  • Add media

  • Lugs Torqued and Marked

  • Add media

  • Grounds Torqued and Marked

  • Add media

  • Knockouts Sealed

  • Add media

Page Complete

  • Add signature

Micro inverters/ Power Optimizers

  • Bonded and Grounded As Per SLD

  • Add media

  • Serial Number Map Complete

  • Add media

  • Monitoring Installation Complete

  • Add media

Page Complete

  • Add signature

Disconnects

    Disconnects
  • Lamacoids Installed As Per SLD

  • Add media

  • Conductors Installed As Per SLD

  • Add media

  • Wires Phased Correctly

  • Add media

  • DC Wiring Done Correctly<br>

  • Add media

  • Lugs Torqued and Marked

  • Add media

  • Fuses Installed As Per SLD

  • Add media

  • Neutral Block Installed, Bonded if Needed

  • Add media

  • Clean and Free of Debris

  • Add media

  • Drain Hole if Needed

  • Add media

Page Complete

  • Add signature

Metering and Monitoring

  • Are Monitoring Enclosures Installed

  • Add media

  • All Pipe work Complete , including Chase to Roof Top, and Inverters

  • Add media

  • Communication Wire Pulled

  • Add media

  • Weather Station Built and Ballasted

  • Add media

  • All Sensors Installed

  • Add media

  • All Sensor Wires Terminated

  • Add media

  • Communication Wires Terminated

  • Add media

  • Meter Installed

  • Include Picture of Complete Enclosure and Face Plate and Serial Number of Meter

