Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Section 1 - Opening Of Audit

1.1

  • A Valid ASB5 Notification Form is on site for the works to be audited

  • The site details on the ASB5 are correct?

  • The Audit is within the dates stated on the ASB5?

  • The ASB5 clearly describes the scope of works?

  • The ASB5 needs to be the correct one for
    the site, meaning that the site address,
    scope of works, working dates etc. are
    correct. The scope of works on the ASB5
    will be a brief overview of the work to be
    carried out, but should still be clear as to
    what works are to be carried out. If there
    is an update of a previous notification, the
    update should be present on site.
    Notifiable Non-Licensed Work is not
    acceptable for site audit purposes. If the
    ASB5 is not valid for the site, the date
    being audited or the nature of the work
    being undertaken, then the audit does not
    continue and ARCA should be informed
    immediately.

  • Section 1 needs to be completed as a pre-audit checklist. These 3 items should be satisfactory in order for the audit to proceed.
    If the audit cannot proceed, make notes on a site audit summary sheet of the reason(s) why, get it countersigned by the supervisor, and inform Rightway Senior Management

1.2

  • There is sufficient provision to view activities within the working enclosure and make meaningful observations

  • Viewing panels and/or cctv are in place to sufficiently observe work practices, and all areas of the enclosure so far as is reasonably practicable?

  • There should be sufficient means to view the works to make meaningful observations of work practices. Within reason, there should be no areas where work practices cannot be observed. It may be considered reasonable, for example, for cameras to be rotated to follow work progression. There should be safe access to viewing panels. If there is no means to view work practices (including cctv that is functioning) then the audit does not proceed.

1.3

  • Asbestos removal / cleaning is in progress during the audit

  • Removal works and associated activities are (or will be) taking place within the enclosure during the audit?<br>

  • ‘Removal works’ includes associated activities such as injection of ACM’s prior to removal, as well as fine cleaning. It does not include pre-smoke test preparation works or the visual inspection prior to clearance air testing. If there are no removal works or associated activities taking place during the audit, then the audit does not continue.

Section 2 – Observed Work Practices and Immediate Site Control: Asbestos Risks

2.1

  • The enclosure is in good condition, properly constructed, and maintained so as to prevent the spread of asbestos

  • The integrity of the enclosure has been established and maintained?<br>

  • Viewing panel sizes meet the minimum requirement?

  • The selection and provision of warning signs are appropriate to the works?

  • The enclosure needs to have been soundly built, maintained and regularly inspected. If there are any flaws or breaches of the enclosure, make a specific note as to the extent. If any remedial works are identified, inform the supervisor immediately - don’t wait until the end of the audit to point this out. Viewing panels should be a minimum of 600 x 300mm panel size. Excessive tape should not unnecessarily restrict the viewing area. Note approximate sizes if they are less than 600 x 300mm. don’t be pedantic about a few millimetres. Bubble viewing panels may appear smaller, though the actual area of the curved surface may well equate to the correct dimensions. Warning signs should include the ‘No Unauthorised Access’ and PPE/RPE signage as a minimum.

2.2

  • The airlock meets the requirements in terms of size, construction, cleanliness and necessary features.

  • The airlock meets the minimum size requirement?

  • Smaller airlock dimensions are detailed and correctly justified in the Plan of Work?<br>

  • The airlock is free from visible asbestos debris?<br>

  • There is suitable provision to clean RPE?

  • All airlock openings/flaps are suitable and weighted?

  • An inner stage viewing panel is present and of the correct size?<br>

  • The 1m x 1m x 2m minimum airlock size requirement should be met unless there is a justifiable reason for smaller dimensions and that the reasoning is documented in the Plan of Work. The airlock should be clean, with no sign of any visible asbestos debris whatsoever. Do not enter the airlock to do this. Push open the outer flap. Use a stick or similar to push the next flap. Use the viewing panel to the inner stage for an additional view. With a direct connection, there are often limitations as to how much can be assessed for visible debris, so make observations to the extent that the site conditions and set-up will allow. Suitable provision for RPE decontamination should be appropriately placed, to be either a bucket of water and sponge, or equivalent such as spray bottle and cloth. All airlock openings should be oval or rectangular, with all flaps weighted, and sufficient overlap that the flaps would sufficiently close the openings in the event of NPU failure. A correctly sized viewing panel should be located on the inner stage. If this cannot be achieved, the expectation is for cctv to be in place instead.

