Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Begin Audit with Facility Information

Warehouse Information

  • Add location
  • Select date

  • Audit completed By:

  • Are one line drawings available?

  • Is thermal imaging performed annually?

Primary Power

Transformers

  • How many primary service transformers on this site. Include any primary transformers used as part of emergency power system. Step up and step down.

  • Are the transformers owned by the utility?

  • Has the lead time been verified with the utility to replace the transformer?

  • What is the verified lead time to replace the transformer?

  • Is there a complete set of replacement Primary fuses?

  • In the event of an emergency has an alternate source for spare fuses been determined

  • Are the transformers tested and serviced on a regular basis?

Main distribution panels

  • Is there more than one service entrance?

  • Are there Main tie Mains?

  • Are there Kirk Keys for the Tie?

  • Has the necessary training been provided to the proper people in the use of the Main tie Main system?

  • Is there a complete set of main distribution fuses?

  • In the event of an emergency has an alternate source for spare fuses been determined.

Refrigeration

Condenser

  • Is there a spare condenser fan motor?

  • Is there a complete set of spare fan motor fuses?

  • Does the condenser fan run on a VFD?

  • Does the VFD have a Bypass

  • Is there a spare VFD?

  • Is there a complete set of spare fan belts?

  • Is there a spare water pump?

  • Is there a complete set of spare pump motor fuses?

  • Is the condenser makeup water supplied by a well?

  • In the event of a pump failure can the pump be replaced in less than 24 hours?

  • Is a complete set of replacement fuses for the pump in stock?

System

  • Do all critical components of the system have manual Hand\Off\Auto control?

  • List all non compliant components.

Automation

Inbound System

  • Is there and automated Inbound system?

  • Are there adequate spare parts for the crane system

Pallet Conveyor

  • Is there a spare Pallet Conveyor motor and gear box?

  • Is there a complete set of Pallet Conveyor motor fuses?

  • Are there spare PLC's and IO cards

  • Are all PLC programs backed up on a regular basis

  • Has adequate training been provided to service PLC's and restore programs.

Outbound System

  • Is there and automated Outbound system?

  • Is there a spare sorter motor and gear box?

  • Is there a complete set of sorter motor fuses?

  • Are there spare PLC's and IO cards

  • Are all PLC programs backed up on a regular basis

  • Has adequate training been provided to service PLC's and restore programs.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.