SAX1177-CO-XX-COM-003
-
Prepared by
1177 Ballynacor Commissioning Check Sheet
-
Date:
-
Site Address: Ballynacor WwTW 22-24 Ballynacor Lane Portadown Craigavon BT23 5RP www.saxlund.co.uk
-
(2x) Sludge Cake Truck Loading Silo; each including.
-
1 off Cake storage Silo
-
1 off Sliding Frame & Powerpack
-
1 off Discharge Screw Conveyor
-
1 off Truck Loading Screw Conveyor
-
Set of gate valves
-
1 off Truck Loading Panel
-
1 off MCC Panel
-
Set of Instruments
-
Commissioning Procedure Reference
-
Commissioning Procedure Specific Risk Assessment
-
Pre-Commissioning Checks - Date tested:
-
Dry Commissioning - Date tested:
-
Wet Commissioning - Date tested:
-
Pre & Dry Commissioning Tested by (on behalf of Saxlund Intl. Ltd) sign
-
print
-
date
-
Pre & Dry Commissioning Accepted by (on behalf of Client) sign
-
print
-
date
-
Wet Commissioning Tested by (on behalf of Saxlund Intl. Ltd) sign
-
print
-
date
-
Wet Commissioning Accepted by (on behalf of Client) sign
-
print
-
date
-
Pre-Commissioning Checks 1 General 1.1 Mechanical Installation: Complete
-
1.1 Accept/Reject
-
1.2 Hydraulic Circuit: Complete
-
1.2 Accept/Reject
-
1.3 Electrical installation and loop testing complete with appropriate certification issued: Complete
-
1.3 Accept/Reject
-
1.4 Client snags completed (if applicable)
-
1.4 Accept/Reject
-
1.5 Permit(s) to work in place?
-
1.5 Accept/Reject
-
2. Stream 1 - Silo/SF/HPP 2.1 Powerpack tank has been filled with hydraulic oil (ISO32 Mineral Oil): Complete
-
2.1 Accept/Reject
-
Print Name
-
2.2 Hydraulic cylinder rods are clean and free of grease and dust: Complete
-
2.2 Accept/Reject
-
2.3 Sliding Frame, inside of silo, clear of any debris
-
2.3 Accept/Reject
-
2.4 Cylinder cover and drip tray in place: Complete
-
2.4 Accept/Reject
-
2.5 Stuffing Box tightness checked and greased: Complete
-
2.5 Accept/Reject
-
2.6 All sensors in place and positioned: Complete
-
2.6 Accept/Reject
-
2.7 All silo access doors/hatches in place and open and close correctly: Complete
-
2.7 Accept/Reject
-
2.8 Hydraulic pipework flushed clean, and valves re-assembled: Complete
-
2.8 Accept/Reject
-
2.9 Silo roof instruments fitted
-
2.9 Accept/Reject
-
2.10 Truck loading panel mounted: Complete
-
2.10 Accept/Reject
-
3 Stream 1 - Discharge Screw Conveyor 3.1 Inspect inside of conveyor for foreign objects: Complete
-
3.1 Accept/Reject
-
3.2 Check bearings greased: Complete
-
3.2 Accept/Reject
-
3.3 Check stuffing box seals for grease and adjustment: Complete
-
3.3 Accept/Reject
-
3.4 Check gearbox for initial fill of oil & breather open: Complete
-
3.4 Accept/Reject
-
3.5 Check position and operating distance of rotation sensors: Complete
-
3.5 Accept/Reject
-
3.6 Check roller chain drive and sprockets greased: Complete
-
3.6 Accept/Reject
-
3.7 Check guards in place: Complete
-
3.7 Accept/Reject
-
3.8 Check discharge flanged connections: Complete
-
3.8 Accept/Reject
-
3.9 Check Slide Gate Valve in place and secure, including rubber compensator: Complete
-
3.9 Accept/Reject
-
4 Stream 1 - Truck Loading Screw Conveyor 4.1 Inspect inside of conveyor for foreign objects: Complete
-
4.1 Accept/Reject
-
4.2 Check bearings greased: Complete
-
4.2 Accept/Reject
-
4.3 Check stuffing box seals for grease and adjustment: Complete
-
4.3 Accept/Reject
-
4.4 Check gearbox for initial fill of oil & breather open: Complete
-
4.4 Accept/Reject
-
4.5 Check position and operating distance of rotation sensors: Complete
