Title Page
-
Site Name and Building name
-
Conducted on
-
Prepared by
-
Location
-
-
Is DC cable roughed in from the roof to inverter location in HD conduit as Per AS5033
-
Is AC Cable roughed in from Inverter Location to Switchboard
-
Are Solar framing footing installed i.e L feet, Klipok or Tilt legs
-
Are rails fixed to footings
-
Are joiners and earthing lugs installed
-
Solar Panel Make and Model
-
How many panels are installed
-
Are panels mid and End Clamps secured
-
How may roof top isolators are installed
-
What is the make and model of the inverter
-
Does Inverter have minimum clearance for Heat Dissipation as per inverter's installation manual
-
Is both AC and DC cables fit off to inverter terminals
-
Is AC Cable from inverter fit off to the Switchboard
-
Is system larger then 30kWp
-
Is Grid Protection relay installed at MSB
-
Is Relay wired to Solar Circuit Breaker / Contractor
-
Is relay tripping contractor when it should be
-
Has commissioning been completed as per the Clean Energy Councils commissioning checklist