  • Other observation

  • Any other observation or concern regarding the design, construction or functionality of the airlock to be noted here, including if it should have and could have been bigger.

2.3

  • The baglock meets the minimum requirements in terms of construction, cleanliness and necessary features, and is of minimum size or greater to accommodate large items of waste.

  • A separate baglock has been provided?

  • The baglock meets the minimum size requirement?

  • The baglock has smaller dimensions, which are detailed and correctly justified in the Plan of Work?

  • The baglock is big enough for the waste size?

  • The baglock is free from visible asbestos debris?

  • All baglock openings/flaps are suitable and weighted?

  • An inner stage viewing panel is present and of the correct size?

  • The absence of a baglock is correctly justified in the Plan of Work?

  • A separate baglock should be provided unless there is a justifiable reason to not have one, such as insufficient space to attach one. A small amount of waste is not a justifiable reason. Correct justification for not having a baglock should be documented in the Plan of Work. The 1m x 1m x 2m minimum baglock size requirement should be met unless there is a justifiable reason for smaller dimensions and that the reasoning is documented in the Plan of Work. If the waste size would require a baglock exceeding the minimum dimensions, the baglock should be enlarged appropriately. The baglock should be clean, with no sign of any visible asbestos debris whatsoever. Do not enter the baglock to check this, but make observations to the extent that the site conditions and set-up will allow. All baglock openings should be oval or rectangular, with all flaps weighted, and sufficient overlap that the flaps would sufficiently close the openings in the event of NPU failure. A correctly sized viewing panel should be located on the inner stage. If this cannot be achieved, the expectation is for cctv to be in place instead.

  • Other observation

  • Any other observation regarding the design, construction or functionality of the baglock to be noted here.

2.4

  • The site is clean and orderly, including clear transit and waste routes of minimal distance, and clean and tidy vehicle(s) / Equipment Storage.

  • There is a suitably maintained and signed transit route of minimal distance?

  • The waste route is free from visible asbestos debris?

  • The waste route is free from general waste?

  • The company vehicles and/or equipment store are reasonably tidy and clean, with no contamination issues or concerns?

  • The transit route (if there is no direct connection of DCU) should be of minimal distance considering the individual site conditions and circumstances, suitably maintained and signposted. The waste route should be suitably free from general waste, and certainly free from any visible asbestos debris. Company vehicles and/or stores should be reasonably tidy, and certainly with no situation giving rise to concerns regarding contamination (e.g. no waste in unsegregated parts of vans, vacuum cleaners double bagged when transported or in storage, etc.). Equipment storage would also include items such as RPE when not in use.

2.5

  • Controlled asbestos removal has been observed, including the use of suitable dust suppression methods, and with waste appropriately bagged.

  • The dust suppression method in use is suitable for the ACM being removed?<br>

  • The removal procedure observed is suitable for the ACM being removed?<br>

  • Waste is properly and promptly bagged?

  • The dust suppression and removal procedure observed must be the most correct and suitable for the ACM being removed. This is based on your observation of the works. Waste should not be allowed to accumulate, but should be promptly bagged/wrapped. The stage of the works may be that no waste has been generated yet, or that final cleaning is being undertaken, in which case this part will not be applicable.

2.6

  • RPE and PPE is suitable for the task and correctly worn

  • RPE is suitable for the task(s)?

  • Enclosure overalls are type 5/6?

  • Transit overalls are type 5/6 ?

  • All RPE and PPE is being properly worn?

  • All PPE/RPE should be of the appropriate type and standard for the tasks being observed, and properly worn (e.g. overalls not tucked into boots, etc.).

2.7

  • Air management allows for sufficient air changes and air movement through the enclosure, with airlock flap deviation indicating sufficient airflow through the airlock.

  • The enclosure design allows for ideal air management?

  • The air movers installed provide sufficient air changes / airflow?

  • There is sufficient airlock flap deviation to indicate adequate airflow through the airlock?

  • Additional air inlets are suitably positioned and in use (where applicable)?

  • Principles of ideal (or near to ideal) air management should be demonstrated in the design of the enclosure, the number, capacity and location of NPU’s, and suitable provision of inlet(s) for replacement air to achieve the required number of air changes. The airlock flap deviation should be sufficient to demonstrate sufficient airflow is being maintained through the airlock.

2.8

  • Plant and equipment is suitable and sufficient for the work, is properly located and being correctly used.

  • There are a minimum of 2 H-type vacuum cleaners on site?