-
4.5 Accept/Reject
-
4.6 Check guards in place: Complete
-
4.6 Accept/Reject
-
4.7 Check discharge flanged connections: Complete
-
4.7 Accept/Reject
-
4.8 Check Slide Gate Valves are in place and secure, including rubber skirts: Complete
-
4.8 Accept/Reject
-
5 Stream 1 - Rotation Checks 5.1 Powerpack Motors: M002 Expected
-
5.1 M002 Measured
-
5.1 M002 Accept/Reject
-
5.1 M003 Expected
-
5.1 M003 Measured
-
5.1 M003 Accept/Reject
-
5.2 Discharge Screw Conveyor M001 Expected
-
5.2 M001 Measured
-
5.2 M001 Accept/Reject
-
5.3 Truck Loading Screw Conveyor M004 Expected
-
5.3 M004 Measured
-
5.3 M004 Accept/Reject
-
6 Stream 2 - Silo, Sliding Frame & Hydraulic Powerpack 6.1 Powerpack tank has been filled with hydraulic oil (ISO32 Mineral Oil): Complete
-
6.1 Accept/Reject
-
6.2 Hydraulic cylinder rods are clean and free of grease and dust: Complete
-
6.2 Accept/Reject
-
6.3 Sliding Frame, inside of silo, clear of any debris: Complete
-
6.3 Accept/Reject
-
6.4 Cylinder cover and drip tray in place: Complete
-
6.4 Accept/Reject
-
6.5 Stuffing Box tightness checked and greased
-
6.5 Accept/Reject
-
6.6 All sensors in place and positioned: Complete
-
6.6 Accept/Reject
-
6.7 All silo access doors/hatches in place and open and close correctly: Complete
-
6.7 Accept/Reject
-
6.8 Hydraulic pipework flushed clean, and valves re-assembled: Complete
-
6.8 Accept/Reject
-
6.9 Silo roof instruments fitted: Complete
-
6.9 Accept/Reject
-
6.10 Truck loading panel mounted: Complete
-
6.10 Accept/Reject
-
7 Stream 2 - Discharge Screw Conveyor 7.1 Inspect inside of conveyor for foreign objects: Complete
-
7.1 Accept/Reject
-
7.2 Check bearings greased: Complete
-
7.2 Accept/Reject
-
7.3 Check stuffing box seals for grease and adjustment: Complete
-
7.3 Accept/Reject
-
7.4 Check gearbox for initial fill of oil & breather open: Complete
-
7.4 Accept/Reject
-
7.5 Check position and operating distance of rotation sensors: Complete
-
7.5 Accept/Reject
-
7.6 Check roller chain drive and sprockets greased: Complete
-
7.6 Accept/Reject
-
7.7 Check guards in place: Complete
-
7.7 Accept/Reject
-
7.8 Check discharge flanged connections: Complete
-
7.8 Accept/Reject
-
7.9 Check Slide Gate Valve in place and secure, including rubber compensator: Complete
-
7.9 Accept/Reject
-
8 Stream 2 - Truck Loading Screw Conveyor 8.1 Inspect inside of conveyor for foreign objects: Complete
-
8.1 Accept/Reject
-
8.2 Check bearings greased: Complete
-
8.2 Accept/Reject
-
8.3 Check stuffing box seals for grease and adjustment: Complete
-
8.3 Accept/Reject
-
8.4 Check gearbox for initial fill of oil & breather open: Complete
-
8.4 Accept/Reject
-
8.5 Check position and operating distance of rotation sensors: Complete
-
8.5 Accept/Reject
-
8.6 Check guards in place: Complete
-
8.6 Accept/Reject
-
8.7 Check discharge flanged connections: Complete
-
8.7 Accept/Reject
-
8.8 Check Slide Gate Valves are in place and secure, including rubber skirts: Complete
-
8.8 Accept/Reject
-
9 Stream 2 - Rotation Checks 9.1 Powerpack Motors M006 Expected
-
9.1 M006 Measured
-
9.1 M006 Accept/Reject
-
9.1 M007 Expected
-
9.1 M007 Measured
-
9.1 M007 Accept/Reject
-
9.2 Discharge Screw Conveyor M005 Expected
-
9.2 M005 Measured
-
9.2 M005 Accept/Reject
-
9.3 Truck Loading Screw Conveyor M008 Expected
-
9.3 M008 Measured
-
9.3 M008 Accept/Reject
-
Pre-Commissioning Comments
-
Remedial Work Required?
