Pre-Construction Audit
-
Has an infection control risk assessment & interim life safety measures assessment been performed prior to the start of work in all areas?
-
Have all infection control risk assessments & interim life safety measures assesments been filed and made accessible to everyone necessary?
-
Have all infection control risk assessments & interim life safety measures assesments been reviews by the owners representatives and RCCI staff?
-
Have requirements of all active infection control risk assessment & interim life safety measures assessments been communicated to all subcontractors performing the work in associated areas?
-
Have all employees completed the healthcare orientation prior to starting work?
-
Is a temporary but equivalent system <br>provided when the fire system is impaired?
-
Has a negative air flow been established in all areas of work?
-
Have sealed partitions been installed around each area of work?
Interim Life Safety
-
Are all exits and alternate routes identified and usable?
-
Are the means of egress in the construction area are inspected daily?
-
Are all fire alarm and suppression systems unimpaired?
-
Before fire alarm systems are taken out of service, has appropriate authority been notified?
-
Additional fire protection equipment in place and has been inspected?
-
Are hot work permits being turned in daily and is a fire watch program established and used when required?
Infection Control
-
Is a negative pressure indicator (manometer, ball-in-the wall, etc.) in place at each area of work?
-
Is airflow being monitored on a regular basis?
-
Are airflow and air quality reports being received and filed on a regular basis?
-
Are all negative air machines functioning properly?
-
Are all duct returns capped, terminated or filtered?
-
Has all stored duct been sealed appropriately?
Housekeeping
-
Are areas of work being kept clean/swept in order to minimize track-out?
-
Are all corridors and surrounding areas swept/vacuumed and clean with no track-out?
-
Are all trash bins, gondolas, carts etc. cleaned prior to exiting work areas?
-
Are the wheels of all bins, gondolas, carts, etc. cleaned prior exiting work areas?
-
Have walk-off/sticky/damp mats been installed at the exits of work areas?
PPE
-
Is proper PPE worn at all times on site (hard hat, safety glasses, high viz, long pants and boots)?
-
Is task specific PPE worn when necessary(gowns, booties, masks, respirators, etc.)?
Area Isolation and Access Control
-
Do all temporary doors into work areas latch and lock properly?
-
Have closures and seals been installed in all temporary doors?
-
Is the integrity of the construction barriers maintained?
-
Is the construction area properly restricted from the rest of the facility with appropriate signage?
-
Has controlled work permit been completed?