Information
-
Audit Title (SBO Job Number yyyy mm dd)
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Describe the task you are observing
1.0 WORKING HABITS / COMPETENCY / BEHAVIOURS
-
1.1 PPE: Are team members wearing / using the prescribed personal protective equipment? Is the PPE in good condition?
-
1.2 Risk Awareness: Can team members describe at least 3 risks and the appropriate controls?
-
1.3 Competency & training: Is everyone inducted, licenced / trained for their task?
-
1.4 Emergency Procedure: Does the team know where the muster point is? Nearest Hospital? First Aid location / person?
2.0 HOUSEKEEPING / WORK ENVIRONMENT
-
2.1 Access / egress: Are pathways clear from hazards and debris
-
2.2 Trips / slips / falls / tidy: is the site neat and tidy? Free from slip, trip hazards?
-
2.3 Lighting: Is the lighting adequate?
-
2.4 Hygiene: Are the team working with waste? Is PPE appropriate? Are the correct procedures being followed?
-
2.5 Rubbish and waste: Placed in bins? Disposed in appropriate manner? Areas tidy?
3.0 COMMUNICATION & PROCEDURES
-
3.1 Have Pre Start talks or Risk Assessments been completed for today? Is the observed task included? (attach photo)
-
3.2 SWMS covering the task: Is it onsite? Relevant? In date? Has it been signed by all on site?
-
3.3 Isolation & lock-out: If required, has this been done correctly? Inspect locks and/or tags. Do they identify personal?
-
3.4 Non-verbal / verbal: Is communication between the team sufficient and working? Verbal, hand signals, radios or other?
4.0 MANUAL HANDLING & ERGONOMICS
-
4.1 Positions / posture: Has the least awkward position been used? Is posture correct?
-
4.2 Repetitive motions: Are the tasks rotated or breaks taken?
-
4.3 Over exertion: Could the activity cause stress, strain or damage? Are there alternives to using the large bursts of energy e.g. tools? Loads shared?
5.0 EQUIPMENT & TOOLS
-
5.1 Are all tools tested and tagged? Is the tag in date?
-
5.2 Tools & portable equipment condition: Are they in working order? Have repairs been completed by a qualfied person?
-
5.3 Lifting & rigging: Slings and chains tagged and in date?
-
5.4 Chemical storage: Is the SDS available? If required; area ventilated / bunded and secured?
-
5.5 Are the appropriate number of spill kits on site?
6.0 WORK AT HEIGHT / ELEVATED WORK
-
Does the task involve work at height or elevated work?
-
6.1 Work overhead signage is in place?
-
6.2 Permit / checklist completed?
-
6.3 Harness is being used and tagged?
-
6.4 Barricading is in place? Encompasses site and whole drop zone?
-
6.5 Appropriate equipment selected? (e.g. Ladder, EWP, Boom, Scaffold)
-
6.6 EWP / Boom pre-start completed? (attach photo)
-
6.7 Rescue Plan documented and known?
7.0 EXCAVATION
-
Does the task involve excavation?
-
7.1 Has the plant pre start check been completed and documented? (attach photo)
-
7.2 Is Signage and exclusion zone in place?
-
7.3 Excavation Permit completed?
-
7.4 Appropriate controls for depth? (>1.5m must have bench, batter or shoring)
-
7.5 Are sediment fences: Upright? Tight? Capturing sediment? Not overfull?
-
7.6 Drain protection: Adequate number of sandbags? water running through sandbag not around?
-
7.7 Air quality: Free of odours, fumes and dust?
8.0 CONFINED SPACE
-
Does the task involve confined space work?
-
8.1 Signage to prevent entry of persons not involved is displayed?
-
8.2 Permit: Completed? onsite? all requirements to standard? e.g. gas monitor calibrated
-
8.3 Rescue Plan documented and known?
-
8.4 Rescue equipment readily available, in date and in good condition?
9.0 HOT WORKS
-
Does the task involve hot works?
-
9.1 Permit: Completed? Onsite? To standard?
-
9.2 Fire extinguisher readily available, tagged and in date?
-
9.3 Area appropriate? (wet down, protected, combustible materials removed)
-
9.4 Adequeate Ventilation? (extraction fans, open vents, PPE)
-
9.5 Air quality: Free of odours, fumes and dust?
CORRECTIVE ACTIONS
-
Enter any corrective actions that will be undertaken.
-
Add signature