Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

1. General:

  • 1.1 Country:

  • 1.2 Region:

  • 1.3 Site name/ID:

  • 1.4 Site type:

  • 1.5 Project:

  • 1.6 Audit date:

  • 1.7 Auditor name:

  • 1.8 Company is Ceragon ASP:

  • 1.9 Sub-contractor name:

  • 1.10 Team leader name:

  • 1.11 ASP members are certified and quilified for equipment to be install:

2. Safety:

  • 2.1 Site risk assessment done?

  • 2.2 Safety preparations are done?

  • 2.3

  • 2.4

  • 2.5 Safety procedures are followed throughout the work and all employees aware?

  • 2.6 All required safety Hazard in place?

  • 2.7 First Aid kit are available?

  • 2.8 Test equipment in Use?

  • 2.9

  • 2.10

  • 2.11

3. Documentation

  • 3.1 Work was coordinate by Ceragon?

  • 3.2 Permit to work by Customer?

  • 3.3 Customer permit to access the SIte.

  • 3.4 Customer permit to commence the work.

  • 3.5 Site RFI by Customer?

  • 3.6 Inventory list of Equipment is available.

  • 3.7 HSE documents.

  • 3.8 IP Plan.

  • 3.9 TSS[Technical SIte Survey] document.

  • 3.10 Checklist file.

  • 3.11 Floor plan layout of Equipment room as per approved plan.

  • 3.12

  • 3.13 PL4/Budget link calculation are available.

  • 3.14 Usage of Antenna brochures.

  • 3.15 Usage of Ceragon best practice installation guides.

4. Logistic.

  • 4.1 All equipment arrived in proper condition?

  • 4.2 Equipment arrived without physical damage?

  • 4.3 All equipment crosschecked to the inventory list.

  • 4.4 All equipment was properly packed.

  • 4.5 Equipment was lodged well till installation.

  • 4.6 Equipment safety uploaded and unpacked.

  • 4.7 No DDA[Dad ]

  • 4.8 No missing materials.

5. Outdoor- Pol mount & Antenna

  • 5.1 Antenna Pol mount is assembled in accordance with manufacturer instruction.

  • 5.2 Antenna Pol mount is install in accordance with Ceragon instruction.

  • 5.3 Antenna Pol mount have sufficient clearance from existing obstruction.

  • 5.4 Antenna Pol mount is secured and vertical.

  • 5.5 Antenna Pol mount is safely positioned and not causes a Safety Hazard.

  • 5.6 Antenna assembled in accordance with Manufacturer instruction.

  • 5.7 Antenna is installed in accordance with Manufacturer instruction.

  • 5.8 Antenna was safety lifted.

  • 5.9 Antenna is secured mounted to the AMB[Antenna mount bracket]

  • 5.10 Antenna is installed with NO Physical damage?

  • 5.11 Antenna offset element is installed in accordance with Link Azimuth angle.

  • 5.12 Antenna is Azimuth & Elevated in accordance with Link Budget calculation report.

  • 5.13 Antenna Feeder Horn polarization is installed in accordance with Link BUdget prediction report.

  • 5.14 Antenna Arm strut is installed in accordance with manufacturer instruction.

  • 5.15 Antenna Arm strut azimuth secured in accordance with manufacturer tolerance angles instruction.

  • 5.16 OMT are installed in accordance to the manufacturer instruction.

  • 5.17 Flex WG installed & clamped in accordance to the manufacturer instruction[both sides]

  • 5.18 Flex WG sealed & waterproofed in accordance with Ceragon instructions.

6. Outdoor-ODU

  • 6.1 ODU installed in accordance with Ceragon guide installation instruction.

  • 6.2 ODU is securely mounted to the Antenna or Pol mount.

  • 6.3 ODU has no physical damage.

  • 6.4 ODU installed in a proper way for future maintenance.

  • 6.5 ODU polarization positioned in accordance with Link Budget prediction report.