-
Pre-Commissioning Accepted by Saxlund Print Name
-
Date
-
Pre-Commissioning Accepted by Client Print Name
-
Date
-
Dry Commissioning 10 Start Up 10.1 Pre-commissioning checks completed & signed off: Complete
-
10.1 Accept/Reject
-
10.2 Electrical & Control system checked and signed off by Client: Complete
-
10.2 Accept/Reject
-
10.3 Permission to Proceed / Permit to Work issued: Complete
-
10.3 Accept/Reject
-
11 Stream 1 - Sliding Frame, including Hydraulic Powerpack 11.1 Power pack motor rotation correct: Complete
-
11.1 Accept/Reject
-
11.2 Run motor-pump unit to prime pump, pipes, and cylinders: Complete
-
11.2 Accept/Reject
-
11.3 Powerpack tank oil level checked: Complete
-
11.3 Accept/Reject
-
11.4 Check stroking cycle of Sliding Frame: Complete
-
11.4 SF Accept/Reject
-
11.4 Check stroking cycle of Slide Gate Valve: Complete
-
11.4 SGV Accept/Reject
-
11.5 Move each cylinder to end of stroke, disconnect pressure switch: Complete
-
11.5 Accept/Reject
-
11.6 Dead head each cylinder to check pressure relief valve setting - Sliding Frame: Complete
-
11.6 SF Accept/Reject
-
11.6 Dead head each cylinder to check pressure relief valve setting - Slide Gate Valve
-
11.6 SGV Accept/Reject
-
11.7 Pressure transmitter set point - Tag No:
-
11.7 Pressure transmitter set point (Set: 175 Bar during construction): Complete
-
11.7 Accept/Reject
-
11.8 Cylinder limit switch position & function (in mm): Sliding Frame - Front:
-
11.8 Sliding Frame - Rear (mm):
-
11.8 Sliding Frame: Complete
-
11.8 Sliding Frame: Accept/Reject
-
11.8 Slide Gate Valve - Front (mm):
-
11.8 Slide Gate Valve - Rear (mm):
-
11.8 Slide Gate Valve: Complete
-
11.8 Slide Gate Valve: Accept/Reject
-
11.9 Hydraulic joints inspected: Complete
-
11.9 Accept/Reject
-
11.10 Powerpack instrument function & alarms. Oil high temperature alarm: Oil low level temperature alarm: Oil tank heater: (Complete)
-
11.10 Accept/Reject
-
11.11 Tank heater function & operation in °C - Set point:
-
11.11 Tank heater function & operation: Complete
-
11.11 Accept/Reject
-
11.12 Cylinder speed range/cycle time in seconds - Sliding Frame, In:
-
11.12 Cylinder speed range/cycle time in seconds - Sliding Frame, Out:
-
11.12 Sliding Frame - Complete:
-
11.12 Sliding Frame - Accept/Reject:
-
11.12 Cylinder speed range/cycle time in seconds - Slide Gate Valve, In:
-
11.12 Cylinder speed range/cycle time in seconds - Slide Gate Valve, Out:
-
11.12 Slide Gate Valve - Complete:
-
11.12 Slide Gate Valve - Accept/Reject:
-
11.13 Check Sliding Frame stuffing box adjustments and record system hydraulic pressure while in operation - Pressure (bar):
-
11.13 Complete
-
11.13 Accept/Reject
-
11.14 Sliding Frame Auto Luber fitted, set up and left running: Complete
-
11.14 Accept/Reject
-
12 Stream 1 - Silo 12.1 Odour control connection made and functioning: Complete