  • The number and capacity of NPU’s matches the Plan of Work?

  • Each NPU is either located outside the working enclosure, or sheeted out if inside the enclosure?

  • There is a functional non-return flap oneach NPU exhaust?

  • Extracted air from each NPU is vented outside?<br>

  • On very small jobs the second vacuum cleaner doesn’t necessarily have to be in use, though must be available on site for use if required. The NPU’s should be correctly fitted to the enclosure. Should circumstances require the NPU(s) to be located within the working area, the unit(s) should be completely sheeted out (not just a polythene sheet over) with only the prefilter exposed to the working area. Where accessible, check the NPU’s have functioning non-return flaps on the exhaust outlet. Extracted air should be vented outside where reasonably practicable. If not reasonably practicable, the expectation is that the exhaust air is regularly monitored by the analyst.

2.9

  • The DCU is fully functional, operational, equipped and suitably positioned.

  • The DCU arrangement is in the form of a

  • A direct connection is the most suitable option?

  • The NPU on the DCU is functioning?

  • Lighting and heating are functioning and sufficient?

  • There is heated water to the shower(s)?

  • The DCU is suitably stocked with consumables (e.g. nail brush, towels)?

  • There are sufficient showerheads for the number of personnel?

  • The DCU is as clean as is reasonably practicable?

  • Waste water is filtered and discharged either directly or via containers to drain?

  • External dirty end and internal doors are all self-closing?

  • DCU doors are marked (including the prohibited entry and mandatory PPE signage) where required?

  • A direct connection should be the first consideration on any job, with a transit arrangement an acceptable second option if circumstances require it. The DCU should be fully functional, equipped, stocked and fit for purpose. All doors, with the exception of the external clean end door, should be tested to ensure they are fully self-closing, where
    these doors are readily accessible to check. The external dirty end door should display the ‘No Unauthorised Access’ sign and the mandatory RPE and PPE signage. The external clean end door should display the ‘No Unauthorised Access’ sign, and the internal clean to shower door should display the mandatory RPE and PPE signage (though the RPE and PPE signage is permissible on the external clean end door). Even if the unit has signs of being well used, it should nevertheless be as clean as is reasonably practicable.

  • Other Observation

  • Any other observation or concern regarding the decontamination unit to be noted here.

2.10

  • Waste storage is secure and segregated as appropriate.

  • Containment is secure?

  • Waste is segregated from equipment?

  • Whether the waste is being stored in a segregated section of a company van, or in a skip, the containment should be secure/locked when not being accessed.

2.11

  • There are suitable
    arrangements in place to
    deal with typical
    emergencies that may
    arise at this particular site,
    and employees are aware
    of such arrangements.

  • Suitable arrangements are in place/evident.<br>

  • Employees are sufficiently aware of the arrangements.

  • There is a suitably stocked First Aid kit available for use on the site.

  • This is a check that arrangements are in place and that these arrangements have been communicated to Rightway site steam, There needs to be at least a basic awareness (though not looking for expertise) of generic Rightway Asbestos company procedures as well as those that are site specific, e.g. what happens if there is an accidental spillage of waste on the bag run, or, where is the muster point on this site? For practicality, questioning should be to workers not in the enclosure. The first aid kit should be clean and reasonably stocked (including plasters!). On some sites there is insistence that first aid provision is only provided through the client or main contractor.

2.12

  • Other observations relating to asbestos risks.

  • Any other observation or concern relating to asbestos risks to be noted here.

Section 3 – Observed Work Practices and Immediate Site Control: Non-Asbestos Risks

3.1

  • For significant non-asbestos risks on site, appropriate controls are being used / in place (excluding substances)

  • Work at height

  • Live services

  • Manual handling

  • Noise

  • Hand arm vibration

  • Workplace transport

  • If appropriate controls are in place, then it is likely that there has been some assessment of the risks for this to be so. This standard is only concerned with these actual control measures, regardless of what might be included in the written risk assessment. The risks listed are significant, and if they are present on site then appropriate controls should be in place. Make notes regarding any significant risks that are not sufficiently controlled, and the extent of the deficiency.

  • Other

  • Any other significant non-asbestos risks that are lacking appropriate controls should be detailed here.

3.2

  • For significant risks from substances introduced to site (or existing on site), appropriate controls are being used / in place / available

  • Substances have been identified?

  • COSHH assessments are available?

  • Controls are in place / available?

