The following Inspection is intended for Residential Services. Commercial Services may need to meet additional specifications. Be sure to attach pictures of any item that does not meet specification.
Primary Underground
-
Is there Primary Underground to be inspected? (N/A if there is not)
-
Trench – Does it follow staking sheet location?
-
Primary depth – 30” min (NESC Sect 35)
-
Conduit required? Size correct? If sand, 6” encasement with additional inspections.
-
Conduit complete/continuous? Protection of conductors from physical damage (NEC 300.5)
-
Max number of bends cannot exceed 359° in one run (NEC 352.26)
-
Pull string installed?
Padmount Location
-
Match staking sheet location?
-
Padmount location level with fine limestone or stone?
-
Conduits stubbed up in correct locations?
-
Pad installed?
Subdivision Secondary
-
Is this a Subdivision Secondary? SCP contractor will dig & install secondary (N/A if it is not)
-
Any obstruction from meter base into padmount?
-
Any obstruction from meter base into ground? Foundation concrete, etc.
-
Meter base have 2.5 - 3” knockout?
-
3” Riser (or 3 to 2.5 reduced) with expansion joint installed?
-
Measure length for secondary run (<300’ req)
Secondary Underground Installation
-
Is this a Secondary Underground Installation where the member is required to install trench/conduit? (N/A if it is not)
-
Trench – Does it follow staking sheet location?
-
Secondary depth – 30” min (SCP Req 30”) (NESC Sect 35/NEC 300.5)
-
Conduit required? Size correct? If sand, 6” encasement with additional inspections.
-
Conduit complete/continuous? Protection of conductors from physical damage (NEC 300.5)
-
Max number of bends cannot exceed 359° in one run (NEC 352.26)
-
3” Conduit up to 350 MCM
-
Schedule 40 PVC conduit. Not SDR, etc.
-
Pull string installed?
-
Measure length for secondary run (<300’ req)
Permanent URD Service Entrance
-
Third party inspection required?
-
Inspection sticker with current date present? (Take picture)
-
Meter base - side wired, ringless, URD only. Top wired bases generally not allowed due to bend radius violations. (NEC 338.24 - SE & USE)
-
Meter base 2S?
-
200A or 320A?
-
Correct wire size? (200A – 4/0 Al or 2/0 Cu, #6 Cu ground, unbroken) (NEC Tables 310.15)
-
Lugs torqued properly per manufacturer specification? (Chart in meter base)
-
Ground rods – (2) 6’ apart with continuous cu wire. Unless already inspected (SCP min 1) (NEC 250.53)
-
Meter base solidly attached to structure?
-
Main Service Disconnect within 6’ of service entrance direct line distance?