-
12.1 Accept/Reject
-
12.2 Lorry in position sensors aligned and functioning: Complete
-
12.2 Accept/Reject
-
12.3 Truck Loading panel positioned and functioning: Complete
-
12.3 Accept/Reject
-
12.4 Vibrating fork high-high level switch functioning: Complete
-
12.4 Accept/Reject
-
13 Stream 1 - Discharge Screw Conveyor 13.1 Motor current at start up: Expected
-
13.1 Motor current at start up: Measured
-
13.1 Accept/Reject
-
13.2 Motor running current: Expected
-
13.2 Motor running current: Measured
-
13.2 Accept/Reject
-
13.3 Isolator functions tested: Complete
-
13.3 Accept/Reject
-
13.4 MCC load protection fitted & set points: Complete
-
13.4 Accept/Reject
-
13.5 Check function/signal of rotation sensor: Complete
-
13.5 Accept/Reject
-
13.6 Check hydraulic slide gate valve open & closed sensor function: Complete
-
13.6 Accept/Reject
-
13.7 Check hydraulic slide gate valve fully opens and closes under power: Complete
-
13.7 Accept/Reject
-
13.8 Check function of hydraulic slide gate valve in relation to the Sliding Frame and Discharge Screw Conveyor operation as per FDS: Complete
-
13.8 Accept/Reject
-
14 Stream 1 - Truck Loading Screw Conveyor 14.1 Motor current at start up (amps): Expected
-
14.1 Motor current at start up: Measured
-
14.1 Accept/Reject
-
14.2 Motor running current: Expected
-
14.2 Motor running current: Measured
-
14.2 Accept/Reject
-
14.3 Isolator functions tested: Complete
-
14.3 Accept/Reject
-
14.4 MCC load protection fitted & set points: Complete
-
14.4 Accept/Reject
-
14.5 Check function/signal of rotation sensor: Complete
-
14.5 Accept/Reject
-
14.6 Check hydraulic slide gate valve (4) open & closed sensor function: Complete
-
14.6 Accept/Reject
-
14.7 Check hydraulic slide gate valve (4) fully opens and closes under power: Complete
-
14.7 Accept/Reject
-
14.8 Check hydraulic slide gate valve (3) open & closed sensor function: Complete
-
14.8 Accept/Reject
-
14.9 Check hydraulic slide gate valve (3) fully opens and closes under power: Complete
-
14.9 Accept/Reject
-
14.10 Check hydraulic slide gate valve (2) open & closed sensor function: Complete
-
14.10 Accept/Reject
-
14.11 Check hydraulic slide gate valve (2) fully opens and closes under power: Complete
-
14.11 Accept/Reject
-
14.12 Check hydraulic slide gate valve (1) open & closed sensor function: Complete
-
14.12 Accept/Reject
-
14.13 Check hydraulic slide gate valve (1) fully opens and closes under power: Complete
-
14.13 Accept/Reject
-
14.14 Check function of hydraulic slide gate valve (4) in relation to the Sliding Frame and Discharge Screw Conveyor operation as per FDS: Complete
-
14.14 Accept/Reject
-
14.15 Check function of all hydraulic slide gate valves in relation to the truck loading valve sequence as per FDS: Complete