  • This should include substances introduced to the site (e.g. spray adhesive, expanding foam, fibre suppressant, smoke machine fluid) as well as any substances already existing on the site. Controls identified in the COSHH assessments should be in place or available on site. If just the Material Safety Data Sheets are presented to you as a COSHH Assessment, then this is insufficient. The information contained within the data sheets should have been used to make an assessment of the actual risks to health.

3.3

  • Other observations relating to non-asbestos risks.

  • Any other observation or concern relating to non-asbestos risks to be noted here.

Section 4 - Plan of Work

4.1

  • The sketch plan clearly shows all the required details.

  • Location of ACM's

  • Outline of enclosure

  • Adjacent areas

  • Airlock location

  • Baglock location

  • NPU location(s)

  • Viewing panel / cctv locations

  • DCU location

  • Transit route

  • Waste route

  • Waste skip / waste van

  • All of the features listed should be on the sketch plan, with the possible exception of the baglock (if space limitations require the airlock to double up as a baglock), or the transit route (if the DCU is directly connected to the enclosure). Please also make a note if the sketch plan is unclear, a poor copy or too small to clearly show all the required details.

4.2

  • The actual site set-up matches the sketch plan.

  • The features shown on the sketch plan have all been implemented in the site set-up?

  • The site set-up should mirror what is shown on the sketch plan. Minor differences (e.g. DCU rotated 90 degrees) are not really an issue. Omissions and additions would require amendments to the sketch plan and recorded as such.

4.3

  • The conditions, arrangements, practices and controls observed on site match those stated in the Plan of Work.

  • The site supervisor is the supervisor named in the Plan of Work

  • The type of RPE being used matches that detailed in the Plan of Work (or Standard Procedures)

  • The construction of the enclosure(s) and airlock(s) matches that detailed in the Plan of Work (or Standard Procedures)

  • The dust suppression method observed matches that detailed in the Plan of Work

  • The removal procedure observed matches that detailed in the Plan of Work

  • The RPE being used matches that stated in the Plan of Work

  • The colours of overalls match those stated in the Plan of Work (or Standard Procedures)

  • The Plan of Work, and any amendments to it, form a live document that should be kept up to date at all times. Therefore, you should find that the Plan of Work accurately mirrors what you have observed. This standard is all about assessing adherence to the Plan of Work by the site team. The information would mostly be found in the Plan of Work, supplemented by the Standard Procedures.

4.4

  • The arrangements in the Plan of Work clearly convey how management have envisaged the work to be carried out

  • The Plan of Work clearly details when the work is to be carried out, including dates, start/finish times and weekend variations

  • The Plan of Work details the analytical company providing the 4-stage clearance<br>

  • The Plan of Work details who the analytical company is contracted to<br>

  • The Plan of Work (or Standard Procedures) details the enclosure entry and exit procedures

  • The Plan of Work (or Standard Procedures) details the arrangements for smoke testing and witnessing

  • The Plan of Work details the air monitoring arrangements for the duration of the works

  • The arrangements for waste disposal are clearly described in the Plan of Work, and evident on site

  • The Plan of Work (or Standard Procedures) details the method and permissions required to amend the Plan of Work

  • Welfare facilities are detailed in the Plan of Work and are available for use as described

  • This standard also assesses adherence to the Plan of Work, with particular emphasis on how the job has been planned by management.

4.5

  • Where amendments to the Plan of Work have been required, these have been authorised by the appropriate level of management

  • Required amendments to the Plan of Work / Sketch Plan have been made?

  • The required amendments have been correctly authorised where necessary?<br>

  • If amendments have been required they should have been made. If the changes are such that management authorisation was required, there should be a record of who authorised the change and when.

4.6

  • The scope of works is adequately described in the Plan of Work, and it matches the details recorded on the ASB5

  • The details in the Plan of Work are accurately reflected in the information provided on the ASB5<br>

  • The ASB5 is a summary of key information extracted from the Plan of Work, and therefore the details in the Plan of Work and on the ASB5 should match. In addition, the details should also match what is seen on site

4.7

  • Any other observation or concern relating to the Plan of Work to be noted here.

Section 5 - Measuring and Monitoring

5.1

  • All components of full face RPE are uniquely identifiable, and inspection records are complete for all RPE in use

  • All components of full face RPE are uniquely identifiable?

  • RPE inspection records are available on site and are up to date?

