Inspection during construction - Concrete footings & slabs

  • Add image of site

  • With reference to structural plan number

Set-out

  • Distances from easements, Sydney water assets and Local Government Infrastructure confirmed?

Excavation of Foundation Material

  • Dimensions of excavation

  • Bearing surfaces of excavation

Compaction of Fill Material (if necessary)

  • Compaction Level/Density

Cut & Fill Batters

  • Location of Cut & Fill Batter

  • Construction and location of retaining walls (all retaining walls must be detailed before construction)

  • Provision of drainage for retaining walls

  • Falls to external finished areas i.e. away from habitable slab edges

Drainage Elements

  • Incorporation of drainage elements per approved plans

  • Provision of falls to drainage elements

Piers through fill

  • Location of piers through compacted fill

  • Depth and bedding of piers through compacted fill to natural ground or in accordance with approved design requirements

Reinforcement of Slab and Footing System

  • Type and placement of steel reinforcing

  • Size and gauge of reinforcing steel

  • Location and dimension of laps to reinforcement steel (refer typical detail sheet)

Vapour Barrier

  • Type and location of vapour (polythene or equivalent)

  • Type and location of joint overlaps to vapour barrier

  • Treatment to penetrations through vapour barrier (taped and lapped as with overlaps)

Control Joints

  • Provision for saw cuts per approved plans

  • Provision for doweled expansion joints per approved plans

Other verbal advice provided to owner/contractor

  • undefined

Inspection Result

  • Result of the inspection

  • Should you have any questions regarding this inspection please contact Taylor Consulting on 02 9982 7092

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.