-
14.15 Accept/Reject
-
15 Stream 1 - Software/Control System (functional) Checks 15.1 Powerpack start up sequence: Complete
-
15.1 Accept/Reject
-
15.2 System Start up sequence - Manual: Complete
-
15.2 Manual start: Accept/Reject
-
15.2 System Start up sequence - Automatic: Complete
-
15.2 Automatic start: Accept/Reject
-
15.3 Controlled Stop: Complete
-
15.3 Accept/Reject
-
15.4 Emergency Stop: Complete
-
15.4 Accept/Reject
-
15.5 Instrument fault/stop check - Hydraulic powerpack: Complete
-
15.5 HPP: Accept/Reject
-
15.5 Instrument fault/stop check - Discharge Screw Conveyor: Complete
-
15.5 DSC: Accept/Reject
-
15.5 Instrument fault/stop check - Truck Loading Screw Conveyor: Complete
-
15.5 Truck Loading SC: Accept/Reject
-
15.6 Interlock/control stop check - Hydraulic powerpack: Complete
-
15.6 HPP: Accept/Reject
-
15.6 Interlock/control stop check - Discharge Screw Conveyor: Complete
-
15.6 DSC: Accept/Reject
-
15.6 Interlock/control stop check - Truck Loading Screw Conveyor: Complete
-
15.6 Truck Loading SC: Accept/Reject
-
16 Stream 2 - Sliding Frame, including Hydraulic Powerpack 16.1 Power pack motor rotation correct: Complete
-
16.1 Accept/Reject
-
16.2 Run motor-pump unit to prime pump, pipes, and cylinders: Complete
-
16.2 Accept/Reject
-
16.3 Powerpack tank oil level checked: Complete
-
16.3 Accept/Reject
-
16.4 Check stroking cycle of Sliding Frame: Complete
-
16.4 SF: Accept/Reject
-
16.4 Check stroking cycle of Slide Gate Valve: Complete
-
16.4 SGV: Accept/Reject
-
16.5 Move each cylinder to end of stroke, disconnect pressure switch: Complete
-
16.5 Accept/Reject
-
16.6 Dead head each cylinder to check pressure relief valve setting - Sliding Frame: Complete
-
16.6 SF: Accept/Reject
-
16.6 Dead head each cylinder to check pressure relief valve setting - Slide Gate Valve: Complete
-
16.6 SGV: Accept/Reject
-
16.7 Pressure transmitter set point - Tag no.
-
16.7 Pressure transmitter set point - Set 175 bar during construction: Complete
-
16.7 Accept/Reject
-
16.8 Cylinder limit switch position & function (in mm) - Sliding Frame, front:
-
16.8 Sliding Frame, rear (mm):
-
16.8 Sliding Frame: Complete
-
16.8 Sliding Frame: Accept/Reject
-
16.8 Cylinder limit switch position & function (in mm) - Slide Gate Valve, front:
-
16.8 SGV, rear (mm)
-
16.8 SGV: Complete
-
16.8 SGV: Accept/Reject
-
16.9 Hydraulic joints inspected: Complete
-
16.9 Accept/Reject
-
16.10 Powerpack instrument function & alarms. Oil high temperature alarm: Oil low level temperature alarm: Oil tank heater: (Complete)
-
16.10 Accept/Reject
-
16.11 Tank heater function & operation in °C - Set point:
-
16.11 Complete
-
16.11 Accept/Reject
-
16.12 Cylinder speed range/cycle time in seconds - Sliding Frame, In:
-
16.12 Cylinder speed range/cycle time in seconds - Sliding Frame, Out:
-
16.12 SF: Complete
-
16.12 SF: Accept/Reject
-
16.12 Cylinder speed range/cycle time in seconds - Slide Gate Valve, In:
-
16.12 Cylinder speed range/cycle time in seconds - Slide Gate Valve, Out:
-
16.12 SGV: Complete
-
16.12 SGV: Accept/Reject
-
16.13 Check Sliding Frame stuffing box adjustments and record system hydraulic pressure while in operation. Pressure (bar):
-
16.13 Complete
-
16.13 Accept/Reject
-
16.14 Sliding Frame Auto Luber fitted, set up and left running: Complete
-
16.14 Accept/Reject
-
17 Stream 2 - Silo 17.1 Odour control connection made and functioning: Complete
-
17.1 Accept/Reject
-
17.2 Lorry in position sensors aligned and functioning: Complete
-
17.2 Accept/Reject
-
17.3 Truck Loading panel positioned and functioning: Complete
-
17.3 Accept/Reject
-
17.4 Vibrating Fork High-High Switch: Complete
-
17.4 Accept/Reject
-
18 Stream 2 - Discharge Screw Conveyor 18.1 Motor current at start up (amps): Expected
-
