Robinson Quality assurance
-
Conducted on
-
Site conducted
-
Plot no.
-
Prepared by
1st fix plumbing
Soils and waste pipe.
-
Soil stacks fitted to manufacturers instruction with minimal bands at low level, clipped minimum 2 per story.
-
Waste pipe fitted correctly adequate support and fitted to minimum falls.
-
All soils and waste to avoid touching any other materials where possible, otherwise wrapped with a suitable material to separate.
-
All penetrations made through walls or joists within correct drilling zones.
-
All final soil and waste positions correct to builders drawings.
-
Soils pre tested to 38mm ready for pre plaster inspection.
Service pipework installation.
-
All plastic and copper pipework supported correctly.
-
Pipework correctly located in bathrooms and kitchen.
-
All pipework sized as per builders design.
-
Pipework installed neatly in straight lines.
-
Separation between hot and cold services, lagged when passing over is unavoidable.
-
Plastic pipework in walls made identifiable with metal detection tape as per builders spec.
-
Copper pipework chased in blockwork as per builders spec.
-
Radiator feeds to avoid common fixing points.
-
Primary's fully lagged as per building regs.
-
Hot and cold identification with either clips or approved talon ID tape.
-
All plumbing pipework pressure tested to manufacturers instruction and witnessed by site team.
Gas installation.
-
Gas to be sized correctly considering size of boiler, length of run and other appliances.
-
Gas pipe to be supported adequately and to be wrapped through joists to dampen noise with noise movement.
-
Gas pipe to be identified with yellow gas tape.
-
Gas pipework chased in clockwork walls to be mucked in ( site dependent if done by others).
-
Gas pipe to be tested minimum 1 bar for 30 mins.
Protection and house keeping.
-
All shower trays protected as per site spec ( protection provided by site).
-
All pipe ends capped with either silicone caps or tape.
-
Pipe ends secured in place or clipped back to avoid trip hazards.
-
Additional notes.
2nd Fix Plumbing
2nd Fix Heating
-
Radiators to be fitted level and in a central position with minimal pipe showing. Plastic wrapping left on radiators for protection.
-
Towel rails to be fitted level with straight pipe connections.
-
Boiler to be fitted neatly in accordance with gas safe, with flue complete.
-
Cylinder ( if required) fitted neatly in cupboard with isolation valves, with consideration for lagging.
-
TRV's fitted to all radiators except rooms with a thermostat installed.
-
Gas pipe for hob turned up and capped ( if required).
-
Connect gas to meter and complete tightness test, ensuring sleeve is sealed.
Sanitaryware
-
Sanitaryware installed correctly using all fixing points.
-
Bath to be fitted to accommodate Bath panel and level. Weight distributors under feet to be a minimum of 25mm x 100mm timber. Bath feet secured to floor and Bath sealed to walls.
-
Glassware to be fitted to manufacturers instructions.
-
Shower fitted with riser rail to accommodate shower head centre.
-
Kitchen sink pipework to be fitted to water regs, neat and fixed correctly leaving services for appropriate appliances.
-
All outlets tested to overflow to ensure correct fitting.
Filling and testing.
-
Fill system before making good and paint.
-
Check hot and cold feeds are correct at all outlets.
-
Fill heating system leaving the radiator closest to the filling loop shut down with inhibator installed.
-
Complete heat test, checking all zones are correct and working individually.
-
Check bath tempreture doesn't exceed 48°c.
Protection and house keeping.
-
All excess material to be removed from plot.
-
All protection installed (provided by site).
-
Any damages to plumbing fixtures or fittings.
-
Addition notes.
Plumbing finals
Finals.
-
Rossetts to be fitted as per builders spec.
-
Toilet seats to be fitted on all toilets, boxing to be left on for protection.
-
Lagging fitted as per builders spec.
-
Labels to be fitted in sink and airing cupboard.
-
Boiler commissioned Benchmark book filled out and copies taken for registration, book left with site team.
-
Cylinder ( where required) commissioned Benchmark book filled out and copies taken for registration, book left with site team.
-
Outside tap fitted and tested.
-
Whole system checked for leaks and system left on frost protection.
-
Open up the last radiator which has the inhibator in.
-
Complete adey pro check.
Additional notes and protection.
-
Any excess material removed from plot.
-
Any damages to plumbing fixtures and fitting.
-
Additional notes.