Section 1 - CONTRACT DETAILS AND SCOPE OF WORK
Client Details
-
Name of client:
-
Client address:
-
Client contact name:
-
Client Number:
RIS PROJECT MANAGEMENT CONTRACT DETAILS
-
RIS Regional Office:
-
Contact Number:
-
Site supervisor:
-
Contact number:
-
Project Manager:
-
Contact number:
-
Site specific access arrangements:
PROJECT DESCRIPTION
-
Brief description of project:
-
Location:
-
Form of asbestos containing material:
- Sprayed Coating
- Boiler Insulation
- Pipe Insulation
- AIB
-
Asbestos Fibre Types
- Amosite
- Chrysotile
- Crocidolite
- Other
-
Extent of ACM to be removed (linear meters / m2)
-
Number of operatives to be employed:
-
Start date on site:
-
Duration of works (days)
-
Hours of work start:
-
Hours of work end:
-
Weekend Working?
ASBESTOS SURVEY DETAILS
-
Asbestos survey available?
ANALYTICAL SERVICES
-
Analytical Services Required:
-
4 Stage Clearance
-
Date:
-
Personal
-
Date:
-
Reassurance
-
Date:
-
Background
-
Date:
-
Vehicle
-
Date:
CDM 2015 DETAILS
-
CDM notifiable project?
-
F10 submitted by client?
-
Name & address of principle designer:
-
Principle designer Representative:
-
Contact number:
-
Name & address of principle contractor:
-
Principle contractor representative:
-
Contact number:
SITE INDUCTION AND BRIEFING
-
Site induction from client available?
SECTION 2 - ENCLOSURE DETAILS
-
No of enclosures:
ENCLOSURE 1 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 1 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 2 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 3 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 4 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 5 DETAILS
-
Condition:
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 6 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 2 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 3 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 4 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 1 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 2 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 3 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 4 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
ENCLOSURE 5 DETAILS
-
Location:
-
Dimensions (Height x Width x Length):
-
Dimensions (m3):
-
Expected fibre concentration controls:
-
Quantity (m2/m):
-
Condition:
-
Level of control:
-
Fully controlled conditions with asbestos & respirator zones with an enclosure under negative pressure, and use of a decontamination unit. Semi controlled conditions with asbestos and respirator zones with the use of a decontamination unit. (INSERT JUSTIFICATION OF SEMI CONTROLLED)
-
The ACM current surface finish:
-
The ACM is fixed place with:
- bolts
- nails
- screws
- clipped
- Unknown fixings
- N/A
- debris
-
Insert pictures of the Asbestos material to be removed:
-
Picture 1
-
Picture 2
DCU -DECONTAMINATION UNIT
-
Power for the DCU will be obtained from:
-
240v 3 pin socket location:
-
Water for the DCU will be obtained from:
-
Location of water supply:
-
Waste water from the DCU will be disposed down the foul drain located:
-
Discharge drain location:
-
Can the DCU be directly connected to the Enclosure:
-
The DCU on this project will be attached directly to the enclosure via a 2 stage tunnel in accordance to the site drawing.
-
Direct connection is not possible due to the location of the enclosure.
POWER & WATER
-
Power from the DCU enclosure is to be obtained from:
-
Picture of power source:
-
Water for the enclosure is to be obtained from:
-
Direct water supply location:
-
Picture of water source:
NPU
-
NPU location:
AIR LOCK & BAGLOCK
-
Type of Air & Baglock
-
More information:
ASBESTOS & RESPIRATOR CONTROLLED ZONES
-
Asbestos and respirator controlled zones information:
WASTE ROUTE AND TRANSIT ROUTE
-
Transit route:
-
Transit route photo 1:
-
Transit route photo 2:
-
Transit route photo 3:
-
Waste route:
-
Waste route photo 1:
-
Waste route photo 2:
-
Waste route photo 3:
SECTION 3 - EQUIPMENT / RPE / PPE REQUIRED
-
Equipment required:
-
1500 NPU
-
2000 NPU
-
4000 NPU
-
5000 NPU
-
Powered Airless Sprayer
-
Hand Held Sprayer
-
"H" Type vacuum
-
Wet Strip Injection Machine
-
Mobile Hygiene Unit
-
Single Shower - 4 men
-
Twin Shower - 8 men
-
Vision Panels
-
CCTV
PPE AND RPE REQUIRED
RPE
-
Site setup
-
Pre Clean
-
Removals
-
Waste
Site PPE to be worn:
-
Ear defenders?
-
Safety Boots?
-
Hard Hat?
-
Hi-visibility Vest?
-
Gloves?
-
Waterproofs?
-
Flame retardant coveralls?
-
Safety Glasses?
-
Safety Harness?
-
Other?
-
Info:
ACESS EQUIPMENT
-
Access Equipment
- Podium steps will be utilised and inspected prior to use by a competent PASMA trained of staff.
- A mobile access tower will be erected and inspected prior to use by a competent PASMA trained person.
- Fixed scaffolding will be utilised on this project, scaffolding to be erected by competent scaffolding company, hand over certificate/s must be obtained and valid scaf tags fitted to the scaffolding prior to he fixed scaffold.
- Due to space restrictions step ladders will be utilised, steps will be footed at all times and will be used for short duration works only.
- MEWP
-
Podium
-
Step ladder
-
MWEP (Scissors)
-
Mobile tower
-
Hop up
-
Extension ladder
-
Fixed Scaffolding
-
Info:
-
MEWP (Boom)
-
Other?
-
Info:
SECTION 4 - SITE SPECIFIC ARRANGEMENTS
SITE WELFARE ARRANGEMENTS
-
Independent welfare unit:
-
Toilets:
-
Rest area:
ISOLATIONS
-
The following isolations will be arranged by:
Live services identified requiring isolation:
-
Lighting - ceiling:
-
Lighting - wall:
-
Fire alarm/s:
-
Compressor/s:
-
Boiler/s:
-
Water pipe:
-
Pipe work:
-
Flue pipe external:
-
Flue pipe internal:
-
Air handling unit/s:
-
Gas supply:
-
Sprinkler head system:
-
Other:
Services to be isolated:
-
Picture 1:
-
Picture 2:
-
Picture 3:
SECTION 5 - ASBESTOS REMOVAL METHOD:
-
Detailed asbestos removal method:
SECTION 6 - EMERGENCY PROCEDURES:
-
Fire extinguisher locations:
-
Emergency Muster Point Location:
-
First Aid Loction:
-