Information

  • Client / Site

  • Conducted on

  • Location
  • Personnel

1.0 - Previous inspection

  • 1.1 - Has the last inspection been reviewed?

  • 1.2 - Are there no outstanding actions?

2.0 Site

  • 2.1 - Is site secure?

  • 2.2 - Adequate amenities provided for workers & supervisor?

  • 2.3 - Adequate safety signs & notices posted?

  • 2.4 - Site induction program and records?

  • 2.5 Safe Work Method Statements for all high risk work available?

  • 2.6 - Site is clean?

3.0 Electrical Hazards

  • 3.1 - Switchboards properly constructed & setup (testes/tagged)?

  • 3.2 - Correct GPO's being used?

  • 3.3 - Portable outlet devices suitable?

  • 3.4 - Cabling protected from mechanical damage?

  • 3.5 - Power tools & leads in safe condition (tested & tagged quarterly)?

  • 3.6 - Have RCD's been tested?

  • 3.7 - Portable generators suitable - RCD, Earthed?

  • 3.8 - Leads set out safely?

  • 3.9 - Plant & temporary structures are safe distance from power lines?

4.0 Public Safety

  • 4.1 - Complies with local government requirements?

  • 4.2 - Site Secure?

  • 4.3 - Traffic properly managed?

  • 4.4 - Public protected from dust & debris?

  • 4.5 - Work in public space properly managed?

5.0 Personal Protection

  • 5.1 - Worker PPE being worn and appropriate?

  • 5.2 - PPE signs posted where necessary?

6.0 Trenching & Excavation

  • 6.1 - All underground services located?

  • 6.2 - Earthmoving plant used safely?

  • 6.3 - Are people safeguarded from falling into excavation?

  • 6.4 - Fall from: balcony, excavation edge, stair well?

7.0 Roofing

  • 7.1 - Safe access to roof areas?

  • 7.3 - Workers protected from falling off edges?

  • 7.4 - Workers protected from falling from incomplete roofs?

  • 7.5 - Workers protected from falling through skylights & penetrations?

  • 7.6 - People protected from dangers of falling materials, Tools, etc.?

8.0 Fit-out & Finishing

  • 8.1 Tools & equipment used safely?

  • 8.2 - PPE being used safely?

  • 8.3 -Mobile scaffolds used safely?

  • 8.4 - Ladders used safely and are commercial grade?

  • 8.5 - Manual handling tasks completed safely?

9.0 Bricklaying

  • 9.1 - Sufficient space set aside for deliveries?

  • 9.2 - Cement mixers used safely?

  • 9.3 - Bricklayers scaffold properly constructed?

  • 9.4 - Bricklayers using scaffold safely?

  • 9.5 - Barrow hoists properly set-up & used safely?

  • 9.6 - Brick cleaning being completed safely?

10.0 Scaffolding

  • 10.1 - Scaffolders properly certified?

  • 10.2 - Scaffold strong enough for loads?

  • 10.3 - Scaffolding stable?

  • 10.4 - Scaffold protects workers & other people?

  • 10.5 - Safe access to every scaffold platform?

  • 10.6 - Scaffolds safe distance from power lines?

  • 10.7 - Scaffolders working safely?

  • 10.8 - Scaffold users working safely?

  • 10.9 - Scaffolds regularly inspected?

11.0 Powered Mobile Plant

  • 11.1 - Operators certified or qualified?

  • 11.2 - Plant registered with workCover?

  • 11.3 - Plant properly maintained, checked & serviced?

  • 11.4 - Plant fitted with reversing beepers?

  • 11.5 - Roll-over protective structures? (seat belts must also be fitted)

  • 11.6 - Plant operated safely?

  • 11.7 - Unattended plant secure?

Corrective Actions for Hazards identified

  • Corrective actions:

Sign Off

  • Auditor's signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.