Information
-
Address:
-
UPRN:
-
Front of Property:
-
Property Type:
-
Property Style:
- Terrace
- End Terrace
- Semi-detached
- Detached
- Ground Level
- Above Ground Level
-
Flat Floor Level
-
Main Contractor:
-
Produce on Behalf and For XXX Limited by :
-
Date of site visit:
General
General Observations
-
Insulation
-
K/B Extractor Fan
-
Quantity
-
Fan 1
-
Fan Route
- Existing on Ceiling & flexi pipe into loft space
- Flexi pipe already connected to roof vent
- New vent tile with existing flexi pipe
- New vent tile + new flexi
- Existing Through Wall
-
Fan 2
-
Fan Route
- Existing on Ceiling & flexi pipe into loft space
- Flexi pipe already connected to roof vent
- New vent tile with existing flexi pipe
- New vent tile + new flexi
- Existing Through Wall
-
Fan 3
-
Fan Route
- Existing on Ceiling & flexi pipe into loft space
- Flexi pipe already connected to roof vent
- New vent tile with existing flexi pipe
- New vent tile + new flexi
- Existing Through Wall
-
Sloping Ceiling
-
Satellite Dishes and TV arials
-
Quantity
-
Location
-
Remove and refix
-
Additional costing for aerial refix
-
Type of fixing needed
-
Renew or replace
-
Quantity
-
Skip Location
-
Skip Shute used
Primary Roof Level
-
Chimney
-
Quantity
-
Chimney 1
-
Shared
-
With Who
-
Chimney Removal
-
Quantity (m2)
-
Chimney Pot
-
Quantity
-
Replace
-
Quantity
-
Flaunching
-
Quantity (m2)
-
Chimney Pointing
-
Quantity (m2)
-
Chimney Flashing
-
Quantity (LM)
-
Chimney 2
-
Shared
-
With Who
-
Chimney Removal
-
Quantity (m2)
-
Chimney Pot
-
Quantity
-
Replace
-
Quantity
-
Flaunching
-
Quantity (m2)
-
Chimney Pointing
-
Quantity (m2)
-
Chimney Flashing
-
Quantity (LM)
-
Chimney 3
-
Shared
-
With Who
-
Chimney Removal
-
Quantity (m2)
-
Chimney Pot
-
Quantity
-
Replace
-
Quantity
-
Flaunching
-
Quantity (m2)
-
Chimney Pointing
-
Quantity (m2)
-
Chimney Flashing
-
Quantity (LM)
-
Chimney 4
-
Shared
-
With Who
-
Chimney Removal
-
Quantity (m2)
-
Chimney Pot
-
Quantity
-
Replace
-
Quantity
-
Flaunching
-
Quantity (m2)
-
Chimney Pointing
-
Quantity (m2)
-
Chimney Flashing
-
Quantity (LM)
Tiles
-
Existing Material
-
Existing Underfelt Present
-
Reclaim Potential
-
Proposed Material
-
Proposed Material Quantity
-
Ridge Tile Replacement
-
Quantity (LM)
-
Hip Tile Replacement
-
Quantity (LM)
-
Verge Replacement
-
Quantity (LM)
-
Bonding Gutter
-
Quantity (LM)
-
Roof Valleys
-
Quantity (Lm)
-
Eavesguard Replaced
-
Quantity (LM)
-
Tile Flashings Replaced
-
Quantity (LM)
-
Lead Slate Replaced/Installed
-
Quantity (No.)
-
Soil Vent Pipes
-
Through Roof
-
Eaves/Swan neck adjustment required
-
Quantity (No.)
Flue
-
Active Boiler flue
-
Location
-
Proximity to Scaffolding
Roofline
-
Facia, Soffit, Gutters measure inc. Eaves overhang (LM)
-
Facia Replacement
-
Soffit Replacement
-
Gutter Replacement
-
Downpipe Replacement
-
Quantity (No.)
-
Quantity (LM)
-
Clean down Existing Facia, Soffit, Gutters
Scaffolding
-
Property Levels
-
Scaffolding Servicing Roof Covering (LM)
-
Chimney Scaffold
-
Location
-
Table Lift Scaffold
-
Quantity (LM)
-
Handrail Protection
-
Quantity (LM)
-
Barrow Run Scaffold
-
Quantity (LM)
Secondary Roof
-
Is there a secondary Roof
Roof Level
-
Chimney
-
Shared
-
With Who
-
Chimney Pot
-
Quantity
-
Replace
-
Quantity
-
Flaunching
-
Quantity (m2)
-
Chimney Pointing
-
Quantity (m2)
-
Chimney Flashing
-
Quantity (LM)
-
Chimney Removal
-
Quantity (m2)
Tiles
-
Existing Material
-
Existing Underfelt Present
-
Reclaim Potential
-
Proposed Material
-
Proposed Material Quantity
-
Ridge Tile Replacement
-
Quantity (LM)
-
Hip Tile Replacement
-
Quantity (LM)
-
Verge Replacement
-
Quantity (LM)
-
Bonding Gutter
-
Quantity (LM)
-
Roof Valleys
-
Quantity (Lm)
-
Eavesguard Replaced
-
Quantity (LM)
-
Tile Flashings Replaced
-
Quantity (LM)
-
Lead Slate Replaced/Installed
-
Quantity (No.)
-
Soil Vent Pipes
-
Through Roof
-
Eaves/Swan neck adjustment required
-
Quantity (No.)
Flue
-
Active Boiler flue Location
-
Proximity to Scaffolding
Roofline
-
Building Perimeter for Facia, Soffit, Gutters (LM)
-
Facia Replacement
-
Soffit Replacement
-
Gutter Replacement
-
Downpipe Replacement
-
Quantity (No.)
-
Quantity (LM)
-
Clean down Existing Facia, Soffit, Gutters
Scaffolding
-
Property Levels
-
Scaffolding Servicing Roof Covering (LM)
-
Chimney Scaffold
-
Location
-
Table Lift Scaffold
-
Quantity (LM)
-
Handrail Protection
-
Quantity (LM)
-
Barrow Run Scaffold
-
Quantity (LM)
-
Can the handover be completed in one visit
-
Why can't the roof be handed over at this point
- Scaffolding needs moving to complete lower level
- Other
Canopy's
-
Canopy's
-
Leadwork replacement
-
Quantity (LM)
-
Material Quantity (m2)
-
Roofline Works
-
Building Perimeter for Facia, Soffit, Gutters (LM)
-
Facia Replacement
-
Soffit Replacement
-
Gutter Replacement
-
Downpipe Replacement
-
Quantity (No.)
-
Quantity (LM)
-
Clean down Existing Facia, Soffit, Gutters
Asbestos Removal
-
Asbestos Removed
-
Quantity (LM)
Snagging
-
Location
-
Defect Description
-
Photo
-
Priority/ Health & Safety
Signature
-
Content Within Including Measures Agreed on Behalf and For Equans Regeneration Limited by:
-
Signature
-
Signature
-
Signature
-
Acis Representative
-
Signature
-
Signature