  • 6.6 ODU is grounded in accordance with Ceragon standard installation to the closed tower TGB.

  • 6.7 IF Cable/N Type connector assembled in accordance to manufacturer instruction.

  • 6.8 IF Cable/N Type connector connected to the ODU & sealed waterproofed with accordance to Ceragon instruction.

7. Outdoor-IF Cable & Connectors

  • 7.1 IF Cables are routed in accordance with Ceragon installation guide instruction.

  • 7.2 IF Cables are fastened with Cable Ties/Clamps across Tower ladders every 90cm.

  • 7.3 IF Cables dressing are done without any cable overlapping & crisscrossing.

  • 7.4 IF Cables are Earthed in accordance with Ceragon instruction.

  • 7.5 Lighting arresters in accordance with Country regulation.

  • 7.6 IF Cable connector assembled in accordance with manufacturer instructions.

  • 7.7 IF Cable connector is sealed & waterproofed in accordance with Ceragon guide instructions.

8. Site GND

  • 8.1 Site Main System[Tower&Shelter] to be measured with value of

  • 8.2 Tower is properly grounded to MGB[Main Terminal Ground Bar]

  • 8.3 Shelter is properly grounded to MGB[Main Terminal Ground Bar]

  • 8.4 Proper color is using for Ground cable[Yellow/Green]

9. Indoor-Installation

  • 9.1 19" Rack install in accordance with the room layout plan.

  • 9.2 19" Rack leveled.

  • 9.3 19" Rack TGB placed on bottom level,

  • If not please take a picture.

  • 9.4 19" Rack is Earthed to the MGB.

  • 9.5 PDU in place & positioned[Top of the Rack]

  • If not please take a picture.

  • 9.6 PDU is Earthed to the 19" Rack TGB?

  • 9.7 PDU Circuit breaker fuses are available for Ceragon equipment?

  • If not please take a picture.

  • 9.8 PDU Circuit breaker fuses suitable to Ceragon equipment power consumption.

  • If not please take a picture.

  • 9.9

  • 9.10 IDU is located in a proper ventilated environment?

  • 9.11 IDU is Earthed to the 19" Rack TGB.

  • If not please take a picture.

  • 9.12 IDU ground cable is routed properly inside the 19" Rack.

  • 9.13 Type of IF Cable that used on site?

  • 9.14 IF Cable are routed in accordance with Ceragon guide installation instruction.

  • 9.15 IF Cable labeled in accordance with Customer instructions.

  • 9.16 IF Cable/N Type connector assembled in accordance to manufacturer instructions.

  • 9.17 IF Cable/N Type connectors are properly connected to the IDU.

  • 9.18 Power connector is properly connected to the IDU.

  • 9.19 Power connector labeled in accordance with Customer instructions.

  • 9.20 IDU power cable is routed properly inside the 19" Rack.

  • 9.21 E1 Cables are properly routed.

  • 9.22 E1 connector is properly connected and tied to the IDU.

  • 9.23 E1 connector is properly connected and tied to the Protection Panel.

  • 9.24 E1 cable is terminated to the DDF and following standard color code.

  • 9.25 E1 cable label done as per Customer instruction.

10. Commission

  • 10.1 Equipment staged and per configured.

  • 10.2 Equipment power up.

  • 10.3 RFU's frequency is configured in accordance to the Link calculation[PL4]

  • Please enter the frequency:<br>

  • 10.4 Output power is configured in accordance to the Link calculation[PL4]

  • 10.5 Expected RSL level compared to the Link calculation, deviation recommended +/-3DBm.

  • Please enter the value:<br>

  • 10.6 IP Address is configured in accordance to the IP Plan.

  • Please enter the IP:

  • 10.7 License throughout loaded.

  • 10.8 NMS connectivity.

  • 10.9 Traffic/Transmission is configured in accordance to the Transmission plan.

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.