18.1 Motor current at start up (amps): Measured
-
18.1 Accept/Reject
-
18.2 Motor running current (amps): Expected
-
18.2 Motor running current (amps); Measured
-
18.2 Accept/Reject
-
18.3 Isolator functions tested: Complete
-
18.3 Accept/Reject
-
18.4 MCC load protection fitted & set points: Complete
-
18.4 Accept/Reject
-
18.5 Check function/signal of rotation sensor: Complete
-
18.5 Accept/Reject
-
18.6 Check hydraulic slide gate valve open & closed sensor function: Complete
-
18.6 Accept/Reject
-
18.7 Check hydraulic slide gate valve fully opens and closes under power: Complete
-
18.7 Accept/Reject
-
18.8 Check function of hydraulic slide gate valve in relation to the Sliding Frame and Discharge Screw Conveyor operation as per FDS: Complete
-
18.8 Accept/Reject
-
19 Stream 2 - Truck Loading Screw Conveyor 19.1 Motor current at start up (amps): Expected
-
19.1 Motor current at start up (amps): Measured
-
19.1 Accept/Reject
-
19.2 Motor running current (amps): Expected
-
19.2 Motor running current (amps): Measured
-
19.2 Accept/Reject
-
19.3 Isolator functions tested: Complete
-
19.3 Accept/Reject
-
19.4 MCC load protection fitted & set points: Complete
-
19.4 Accept/Reject
-
19.5 Check function/signal of rotation sensor: Complete
-
19.5 Accept/Reject
-
19.6 Check hydraulic slide gate valve (4) open & closed sensor function: Complete
-
19.6 Accept/Reject
-
19.7 Check hydraulic slide gate valve (4) fully opens and closes under power: Complete
-
19.7 Accept/Reject
-
19.8 Check hydraulic slide gate valve (3) open & closed sensor function: Complete
-
19.8 Accept/Reject
-
19.9 Check hydraulic slide gate valve (3) fully opens and closes under power: Complete
-
19.9 Accept/Reject
-
19.10 Check hydraulic slide gate valve (2) open & closed sensor function: Complete
-
19.10 Accept/Reject
-
19.11 Check hydraulic slide gate valve (2) fully opens and closes under power: Complete
-
19.11 Accept/Reject
-
19.12 Check hydraulic slide gate valve (1) open & closed sensor function: Complete
-
19.12 Accept/Reject
-
19.13 Check hydraulic slide gate valve (1) fully opens and closes under power: Complete
-
19.13 Accept/Reject
-
19.14 Check function of hydraulic slide gate valve (4) in relation to the Sliding Frame and Discharge Screw Conveyor operation as per FDS: Complete
-
19.14 Accept/Reject
-
19.15 Check function of all hydraulic slide gate valves in relation to the truck loading valve sequence as per FDS: Complete
-
19.15 Accept/Reject
-
20 Stream 2 - Software/Control System (functional) Checks 20.1 Powerpack start up sequence: Complete
-
20.1 Accept/Reject
-
20.2 System Start up sequence - Manual: Complete
-
20.2 Manual: Accept/Reject
-
20.2 System Start up sequence - Automatic: Complete
-
20.2 Automatic: Accept/Reject
-
20.3 Controlled Stop: Complete
-
20.3 Accept/Reject
- Accept
- Reject
-
20.4 Emergency Stop: Complete
-
20.4 Accept/Reject
-
20.5 Instrument fault/stop check - Hydraulic powerpack: Complete
-
20.5 HPP: Accept/Reject
-
20.5 Instrument fault/stop check - Discharge Screw Conveyor: Complete
-
20.5 DSC: Accept/Reject
-
20.5 Instrument fault/stop check - Truck Loading Screw Conveyor: Complete
-
20.5 Truck Loading SC: Accept/Reject
-
20.6 Interlock/control stop check - Hydraulic powerpack: Complete
-
20.6 HPP: Accept/Reject
-
20.6 Interlock/control stop check - Discharge Screw Conveyor: Complete
-
20.6 DSC: Accept/Reject
-
20.6 Interlock/control stop check - Truck Loading Screw Conveyor: Complete
-
20.6 Truck Loading SC: Accept/Reject
-
Dry Commissioning Comments
-
Remedial Work Required?
-
Dry Commissioning Accepted by Saxlund Print Name:
-
Date
-
Dry Commissioning Accepted by Client Print Name:
-
Date
-
Wet Commissioning 21 Start Up 21.1 Dry-commissioning checks completed & signed off: Complete
