Title Page

  • Site Name

  • Conducted on

  • Prepared by

  • Location
  • SWARCO Inspector:

  • Date:

  • SWARCO Personnel:

  • Subcontractors:

  • Client:

Intake Equipment:

  • Is the service cable in good condition?

  • Is the service cable adequately supported?

  • Is the fuse carrier & Meter sealed?

  • Is the service head in good condition?

  • Are the meter tails adequately supported?

  • Are the meter tails less than 3m long?

  • Are the tales protected solely via the DNO Fuses

Solar PV:

  • Isolator present to isolate PV from public supply?

  • Warning label to show 2 sources of supply?

  • Are the AC & DC isolators in good condition?

  • Is there a single-line diagram showing the installation?

  • Are all cables correctly supported?

TT / Earthing:

  • Is the earthing conductor suitable? (Copper Rod / Tape)

  • Is the termination to earth electrode protected against corrosion?

  • Is the termination to earth electrode reliably secured?

  • Is TT Earthing Required for this install?

  • Is the earthing connection label fitted at the electrode?

  • Is the earthing connection label fitted at the MET?

  • Is the earthing connection label fitted at cross-bonding locations?

  • Is the MET / Earth bar in good condition?

Feeder Pillar:

  • Is the consumer unit fixed correctly?

  • Is the lid to the consumer unit fitted correctly?

  • Are all the blanks fitted?

  • Is the top of the consumer unit rated to IP4X?

  • Is the side & bottom of the consumer unit rated to IP2X?

  • Are rubber closed grommets used? Can they be removed to allow access to live parts without the use of a tool?

  • Are the blanks fitted tight and correctly fitted?

  • Is the consumer unit in good condition?

  • Does the RCD trip when the test button is used?

  • Are the circuits correctly labelled?

  • Is the RCD Test notice present?

  • Is the next inspection label present?

  • Is there a Circuit schedule?

  • Are the cable ducts sealed to prevent rodent entry?

  • Is the feeder pillar locked?

Chargers:

  • Are the chargers correctly fixed?

  • Are the chargers Level?

  • Are the chargers operational?

  • Are the chargers in good condition?

  • Are the chargers identified?

  • Are Barriers / Wheel stops installed?

  • Are the chargers accessible?

Car Park:

  • Is the area clear from construction debris?

  • Are the bay lines installed?

  • Are the spaces the correct size?

  • Is the tarmac/concrete from trenching level with the finished surface?

  • Is all signage installed?

Touch Potential (Not required if o-pen device is used)

  • Is any street furniture located within 2m of the charger? (fed via another power source than the charger)

  • Is any street furniture located within 2m of the Feeder Pillar? (fed via another power source than the charger)

  • Is any street furniture located within 2m of the EV whilst on charge? (fed via another power source than the charger)

  • Are there any other exposed conductive parts or extraneous conductive parts within 2m of the charger?

  • Are there any other exposed conductive parts or extraneous conductive parts within 2m of the Feeder Pillar?

  • Are there any other exposed conductive parts or extraneous conductive parts within 2m of the EV Whilst on Charge?

Site Photos

  • Photo of whole install

  • Photo inside of feeder pillar

  • Photo inside charger (Showing connections)

  • Photo inside DB

  • Photo of Signage

Certification

  • Has the correct certificate been provided? (EIC / Minor Works)

  • Is the Client & Site address correct?

  • Is the correct installation listed E.G. 2 X Raption 150s (Not 2 X EV Chargers)

  • is the correct new installation/addition to the existing install listed?

  • Is the Regulation amendment date correct on the certificate?

  • is the correct earthing system ticked?

  • is the nature of the supply parameters & protective device completed in full? (No N/A should be listed in any of these boxes)

  • Is the maximum demand listed?

  • is the main protective conductors completed correctly?

  • Are the R1+R2 readings calculated? These should not be calculated unless cables are installed within a DSEAR / ATEX area:<br><br>The R1+R2 should be around the calculated figure but are unlikely to all be the exact calculated figure, to calculate the figure find the ZE of the site (normally on page 1 within the supply details section) then<br>minus the ZS value of the circuit, normally shown on the 4th box from the right on the results page. ZE‐ZS= R1+R2.

  • Are all signatures correct?

  • Are all test results correct & comply with BS7671

Signed:

  • Date:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.