  • 120 On Pad with Plug

  • Add media

  • Metering Phone Line Installed

  • Add media

  • Monitoring Internet Connection (hardline) Installed and Tested

  • Add media

  • Pre-Commissioning Forms Completed

Page Complete

  • Add signature

Transformer

  • Make, Model, Name Plate

  • Add media

  • Lamacoids Installed by SLD

  • Add media

  • Taps Are Free From Any Modifications and Have Adequate Space Between Them

  • Add media

  • Terminations Are Rubber Taped

  • Add media

  • Clean and Free of Debris

  • Add media

Primary

  • Conductors Installed As Per SLD

  • Conductor Size As Per SLD

  • Include picture of wire size

  • Lugs Torqued and Marked

  • Add media

  • XO Grounded, By Us or By Factory

  • Add media

  • Transformer Chassis Grounded

  • Add media

  • Conduits Sealed

  • Add media

Secondary

  • Conductors Installed As Per SLD

  • Conductor Size As Per SLD<br>

  • Include picture of wire size

  • Lugs Torqued and Marked

  • Add media

  • Conduits Sealed

  • Add media

Page Complete

  • Add signature

Recombiner

    Recombiner
  • Make, Model, Name Plate

  • Add media

  • Lamicoids Installed As Per SLD

  • Add media

  • Recombiner Secured to the Pad

  • Add media

  • Conductors Installed As Per SLD

  • Add media

  • Teck Installed Correctly, Conductor Size As Per SLD

  • Add media

  • Conductors Size As Per SLD, From Recombiner to Inverter

  • Add media

  • Conductors Phased Correctly<br>

  • Add media

  • Teck Cables Labeled As Per SLD, to Correct Breaker

  • Add media

  • Breakers Installed As Per SLD

  • Add media

  • Teck Connectors Installed Correctly, and Sealed

  • Add media

  • Ground Installed and Torqued

  • Add media

  • Rubber Taped on Lugs

  • Add media

  • Lugs Torqued and Marked

  • Add media

  • Conduits Sealed, Gland Plate Installed

  • Add media

  • Clean and Free of Debris

  • Add media

Page Complete

  • Add signature

Electrical Room

  • Clean and Free of Debris

  • Add media

  • All Lamacoids Installed As Per SLD

  • Add media

  • All Pipe or Teck Runs Secured Correctly

  • Add media

  • Overall Photo Of Completed Work

  • Add media

Page Complete

  • Add signature

Main Switch / Shutdown

  • Make, Model, Name Plate<br>

  • Add media

  • Lamacoids Installed As Per SLD

  • Add media

  • Shut Down Complete<br>

  • Include All Shut Down Pictures

  • Lugs Torqued and Marked

  • Add media

  • Size Of Main Breaker

  • Add media

DG1

  • Clean and Free of Debris

  • Add media

  • Shutdown Lock Installed

  • Add media

  • Installed As Per SLD

  • Add media

  • Conductor Size As Per SLD

  • Add media

  • Neutral Block Installed and Bonded

  • Add media

  • Ground Bushings

  • Add media

  • Lugs Torqued and Marked

  • Add media

  • Lamacoids Installed As Per SLD

  • Add media

Page Complete

  • Add signature

Combiner boxes

    Combiner Box
  • Add media

  • Secured To Rack or Durablock<br>

  • Add media

  • Number of Strings

  • Lamacoid As Per SLD

  • Add media

  • Expansion Joints Installed for Wire Management With Sealing Rings

  • Add media

  • Teck Connectors Seated Correctly With Sealing Rings

  • Add media

  • Teck and Pipe Supported Correctly

  • Add media

  • Feeders Installed Correctly and Phased

  • Add media

  • All Fuses Installed and Open

  • Add media

  • All Home Runs Connected

  • Lugs Torqued and Marked

  • Add media

  • Bonding Conductor Installed ,Torqued and Fastened to Array

  • Add media

  • Conduits Entering Are Sealed

  • Add media

  • Clean and Free of Debris

  • Add media

  • PV Wire Installed Neatly, As Per SLD and Labeled Correctly

  • Add media

  • Make and Model, Serial Number<br>

  • Add media

  • Combiner Installed As Per SLD and Location

Page Complete

  • Add signature

Cable Tray / Wire trough / Wire Basket

Cable Tray

  • Installed Securely, Fasten to Durablock

  • Add media

  • Bonded Every 50 Feet<br>Bonded to Recombiner

  • Add media

  • Cable Space Maintained

  • Add media

  • Covers Installed Correctly

  • Add media

Wire Trough

  • Expansion Joints On Non Continues Runs

  • Add media

  • Installed Securely, fasten to Durablock, Fasten to Array<br>

  • Add media

  • Lapp Connectors Installed Securely

  • Add media

  • Bonded to Corresponding Combiner Box

  • Add media

  • End Caps Installed

  • Add media

  • Covers and Latches Installed Screws All Installed With Gaskets

  • Add media

Wire Basket

  • Installed Securely, Fasten to Durablock, Fasten to Array

  • Add media

  • Every Piece Bonded

  • Add media

  • PV Wire Protected Leaving Basket

  • Add media

  • Covers Installed Correctly

  • Add media

Page Complete

  • Add signature

Array / Racking

  • Array Installed Straight and Square

  • Add media

  • General Pictures of the Array

  • Add media

  • Installed As Per Drawing <br>

  • Add media

  • Ballasted As Per Drawing

  • Add media

  • All Roof Protection Is Installed As Per Drawing

  • Add media

  • Module Type and Name Plate<br>

  • Add media

  • Hardware Torqued and Marked As Per Specs

  • Add media

  • Pv Wire Size, Wire Type and Connector Type

  • Add media

  • Pv Dressed Under Modules

  • Add media

  • Pvc Jumpers North to South Fastened to Racking

  • Add media

  • Home Runs Labeled Correctly

  • Add media

  • Teck Cables Dressed Under Modules

  • Add media

  • Array is Bonded

  • Add media

  • Clean and Free of Debris <br>

  • Add media

Page Complete

  • Add signature

Over All Site Conditions

Roof top

  • Any Signs of Degranulation

  • Any Left Behind Material, Safety Devices

  • Drain Flags Installed

  • Clean and Free of Debris

  • All Stone Spread Out Evenly

Site Services

  • Site trailer

  • Port-a-jon

  • Seacan

  • Bin or Dumpster

  • Safety Fence

  • Landscaping or Property Damage

  • Clean and Free of Debris

Page Complete

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.