Information
-
Job No.
-
Warden Call Audit test
-
Hyde housing:
-
Conducted on
-
Engineer carrying out test:
-
Location
-
Add media
-
Manager name:
Before commencing test notify control centre of testing
Control cabinet test:
-
Mains failure
-
Mains restored
-
Low battery warning:
-
Power supply test voltages
-
Carry out battery testing and run system on standby:
Smoke detector testing:
-
Do all detectors operate correctly and signal control
Alarm signalling and communication
-
Do all signals from equipment work in all modes<br>On site<br>Off site<br>Remote off site
Handsets/Cordless phones
-
Do all functions on handset work correctly and is the condition of the handset acceptable for use and shows any sign of damage
Call points and pull cords test
-
Do all devices work correctly.report defects
Radio devices/receivers
-
Do all radio devices work .Report defects
Door entry panel test:
-
Carry out full functional panel test:report defects
Visual inspections
-
Cabling/trunking/modules etc are intact and no damage: Report defects
-
Engineer signature
-
Customer Signoff