  • A respirator needs a service record. It cannot have a complete service record unless all parts are identifiable. Each component does not necessarily have to have the same number, just so long as each component is identifiable. This may be by serial number, name or initials etc. Up to date daily RPE inspection records should be available for all workers in the enclosure and anyone else likely to be involved in the works, e.g. waste run. There should also be copies of monthly RPE inspection records on site.

5.2

  • Daily site and plant inspection records are available for inspection and are up to date

  • Enclosure

  • Airlock

  • Baglock

  • NPU(s)

  • NPU pressure gauge readings

  • NPU anemometer readings

  • Vacuum cleaners

  • DCU

  • DCU pressure gauge readings for NPU

  • Blasting equipment

  • Scaffolding / mobile towers

  • MEWP’s

  • There should be records kept of all the elements listed, where applicable. These should be up to date at all times.

  • Other

  • Any other equipment that would require inspection records to be included here.

5.3

  • A smoke test record for the enclosure has been completed, and the witness details match those stated in the Plan of Work

  • A smoke test record has been completed

  • The smoke test was witnessed by the person / organisation detailed in the Plan of Work

  • There should be a smoke test record, which should match up with the arrangement in the Plan of Work, including being witnessed as per the Plan. Make a note if witness details do not match. On the rare occasion when a smoke test is not feasible, this should have been determined at the planning stage and a suitable alternative arrangement for checking the integrity of the working enclosure should be detailed in the Plan of Work, and a record kept which shows the arrangement has been followed.

5.4

  • Air monitoring and personal sampling has been carried out in an appropriate time period, with a clear indication of the tasks being undertaken during monitoring

  • Background / leak tests and/or personal monitoring have been planned for this job according to the Plan of Work

  • It would be reasonable to expect the air monitoring programme to have commenced by the point of audit

  • Air monitoring has been undertaken as proposed

  • Personal air monitoring records provide a clear indication of the tasks being undertaken during monitoring

  • The first item on the checklist determines whether any air monitoring has been planned for the job in addition to the 4 stage clearance. The second and third items test whether this has been done (or arranged) as planned, within reason. Any personal monitoring having been undertaken should also clearly describe what tasks were being undertaken during the monitoring.

5.5

  • There is evidence of management involvement to monitor progress and standards on site, through management visit, internal audit or inspection

  • There is evidence of management involvement on site since the commencement of works, e.g. site visit as scheduled in the Plan of Work

  • Management involvement was scheduled to have taken place, but there is no evidence of such involvement

  • It would be unreasonable to expect management involvement up to the point of audit, e.g. early stage of contract, or future visit scheduled

  • Remedial action has been taken as a result of the management involvement

  • The Plan of Work will often state how often managers and directors will visit site as part of management of the job. This is a check on whether this has taken place as planned, or otherwise. If a visit has been made, was there an outcome, feedback, remedial action required etc.? Is there evidence of any required action having been implemented?

5.6

  • Other observations relating to measuring and monitoring

  • Any other observation or concern relating to the measuring and monitoring to be noted here.

Section 6 – Supporting Documentation

6.1

  • The copy of Standard Procedures on site is current, and matches the version referred to in the Plan of Work

  • Standard Procedures are on site, and appear current

  • The Plan of Work references the Standard Procedures

  • The version number of the Standard<br>Procedures matches the reference in the<br>Plan of Work

  • The Standard Procedures document on site should be current, so far as you are able to ascertain. The Plan of Work should make reference to the current version of Standard Procedures.

6.2

  • A copy of the current HSE licence, and evidence of current employer’s and public liability insurance are on site

  • A copy of the current HSE licence is available on site

  • Evidence of current employer’s liability insurance is on site

  • Evidence of current public liability insurance is on site<br>

  • A copy of the licence should be available on site. It doesn’t need to be displayed. Note that two types of insurance are called for here, and you need to see evidence of both. Usually these are both recorded on a single schedule. A certificate of insurance is likely to only show employer’s liability. A “to whom it may concern” letter would be acceptable, providing it is current

6.3

  • Current certificates of thorough test and inspection are available for all plant on site

  • NPU(s) on enclosure

  • Vacuum cleaners

  • NPU in DCU

  • These should all be available on site, with serial numbers matching the equipment being used.A current certificate attached to the equipment is not ideal but acceptable. A sticker on the equipment is not acceptable as a certificate of thorough test and inspection.