-
21.1 Accept/Reject
-
21.2 Upstream system Commissioning completed (BY OTHERS): Complete
-
21.2 Accept/Reject
-
21.3 Trucks available to receive material?
-
21.4 Material available as per schedule?
-
21.5 Material type:
-
21.5 Material Density (kg/m3):
-
21.5 Dry solids (%)
-
21.6 Permission to Proceed / Permit to Work issued
-
22 Stream 1 - Silo Level Instrumentation 22.1 Radar instrument commissioned: Complete
-
22.1 Accept/Reject
-
22.2 Level set-points programmed in. Upper set point (silo full) used to inhibit Infeed pumps S1
-
22.2 S2
-
22.2 S3
-
22.2 S4
-
22.2 S5
-
23 Stream 1 - Material Feed 23.1 Loading from connected pipeline - Initial min material load/feed rate
-
23.1 50% material load/feed rate
-
23.1 100% material load/feed rate
-
23.2 Feed into Silo - Initial min material load/feed rate
-
23.2 50% material load/feed rate
-
23.2 100% material load/feed rate
-
24 Stream 1 - Running Current at 100% material load (or max achievable rate) 24.1 Hydraulic Power Pack
-
24.2 Discharge Screw Conveyor
-
24.3 Truck Loading Screw Conveyor
-
25 Stream 1 - Software/Control System (Functional) Checks (as possible with feed requirements) 25.1 Start-up sequence - Manual: Complete
-
25.1 Manual: Accept/Reject
-
25.1 Start-up sequence - Automatic: Complete
-
25.1 Automatic: Accept/Reject
-
25.2 Controlled Stop: Complete
-
25.2 Accept/Reject
-
25.3 Emergency Stop: Complete
-
25.3 Accept/Reject
-
25.4 Instrument fault/stop check: Complete
-
25.4 Accept/Reject
-
25.5 Interlock/control stop check: Complete
-
25.5 Accept/Reject
-
25.6 Sliding Frame Cycle Time: Complete
-
25.6 Accept/Reject
-
25.7 Truck Loading Time (and final material load weight)
-
26 Stream 2 - Silo Level Instrumentation 26.1 Radar instrument commissioned: Complete
-
26.1 Accept/Reject
-
26.2 Level set-points programmed in. Upper set point (silo full) used to inhibit Infeed pumps: S1
-
26.2 S2
-
26.2 S3
-
26.2 S4
-
26.2 S5
-
27 Stream 2 - Material Feed 27.1 Loading from connected pipeline - Initial min material load/feed rate
-
27.1 50% material load/feed rate
-
27.1 100% material load/feed rate
-
27.2 Feed into Silo - Initial min material load/feed rate
-
27.2 50% material load/feed rate
-
27.2 100% material load/feed rate
-
28 Stream 2 - Running Current at 100% material load (or max achievable rate) 28.1 Hydraulic Power Pack
-
28.2 Discharge Screw Conveyor
-
28.3 Truck Loading Screw Conveyor
-
29 Stream 2 - Software/Control System (Functional) Checks (as possible with feed requirements) 29.1 Start-up sequence - Manual: Complete
-
29.1 Manual: Accept/Reject
-
29.1 Start-up sequence - Automatic: Complete
-
29.1 Automatic: Accept/Reject
-
29.2 Controlled Stop: Complete
-
29.2 Accept/Reject
-
29.3 Emergency Stop
-
29.3 Accept/Reject
-
29.4 Instrument fault/stop check: Complete
-
29.4 Accept/Reject
-
29.5 Interlock/control stop check: Complete
-
29.5 Accept/Reject
-
29.6 Sliding Frame Cycle Time
-
29.7 Truck Loading Time (and final material load weight)
-
Operational Data
-
Motor Current
-
Cycle Time
-
System Pressure
-
Approx. silo material height/ load
-
Operational data
-
Motor current
-
Cycle time
-
System pressure
-
Approx. silo material height/load
-
Wet Commissioning Comments
-
Remedial Work Required?
-
Wet Commissioning Accepted by Saxlund Print Name
-
Date
-
Wet Commissioning Accepted by Client Print Name
-
Date
Initial min 50% 100% material
-
27 Stream 2 - Material Feed
-
load/feed rate
-
27.1 Loading from connected pipeline
-
27.2 Feed into Silo
-
28 Stream 2 - Running Current at 100% material load (or max achievable rate)
-
28.1 Hydraulic Power Pack
-
28.2 Discharge Screw Conveyor
-
28.3 Truck Loading Screw Conveyor
-
Stream 2 - Software/Control System (Functional) Checks Accept / Reject
-
29.1 Start-up sequence; manual automatic
-
29.2 Controlled Stop
-
29.3 Emergency Stop
-
29.4 Instrument fault/stop check
-
29.5 Interlock/control stop check
-
29.6 Sliding Frame Cycle Time
-
29.7 Truck Loading Time (and final material load weight)
-
Page 18
-
Commissioning Checklist
-
Approx. silo system material
-
Operational data
-
Motor current
-
Cycle time
-
pressure
-
height/load
-
Page 19
-
Commissioning Check Sheet
-
Wet Commissioning Comments
-
Remedial Work Required?
-
Wet Commissioning Accepted by Saxlund
-
Print Name
-
Date: Wet Commissioning Accepted by Saxlund
-
Wet Commissioning Accepted by Client
-
Print Name
-
Date: Wet Commissioning Accepted by Client