Documentation review - Prior to undertaking a plant/vehicle movement review, please make yourself familiar with Principal Contractor documents, (tick applicable)

  • Vehicle movement plan(s)

  • Safety Management System requirements for plant/vehicle movements.

  • SWMS covering plant/vehicle movements.

  • Other documentation the PC may have on plant/vehicle movements and controls.

  • TfNSW document, "Separate Yourself"

  • TfNSW document - TPR-G22 "Truck and Plant Requirements".

Review Questions

  • Are plant/vehicle routes delineated?

  • Are HV and LV routes separated and well identified?

  • Is radio communication required between plant/vehicles?

  • Are radio channel(s) well sign posted?

  • Monitor the radio channel(s) for a period - are comm's requirements being followed?

Spotters

  • Are spotters being used on-site? if NO go to next section.

  • Spotters are isolated from plant/vehicle movements?

  • Have good line-of-sight of plant/vehicles?

  • Are identifiable from general site workers?

  • Have radio communications?

  • Are vehicles/plant complying with their instructions?

  • Only perform spotter duties?

Review Questions continued

  • Have LV parking areas been established at the work area(s) which comply with Separate Yourself guidelines?

  • Have parking area(s) been established on risk management principles?

  • If hazards have not been eliminated are they controlled?

  • Have HV parking area(s) been established at the work site(s)?

  • Are HV parking areas level?

  • If HV parking area(s) are not level, has the risk of run-away been controlled?

  • If HV/plant are temporarily parked on-site, have they been turned off, gear box in "P" or an appropriate gear and handbrake applied?

Safety Devices

  • All plant/vehicles fitted with a roof mounted (or similar) rotating/flashing, amber light?

  • Audible, reversing squawker or buzzer?

  • Reversing camera? - NOT a requirement under TPR-G22

  • Reversing light? - NOT a requirement under TPR-G22

Safety Devices - Nonconformities

  • If either plant or HV have an inoperable or inaudible reversing alarm, they must not continue to operate and should be removed from site. As per TGR-G22

Administrative Controls

  • Have pre-start checks been completed on plant?

  • Are plant movements and associated hazards discussed at pre-start meetings?

  • Plant operators have undertaken a VOC for this project?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.