6.4

  • Medical, training/competency and face fit certification for 2 selected employees is relevant and in date, and authenticated where necessary

  • Name Of Employee 1

  • Employee is in the enclosure

  • Current medical certificate is on site

  • Evidence of competence (competence certificate less than 12 months old or current training certificate or evidence through TNA) is on site

  • Face fit test certificate is available for the RPE in use

  • Employee is clean shaven

  • Select a supervisor or operative, at random. Indicate whether they are in the enclosure or not. You can include anyone on site who is involved in the site works. Permitted exemptions would include the driver who has quite obviously just arrived on site to deliver a piece of equipment, or the contracts manager who is attending site in his role as a contracts manager. Current medical certificates should be present. If they really have just had a medical and are awaiting the certificate, then ARCA would expect a note from the office to already be present in the file to cover this. The supervisor and each operative on site should be able to produce either a certificate of competence issued by the Royal Society for the Promotion of Health (RSPH), which is no more than 12 months old or a current training record (new or refresher, valid for 1 year) or evidence of competence derived through Training Needs Analysis by their employer. For the RSPH certificate, level 2 refers to operatives, and level 3 to supervisors. Face fit tests should match up to the RPE in actual use. It is not uncommon to find operatives using one type of RPE and having a face fit test certificate for another type. Note that there is no official expiry date for a face fit test. Employees should be clean shaven. If they are in the enclosure, it is not necessary for the auditor to try to observe and confirm this.

  • Name Of Employee 2

  • Employee is in the enclosure

  • Current medical certificate is on site

  • Evidence of competence (competence certificate less than 12 months old or current training certificate or evidence through TNA) is on site

  • Face fit test certificate is available for the RPE in use

  • Employee is clean shaven

  • Select a supervisor or operative, at random. Indicate whether they are in the enclosure or not. You can include anyone on site who is involved in the site works. Permitted exemptions would include the driver who has quite obviously just arrived on site to deliver a piece of equipment, or the contracts manager who is attending site in his role as a contracts manager. Current medical certificates should be present. If they really have just had a medical and are awaiting the certificate, then ARCA would expect a note from the office to already be present in the file to cover this. The supervisor and each operative on site should be able to produce either a certificate of competence issued by the Royal Society for the Promotion of Health (RSPH), which is no more than 12 months old or a current training record (new or refresher, valid for 1 year) or evidence of competence derived through Training Needs Analysis by their employer. For the RSPH certificate, level 2 refers to operatives, and level 3 to supervisors. Face fit tests should match up to the RPE in actual use. It is not uncommon to find operatives using one type of RPE and having a face fit test certificate for another type. Note that there is no official expiry date for a face fit test. Employees should be clean shaven. If they are in the enclosure, it is not necessary for the auditor to try to observe and confirm this.

  • For certificates where the name of the company being audited has not been recorded on the certificate by the provider; Has each copy been authenticated by, or under the direction of, senior management, with a statement confirming their validity?<br>

  • This requirement applies only to copies of certificates – original certificates need not be authenticated. For auditing purposes, this requirement applies to copies of certificates that do not have the name of the company you are auditing printed on them by the certificate provider. For example, if the certificate was awarded to Joe Bloggs of XYZ Asbestos Ltd, and you are auditing XYZ Asbestos Ltd, then no further action is required for this part of the audit. Where the copy certificate does not bear the name of the company being audited (i.e. no company name, or different company name) then these copies should be verified / authenticated by the contracting company, usually with an official company stamp and individually signed and dated by a senior representative of the employer (i.e. not by the site supervisor). There should also be a statement confirming their validity. Indicate yes only if all copy certificates requiring validation were verified or authenticated. Copies of authenticated certificates are acceptable, which is a change from the previous guidance. Stamps that merely state “copy” or “checked” or only display the company name are not sufficient. Some licence holders may opt to provide site packs in electronic format. For site audit purposes, ARCA would accept electronic copies of employee certificates, providing they are accessible, in date, and there is a declaration by an authorised person from the licence holder company, within the data folder, that the copies provided electronically are verified / authenticated copies. There would be no need for each copy certificate to display the validation stamp, signature etc

6.5

  • There is a clearance test certificate for the DCU from the previous job

  • A clearance test certificate is available for the DCU in use

  • It may be difficult to know if the certificate is actually from the previous job, or for a job prior to that. Make a judgement if you think the certificate presented is the most recent or not

6.6

  • Other observations relating to supporting documentation

  • Any other observation or concern relating to supporting documentation to be noted here.

Section 7 - Additional Notes

  • Any other notes, observations or explanations can be included here

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.