Information

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Personnel

Exterior

Exterior

  • Propane cylinders are stored in a cage

  • Oxy / acetylene cylinders secured properly

  • Safety barriers are in good condition around fire hydrants and PIV's where necessary

  • Exterior doors are in good condition and secure, strip curtains in place at dry dock delivery door

  • Adequate quantity of wheel chocks are available

  • Security cameras are all functional

  • Wheel chocks are being used as intended

  • Egress doors are not obstructed

  • Security fencing is in good condition

  • Security gates are in good condition

  • PIV ramp to shipping door 31 is in good repair, ramp surface, railing, strip curtains

  • Exterior lighting is all working properly

  • Traffic signs are in good condition and in proper locations

  • Dock door Red / Green safety lights are working properly

  • Fire hydrants, PIV's are protected, fire department hook up is labeled, accessible, pavement is clearly painted and marked

  • Generators appear to be in good condition, access doors are locked, no visible leaks of fuel

  • Fire pump house is secured, all panel indicator lights are in working order, free of debris, is clean, no exposed wires, lighting inside and out is on working order, confined space signage is in place

  • Other items that were found but not included in this report

Roof

Roof

  • Doors and hatches operate properly

  • Hand rails along condenser area is in place and secure

  • Ladders and ladder cage in place and secure on condensers

  • Ventilation exhaust fans secure

  • No storage of supplies on roof unless in secure cabinet

  • No debris on roof

  • Piping appears to be in good condition

  • Piping appears to be well supported

  • No signs of ammonia leaks are noticed

  • Roof drainage is unrestricted

Building Maintenance

Building Maintenance

  • All PIV operators have completed a pre shift inspection, information is legible

  • Hot work permits are accessible, audit process is in place and is being utilized

  • Eye wash station is clean and accessible. Bump test during audit completed

  • Parts cleaner lid is closed

  • Fire protection panel is free from alarms, fire protection system is in "ready" mode and operational. Weekly / monthly inspections are on file and up to date.

  • All combustibles stored properly

  • Housekeeping completed in a manner that doesn't create any safety hazards or, food safety concerns

  • No loose propane tanks in or around shop

  • No loose oxy / acetylene tanks in or around shop

  • Grinder guards in place and adjusted properly

  • Electrical extension cords in good condition. Verify cord and plug ends

  • Shop hand tools in good condition and all guards in place

  • Safety glasses available at shop entrance

  • Ladders are stored properly. Hung up or secured with c

  • Hot work area sign in place

  • Safe days posted and, is maintained with accurate information

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.